April 7 Meeting on Spring Creek Flood Control Dams

Spring Creek Flood Control Dams are back in the news. The San Jacinto River Authority (SJRA) recently announced the first of three meetings related to a feasibility study. So save the date – April 7.

According to Matt Barrett of the SJRA, this feasibility study is a continuation of the Spring Creek Siting Study which came out of the San Jacinto Regional Watershed Master Drainage Plan project (SJMDP). The Harris County Flood Control District (HCFCD) and multiple partner agencies including SJRA developed the Master Drainage Plan. 

Overview of Feasibility Study 

The Spring Creek Siting Study from December 2020 explored multiple alternative locations that could provide flood-mitigation benefits to the Spring Creek watershed. Two of the more cost-effective were dams on Walnut and Birch Creeks.   

The Spring Creek Flood Control Dams Feasibility Study will include:

  • A conceptual design for each dam
  • Benefits and costs for each dam and a combination of the two dams.  

The goal: to determine the most feasible and economical alternative(s) for possible future design and construction. 

The cost of the study is estimated at $1 million. The Texas Water Development Board (TWDB) Flood Infrastructure Fund (FIF) grant program will provide half.  City of Humble, HCFCD, and five (5) Municipal Utility Districts will fund the other half.  SJRA is performing in-kind services to reduce the local match amount to be funded by the Partners. 

One Crucial Step of Many

This project is currently only in the feasibility phase. Construction of one or both dams, if feasible, would likely not occur for several years. Partners still need to identify a project sponsor and funding. They also need to perform final design, obtain environmental permits, and acquire land.

Details of Public Input Meeting

Public input and participation are critical components of this study, and SJRA wants to hear from you.  A public meeting related to the study will be held on/at the following date and location:

Thursday, April 7, 2022 

6:00 p.m. to 8:00 p.m. 

Fields Store Community Center 

26098 FM 362 

Waller, Texas  77484 

The meeting will be in an open-house format, allowing members of the public to come and go at their convenience at any time between 6:00 p.m. and 8:00 p.m.  A five-minute, high-level, project-summary presentation will be given at 6:00 p.m., 6:30 p.m., 7:00 p.m., and 7:30 p.m.  

Between these presentations, project team members will answer questions and collect input.  If you can’t attend in person, you can view the summary presentation on SJRA’s Facebook page following the meeting. You may also submit questions via email and the project team will answer them. 

Project Location

Below, see preliminary maps.  These project areas could change based on the results of study efforts. 

The proposed Spring Creek Flood Control Dams would lie in far northeastern Waller County, a few miles west of Magnolia in Montgomery County.

The next map shows parcels of land that partners would need to acquire to develop the project(s).

Preliminary map of Birch and Walnut Creeks flood control dams. Extent of inundation limits subject to change during study.
One more public engagement meeting will be held this summer. The third will happen after partners release the draft report in February, next year.

Projected Benefits of Projects

As presently conceived, the Birch Creek dam could reduce water surface elevations by a half foot in a 100-year storm for almost 26 miles downstream. The larger Walnut Creek dam could produce a similar benefit for 41 miles downstream.

Each would cut the annual chance of exceedance (ACE) in half for the people in the affected areas. Thus, a hundred year storm would only have the impact of a 50-year storm.

Barrett currently estimates that the Birch Creek Dam could remove 815 structures from the 100-year floodplain and the Walnut Creek Dam could remove 1205. However, he also points out that those numbers will likely change as a result of updated modeling in the current study now underway.

How much would these dams benefit people in the Lake Houston Area? Barrett admits the impact would be small that far downstream. But he also points out that these represent the first two of 16 similar projects proposed in the Master Drainage Plan, and that they could have a major cumulative impact.

Every little bit helps. Even if you can’t attend the meeting, I hope you submit a public comment via email in support of the project.

How to Learn More and Provide Public Comment

For a fact sheet on each of the two proposed dams, click here.

For more information about the Spring Creek Flood Control Dams Feasibility Study, please visit www.SpringCreekStudy.com.

You can submit comments at the public meeting and throughout the duration of the study. Email comments to floodmanagementdivision@sjra.net, or submitted online at www.SpringCreekStudy.com

Posted by Bob Rehak on 3/18/2022

1662 Days since Hurricane Harvey

SJRA Board Accepts Grant Funding for Three Studies

Yesterday, the San Jacinto River Authority (SJRA) Board accepted three grants from the Texas Water Development Board (TWDB) to conduct studies for various projects. This was expected. The SJRA had applied for each of the grants about a year ago. The vote, however, now obligates the SJRA. It’s somewhat like applying for a loan and then signing the contract after it is approved.

Three Studies Now Teed Up

The SJRA and its partners can now officially start three studies:

  • An upper San Jacinto Watershed regional sedimentation study
  • A conceptual engineering feasibility study for flood-control dams in the Spring Creek Watershed
  • A joint reservoir operations study between Lake Conroe and Lake Houston
Lake Houston Gates can discharge only 10,000 CFS (left), while Lake Conroe’s can discharge 150,000 CFS. To help provide better watershed management, the Coastal Water Authority is studying the addition of 1000 crest gates to Lake Houston, necessitating the joint reservoir operations study.

Why Flood Mitigation Takes So Long

We are all learning together how long flood mitigation takes. It’s somewhat frustrating to see a conceptual engineering feasibility study being kicked off one month from the fourth anniversary of Hurricane Harvey.

I’m not pointing fingers at the SJRA, its partners, the TWDB, or the State. If you took the time to read all of the approximately 1500 posts on ReduceFlooding.com, you would see that:

  • Harvey happened right after the 2017 legislature finished its work.
  • Eighteen months elapsed before the legislature met again.
  • It took another nine months for the legislature and governor to approve flood mitigation funding.
  • Then, the TWDB needed to define rules for the distribution of funds, solicit public comment, refine the rules, solicit grant applications, and evaluate them in a competitive context.
  • Finally, add time for related preliminary studies such as the Lake Houston Spillway Improvement Project, the San Jacinto River Basin Master Drainage Study, a sand trap study, and a siting study for the flood-control dams.
  • And don’t forget the time to find partners and develop political consensus around solutions.

Still Years from Construction

The truly scary thing is that even when these studies are completed, we still could be years from construction and more years from completion of any of these projects.

For instance, we just started final engineering on the Lake Houston Spillway Improvement Project. Best-case projections show completion of the project in mid 2024 – 7 years after Harvey.

The system seems set up to protect money more than people. We certainly don’t want people rushing off, building half-baked projects that endanger people downstream, the environment, or the safety of a dam…especially if they produce no demonstrable benefit.

But we also don’t want people to flood multiple times waiting for flood-mitigation improvements. And some have. Remember Imelda? Just a thought as we head into the heart of hurricane season.

Studies Could Take 18 Months to 4 Years

The Spring Creek Flood-control Dam study will take 18 months. The Joint Reservoir Operations Study will take 3 years. And the Sediment Study is scheduled to take 4 years, though Matt Barrett, SJRA’s flood-mitigation director, is trying to compress that to 18 months.

If you missed the original post about these three studies, you can find more details here. SJRA partners in these projects include Harris County Flood Control, City of Houston, City of Humble, Montgomery County and five utility districts.

Posted by Bob Rehak on July 23, 2021

1424 Days since Hurricane Harvey and 673 since Imelda

SJRA to Consider Three Flood-Mitigation Studies Thursday

SJRA directors will consider accepting grant funding for three flood-mitigation studies at their board meeting on Thursday, 7/22/21. The studies include:

  • A joint reservoir operations study between Lake Conroe and Lake Houston
  • An upper San Jacinto Watershed regional sedimentation study
  • A conceptual engineering feasibility study for flood-control dams in the Spring Creek Watershed

The board will also consider executing escrow agreements related to each grant. TWDB grants work on a reimbursement basis. At the start of the project, TWDB puts the grant money into an escrow account. Then funds are drawn down as vendors submit invoices and TWDB approves them.

I posted previously about grant applications for these projects. Now that the grants have been approved, work can actually begin once the board agrees to accept the money. See details below about each project.

Joint Reservoir Operations Study

The addition of 1000-feet of crest gates to the Lake Houston Dam is a game changer for the way reservoirs on the San Jacinto work together. Right now, the gates on Lake Houston have a discharge capacity of only 10,000 cubic feet per second (CFS). The discharge capacity of the crest gates would increase that by more than 4X to 45,000 cfs. It’s still not the 150,000 CFS of Lake Conroe gates, but percentage-wise it’s much closer.

Thus, operators need to re-examine how best to synchronize their operations and plans. For instance, pre-releasing water in advance of a storm might be more viable now as a flood-mitigation strategy.

Another element of this study is a “flow forecasting tool.” It would predict rises in Lake Houston depending on the flow rates in tributaries during major storms. Matt Barrett, SJRA’s flood-mitigation director, says this tool could be useful for flood warnings and evacuations. If you knew that lake water would rise X feet in Y hours, and that your slab was a foot below X, you’d know exactly how much time you had to pack up your valuables and get out.

This study is being conducted with help from the Cities of Houston and Humble.

Upper San Jacinto Basin Sedimentation Study

The upper basin of the San Jacinto River includes everything above Lake Houston. This study has three goals:

  • Understand where the sediment is coming from
  • Learn where it ends up
  • Develop a management plan to handle it.

For the record, here is the scope of work. Note that stakeholder input and public meetings will be a big component of this project (Task 2). Tasks 3 and 6 include evaluation of sand mines. And Task 7 includes “Sand and Gravel Mining Best Management Practices.”

The San Jacinto West Fork has more than 20-square miles of sand mines in the 20-mile stretch between I-69 and I-45, exposing a swath of sediment averaging a mile wide.

The sedimentation study is being conducted with financial help from the Cities of Houston and Humble, and the Harris County Flood Control District.

A related sand-trap study is nearly complete. The SJRA should release it next month for public input.

Spring Creek Flood Control Dam Feasibility Study

About a year ago, SJRA applied for a TWDB grant to study the feasibility of building two flood control dams in the upper Spring Creek Watershed. The partners identified two preferred locations from a previous siting study that considered dozens. The two included Walnut and Birch Creek tributaries.

The objective now: to see whether the benefits justify the costs. Said another way, will the dams reduce flooding and protect enough structures to make the cost of building them worthwhile?

Together, they would have a combined capacity of 20,000 acre feet. That’s significant. But it would provide more benefit to people in the upper Spring Creek watershed than the Lake Houston Area.

The scope of work includes:

  • Environmental due diligence
  • Site investigations
  • Literature and mapping review
  • Permitting requirement investigations
  • Desktop surveys/assessments
  • Preliminary coordination with permitting agency
  • Conceptual design of dams to determine feasibility – geotechnical borings, alternative configurations development, H&H modeling analysis, etc.
  • Cost estimate development – dam construction costs, as well as costs related to land acquisition, utility conflicts and relocations, environmental mitigation, O&M, etc.
  • Update benefit/cost ratios (BCR) from SJRWMDP using data developed as part of this effort.

Partners in this effort include the SJRA, HCFCD, City of Humble, and five municipal utility districts. To learn more about these projects and others, consult pages 19 and 21 of this PDF.

To View or Participate in the Board Meeting

The SJRA board meeting starts at 8am.

If you choose to participate via webinar, register at this link and use webinar ID 950-202-179.

If you use the GoToWebinar App, you will have the opportunity to provide public comments.

To view the Agenda, visit SJRA’s website at: 07-22-21 Agenda and Coversheets.

Posted by Bob Rehak on 7/22/21

1423 Days after Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Harris County Commissioners Approve Two Projects That Could Benefit Humble-Kingwood Area

Harris County Commissioners Court unanimously approved two items on today’s agenda that could eventually benefit the Humble/Kingwood Area.

  • #60 Recommendation to execute a Partnership Agreement with TXDoT for preliminary engineering and environmental review for a railroad grade separation on Hamblen Road, from Loop 494 to Laurel Springs Lane.
  • #83 Authorization to negotiate an interlocal agreement for a partnership project with the SJRA, Humble, and five utility districts for a feasibility study and conceptual design on the Spring Creek Watershed Flood Control Reservoirs.

Consideration of the projects was originally scheduled for last Friday. But visits by President Biden and Governor Abbott delayed that part of the meeting until today.

More About the Projects

The first item will formally establish a partnership with TXDoT to study the feasibility of rerouting Hamblen Road north to meet up with a bridge over US59 at Sorters-McClellan Road. The project, is key to managing traffic in Harris County’s new 90-acre Precinct 4 Edgewater Park. The preliminary engineering study will also look at building a bridge over the Union Pacific Railroad tracks. The latter is important because UP has announced its intention to start running longer trains. If one derailed, it could theoretically block every exit to Kingwood.

Site of Precinct 4’s new Edgewater Park. Hamblen Road (center) could be re-routed north to connect with the bridge over 59 at Sorters-McClellan road (top center). The project could also create a railroad bridge over the Union Pacific tracks (right).

The second item will further explore the feasibility of one or more Flood Control Reservoirs upstream from the Lake Houston Area along Spring Creek. This could reduce the amount of inbound water during future floods. In that regard, it is worth noting that the amount of water coming down Spring Creek during Harvey almost exactly equaled the amount of the SJRA’s release from Lake Conroe. Thus, such a project could partially offset future Lake Conroe releases during floods.

San Jacinto River Watershed Flow Rates
Where Water Came From During Harvey. Source: SJRA.

Next Steps

Neither of these projects involves approval to begin construction. They simply will study the feasibility, locations, costs, and nature of construction. Commissioners would have to approve construction after studying the results of the studies. But first the engineering department and Flood Control District must solicit bidders to conduct the studies.

Posted by Bob Rehak on 3/1/2021

1280 Days since Hurricane Harvey

TWDB Advances 4 of 5 SJRA Grant Applications for Flood Infrastructure Funding

The Texas Water Development Board (TWDB) has advanced four of five San Jacinto River Authority (SJRA) abridged grant applications to the next round for consideration. TWDB named them as priorities for the 2020 Flood Infrastructure Fund (FIF) cycle. That advances SJRA one step closer to funding for the projects. 

SJRA Now Invited to Submit Full Applications


With these rankings, SJRA will now submit full grant applications for four projects for approval. In the two-stage process, applicants first submit an abridged application. TWDB then prioritizes them within the overall available funding capacity. 

Senate Bill 7 last year made the Flood Infrastructure Fund (FIF) possible. Senator Brandon Creighton sponsored it. The Legislature passed it and Texas voters approved it through a constitutional amendment. FIF provides financial assistance in the form of loans and grants for flood control, flood mitigation, and drainage projects. 

Why SJRA Seeks Grants, Partnerships

As with most Texas river authorities, SJRA is not a taxing entity, therefore these large-scale flood mitigation projects require regional and local partnerships as well as grant funding.

“Hundreds of abridged applications were submitted by entities—cities, counties, other political subdivisions—as part of this competitive process. We are very proud SJRA was selected to move ahead in the approval process on four of our five abridged grant applications,” said Chuck Gilman, SJRA Director of Water Resources and Flood Management. “The next step is to find local partners who, along with SJRA, will commit to the local-match funding and in-kind services. These large-scale, impactful projects come with a very high price tag. It will take a regional approach with various funding commitments to see these projects through to completion. The FIF funding is an essential piece of that process.”

Flood Infrastructure Fund Criteria

According to Flood Infrastructure Fund criteria, eligible projects must fall under one of four categories:

  1. Flood Protection Planning for Watersheds
  2. Planning, Acquisition, and Design, Construction/Rehabilitation
  3. Federal Award Matching Funds
  4. Measures Immediately Effective in Protecting Life and Property

TWDB will review the full grant applications and make final selections for grant and loan funding later this year. 

SJRA

Proposed Projects Advancing to Next Round


Upper San Jacinto River Basin Regional Sedimentation Study 

Would identify and create a plan for implementing potential sedimentation solutions in the Upper San Jacinto River Basin (Lake Houston watershed). It would evaluate the input, output, and storage of sediment for the entire basin as well as for sub-watersheds.  

LMI River Bend Sand Mine on San Jacinto West Fork exposes more than 500 acres of sand to floodwaters. Altogether, sand mines expose approximately 20 square miles of sand along the West Fork to floodwaters in a 20 mile stretch between I-45 and US59.
Spring Creek Watershed Flood Control Dams Conceptual Engineering Feasibility Study 

Would perform a conceptual engineering feasibility study of two potential dam/reservoir locations within the Spring Creek watershed. This is the next phase of the Spring Creek Siting Study, which is currently being completed as part of the San Jacinto Regional Watershed Master Drainage Plan. Harris County Flood Control District leads the Master Drainage Plan effort. SJRA and other regional partners support it.

Lake Conroe – Lake Houston Joint Reservoir Operations Study 

Would develop a joint reservoir operations and communications strategy for Lake Conroe and Lake Houston. 
The City of Houston is currently studying new tainter gates for the Lake Houston dam. They could greatly increase the controlled release capacity. 

The main goal of the plan: to determine the most efficient and safe operation of the two reservoirs in series. The study would evaluate multiple individual components of a joint operational strategy. 

It will evaluate:

  • Operational synergy between the two reservoirs
  • Joint notification and communications protocols
  • Pre-release
  • Impacts on water supply
  • Use of forecasting tools.

This project will benefit both water supply and flood mitigation in the region.

Flood Early Warning System for San Jacinto County 

Would provide for installation of rain and river/stream gages at three locations identified as critical by San Jacinto County to provide early warning information to the county during storm events.  

Locations:

  • Winters Bayou at State Highway 150
  • East Fork San Jacinto River at FM 945
  • Peach Creek at FM 3081. 

Rain and river/stream stage data obtained at the sites would be transmitted to SJRA’s ALERT2 network and displayed on SJRA’s Contrail system. The data could be viewed online via SJRA’s website. That lets San Jacinto County staff and residents view the data at any time.

Not Advancing to Next Round

The SJRA had also submitted a first-round grant application to develop preliminary designs for sand traps. The sand traps were supposed to reduce the amount of sediment moving downstream. SJRA confirmed that this grant application will not move forward.

Posted by Bob Rehak on 9/24/2020 based on input from SJRA