$5.5 Million Approved to Begin Edgewater Park Construction
11/23/26 – On November 12, 2026, Harris County Commissioners Court approved a $5.5 million contract to begin construction of Edgewater Park. See Item 330 on the agenda.
After Hurricane Harvey, Harris County purchased large swaths of land along the north side of the San Jacinto West Fork east of US59 to build a park – the first good thing to come out of Harvey. The County hoped to start construction in 2021. However, they delayed it because of pushback from Forest Cove residents, City of Houston Permitting, and redistricting in county government. The County also held public input sessions to determine exactly what residents wanted for the area.
Finally, in 2025, Harris County Precinct 3 Commissioner Tom Ramsey PE announced that development of the park was restarting. New plans finally went out for bid in mid-2026. Dozens of contractors registered to bid. And earlier this month, the County awarded the job to Times Construction based on “best overall proposal.”
First of Three Phases Starting in January
According to Eric Heppen, Ramsey’s Director of Engineering, Phase 1 construction should take around nine months. “We anticipate that Phase 1 will start construction in January. With the award recently completed, the contractor will go through final bonding. Then the county will generate a purchase order.”
Plans for Phase 1 were permitted as part of a larger set that includes plans for two additional phases. They include a public boat ramp, a parking lot, playground, trails, restrooms, and four detention basins (two large and two small).
Grants from Texas Parks and Wildlife
“The phasing maximizes usage of grants from Texas Parks and Wildlife Division (TPWD). We anticipate that both phases 2 (east side) and 3 (boat launch) will go out for bid in the next 12 months,” said Heppen. “We will actually bid the boat launch (Phase 3) before we bid the east side (Phase 2) based on our current projection of grant needs.”
Phase 1 includes all of the detention needs for Phases 2 and 3. Plans show four detention basins. Building those first ensures the county will not add to flooding during construction.
Ponds and wetlands lace the area. Plans show park amenities thoughtfully placed around them.
Next Steps
The park will eventually connect to the West Fork Greenway and Spring Creek Trailhead, making it a critical link in one of the longest urban trail networks in North America.

The playground in the upper right of the plans will be constructed in a future phase. But that area is being cleared in Phase I to provide access for contractors and a staging area for their equipment.
Here’s what that same area looks like from the air.

Currently, the County does not plan to develop any of the land north of Hamblen that it owns adjacent to the area you see above. That area includes a large, environmentally sensitive cypress pond.

Looking E toward large cypress pond north of Hamblen. File photo from 2023.
Posted by Bob Rehak on 11/23/2026