Commissioners Approve Excavation Contract for Regional Detention Pond on Taylor Gully

In yesterday’s Harris County Commissioners Court meeting, commissioners unanimously approved a contract with Spring Sand & Clay LLC for excavation of a regional detention pond on Taylor Gully in Montgomery County at the Woodridge Village site.

Preliminary Engineering Began in Early July

Earlier this year, Harris County purchased Woodridge Village from Perry Homes for this purpose. Currently, engineers are examining several Taylor Gully alternatives.

Woodridge Village
Looking north across Woodridge Village toward Porter from over the Harris/Montgomery County line. The abandoned development currently has five detention ponds that will hold about 60% of the rain in an Atlas-14 100-year storm.

Currently, Idcus, Inc., an engineering company, has been contracted to look at:

  1. Whether existing detention and proposed channel improvements would suffice to mitigate flooding
  2. Whether expanding existing detention would eliminate the need for channel improvements
  3. A combination of the two scenarios above – determining the amount of additional detention and channel improvements necessary to ensure no adverse impact all the way to Lake Houston.
  4. Out-of-the-box alternatives that ensure no adverse impact while maximizing flood mitigation and minimizing construction costs.

The Idcus contract calls for the company to deliver channel and basin layouts for Taylor Gully no later than 300 days from the notice to proceed, which presumably was given in early July. However, excavation could start much sooner than that. (See below.)

Pieces of Puzzle Falling into Place

The no-cost contract with Sprint lets them set their own timetable as long as they complete improvements within three years. Sprint’s timetable will be driven by the company’s ability to sell the material they excavate; that forms their compensation.

The next step is for Harris County Flood Control District (HCFCD) to provide a grading plan to the contractor. While that will not happen tomorrow, the good news is that it won’t require waiting 300 days.

HCFCD can start excavating the retention pond before plans are finalized. After all, it’s not a problem if a detention pond holds more than the minimum required. It’s only a problem if it holds less. Engineers and contractors can adjust plans if necessary after excavation starts. This approach should minimize flood risk for worried Elm Grove and North Kingwood Forest residents.

All the pieces of the puzzle are starting to fall into place.

Posted by Bob Rehak on 7/21/2021

1422 Days since Hurricane Harvey

Commissioners Vote Tuesday on Contract for Woodridge Village Detention Pond Excavation

Tuesday, 7.20.21, Harris County Commissioners will vote on a contract with Sprint Sand & Clay for excavation of a Woodridge Village detention basin. Item #21-3394 on the agenda is only for $1000, but it gives the contractor the right to enter the site and begin removing up to 500,000 cubic yards of dirt (at no cost to HCFCD) which it can then sell.

Backup provided to commissioners states that “This benefits the District because excavation and removal is always the highest cost of any stormwater detention basin that is constructed.”

Details of Proposed Contract

Here is the full text of the proposed agreement. Highlights include:

  • Amount of excavation TBD – somewhere between 20,000 and 500,000 cubic yards, depending on plans that HCFCD will deliver to the contractor based on the outcome on an engineering study currently underway.
  • The contractor must properly dispose of the spoils, which it is allowed to sell to make its money on the contract.
  • Contractor is liable for any materials that are disposed of improperly, i.e., within Base Flood Elevation or the 500-year flood plain and must identify all disposal locations.
  • Time allowed: 3 years.
  • Termination of contract possible if contractor fails to excavate a minimum average of 5,000 cubic yards every month.
  • Contractor responsible for environmental mitigation if necessary, excluding wetlands.
  • The contractor must provide an approved Stormwater Pollution Prevention Plan and abide by it.

The contract outline contains the map above but does not specify the exact size, depth or location of the proposed work within the outlined area – just that it will occur in Montgomery County. Engineers will supply additional details at a later date.

Making up for the 60% Solution

Assuming commissioners approve this, it is good news for the people who live who live in Elm Grove and North Kingwood Forest – indeed, for everyone who lives along Taylor Gully. The detention ponds installed by Perry Homes before they sold the land to Harris County were based on old rainfall statistics and will only hold about 60% of a new 100-year rain defined in Atlas-14.

Looking SE across Woodridge Village toward Elm Grove and North Kingwood Forest, areas where hundreds of homes flooded badly in 2019 twice. Photo taken May 26, 2021.

Sprint Sand and Clay is a regular contractor for HCFCD. Currently, the company is excavating the massive Cutten Detention Basin near 290, Beltway 8 and Cutten Road.

Posted by Bob Rehak on 7/20/21