But instead of deepening the channel, the next phase of dredging seems aimed at reducing the mouth bar itself.
Progress to Date in Reducing Mouth Bar
Aerial photos taken on 2/13/2020, show that to date DRC has removed most vegetation from the bar. They have also reduced the crown of the bar and flattened it to create a platform for excavator(s) that’s little more than a foot or so above the water. Parts of the bar used to stand four to five feet above water.
While two excavators worked on the scalping process Thursday, a third took bites from the edge of the bar, much like a human might nibble away at an ear of corn, row by row.
On Thursday, 2/13/2020, three excavators worked various portions of the mouth bar.Two were still leveling the bar and removing vegetation while a third whittled down the edges of the bar. The excavator near the water appears to be walking backward as it pulls sediment from in front of it and dumps it on the waiting pontoon.When the pontoon is full, a small tug pushes it upstream.
Placement Area for Sediment
Tugs push the pontoons upstream to Berry Madden’s property on the south side of the West Fork, just upstream from Kings Lake Estates, roughly opposite River Grove Park.
…through the back channels of the West Fork to Berry Madden’s property, the placement area. Photo courtesy of Josh Alberson.At Madden’s property, the sediment is offloaded.Photo courtesy of Josh Alberson.The tug will then take a pontoon back downstream for the next load.The sediment will then get loaded into dump trucks……and carried away from the river.
From the number of trucks on Madden’s property, it appears that DRC is using it as its command post for the operation.
Bulldozers then compact the dirt and spread it out.
Operational Tempo Expected to Increase
Josh Alberson, a local boater, monitors the dredging program. He says that the cycle time per pontoon load has decreased from roughly three hours to about two hours and twenty minutes.
Berry Madden, the placement area owner, says DRC has told him that it expects to add more equipment to the job by next week. That should increase the operational tempo and the volume of sediment transported each day.
Madden’s property is also permitted to receive spoils from hydraulic dredging.
The Harris County Engineering Department is managing this project with the City of Houston.
Next Steps Still Unclear
The Harris County Engineers office has not yet released plans for the remainder of the project. Several things remain unclear at this point. Key among them:
Why remove the mouth bar instead of deepening the channel in front of it?
Will the operation switch over to hydraulic dredging to speed up the project and reduce the flood-risk window?
What will the next steps be after completion of the West Fork?
Have the partners agreed on a maintenance dredging program?
The grant request submitted by the County to the TWDB indicates that the team also expects to tackle the rapidly growing East Fork mouth bar. During Imelda, boaters say the channel north of Luce Bayou silted in badly. It went from 18 feet deep to approximately 3 at the deepest point, they say.
Posted by Bob Rehak on 2/15/2020 with photos from Josh Alberson
900 days after Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/02/20200213-RJR_8078.jpg?fit=1200%2C800&ssl=18001200adminadmin2020-02-14 17:43:052020-02-14 18:00:29Take Down: West Fork Mouth Bar
As I flew over the site on 2/13/2020, men were removing two small bulldozers, the last pieces of equipment. Here’s how it looked from the upstream side.
The once bustling Army Corps Command Post for the Emergency West Fork Dredging Program after Harvey. Photo taken 2/13/2020.
Here’s how it looked from the downstream side.
Reverse angle of same location, looking west toward US59.
How Same Site Looked Three Weeks Ago
Less than a month ago, on my January 20th flyover, the site still bustled with activity. Demobilization was in full swing.
Army Corps Command Post on January 20, 2020.Looking East.Pieces of the Great Lakes dredge at the Army Corps Command Post on January 20, 2020.
They say, “It ain’t over till it’s over.” Well, I’d say that the Emergency West Fork Dredging program that started in 2018 is now over.
Altogether they removed approximately 2.3 million cubic yards of sediment clogging the West Fork that Hurricane Harvey deposited.
Grants from FEMA and the Texas Water Development Board, plus money from the 2018 Harris County Flood Bond fund the current program.
It uses mechanical, not hydraulic dredging equipment. The focus of activity is farther downstream closer to the West Fork Mouth Bar.
More on that in my next post.
Posted by Bob Rehak on February 14, 2020
899 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/02/20200213-RJR_7977-3.jpg?fit=1200%2C800&ssl=18001200adminadmin2020-02-14 10:39:202020-02-14 10:41:06Corps, Contractors Vacate Old Dredging Command Post, Demobilize
Photo taken 2/12/2020 on West Fork San Jacinto from helicopter.
While photographing the West Fork from a helicopter Thursday, I saw something large from the corner of my eye. I looked up and was treated to a magnificent sight – a bald eagle in flight … right beside us. I quickly zoomed my lens out to 300mm and snagged this air-to-air shot.
We were in the vicinity of the Romerica property just downstream from River Grove Park. You may remember a year ago that two developers from Mexico wanted to build 500-foot high-rises right next to the river. The community rose up in protest. One of the biggest concerns: the effect on bald eagles nesting in the area.
The company reserved the right to refile in the future. In the meantime, it appears that the eagle(s) living there have no intent to move.
The Herons Kingwood recently took down its website. However, the domain name is still registered. I have contacted the agent for the company to inquire about the project’s status. Emails have not yet been returned.
Posted by Bob Rehak on 2/13/2020
899 Days after Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/02/EagleInFlight.jpg?fit=1200%2C818&ssl=18181200adminadmin2020-02-13 21:38:512020-02-13 22:00:46Bald Eagle Sighted Over Romerica Property
Take Down: West Fork Mouth Bar
DRC (Disaster Recovery Corporation) excavators are slowly whittling down the mouth bar of the West Fork of the San Jacinto. DRC is picking up where the Army Corps and Great Lakes Dredge and Dock left off around Labor Day last year. The Corps and Great Lakes removed 500,000 cubic yards of sediment. DRC will remove another 400,000 in 8-12 months as part of its contract.
DRC Focus Differs from Corps’ So Far
The Corps effort focused on deepening the channel between the mouth bar and Atascocita Point. DRC’s effort appears to focus on reducing the mouth bar itself.
A survey conducted after the Corps finished in September showed they had reduced the average depth in front of the mouth bar to about 5.5 feet. Local residents including high-level geologists questioned whether that was enough to restore safety. They pointed out that the river upstream of the mouth bar had been dredged to more than 25 feet and worried that the 20 feet difference would partially dam the river during floods and create a backwater effect that contributed to flooding.
Progress to Date in Reducing Mouth Bar
Aerial photos taken on 2/13/2020, show that to date DRC has removed most vegetation from the bar. They have also reduced the crown of the bar and flattened it to create a platform for excavator(s) that’s little more than a foot or so above the water. Parts of the bar used to stand four to five feet above water.
While two excavators worked on the scalping process Thursday, a third took bites from the edge of the bar, much like a human might nibble away at an ear of corn, row by row.
Placement Area for Sediment
Tugs push the pontoons upstream to Berry Madden’s property on the south side of the West Fork, just upstream from Kings Lake Estates, roughly opposite River Grove Park.
From the number of trucks on Madden’s property, it appears that DRC is using it as its command post for the operation.
Operational Tempo Expected to Increase
Josh Alberson, a local boater, monitors the dredging program. He says that the cycle time per pontoon load has decreased from roughly three hours to about two hours and twenty minutes.
Berry Madden, the placement area owner, says DRC has told him that it expects to add more equipment to the job by next week. That should increase the operational tempo and the volume of sediment transported each day.
Madden’s property is also permitted to receive spoils from hydraulic dredging.
The Harris County Engineering Department is managing this project with the City of Houston.
Next Steps Still Unclear
The Harris County Engineers office has not yet released plans for the remainder of the project. Several things remain unclear at this point. Key among them:
The grant request submitted by the County to the TWDB indicates that the team also expects to tackle the rapidly growing East Fork mouth bar. During Imelda, boaters say the channel north of Luce Bayou silted in badly. It went from 18 feet deep to approximately 3 at the deepest point, they say.
Posted by Bob Rehak on 2/15/2020 with photos from Josh Alberson
900 days after Hurricane Harvey
Corps, Contractors Vacate Old Dredging Command Post, Demobilize
The Emergency West Fork Dredging Program started by the Army Corps of Engineers in May of 2018 is now virtually done with demobilization. In the last month, the Army Corps and its contractors have vacated the old command post they established on the south side of the San Jacinto West Fork opposite Forest Cove. They have removed the remaining pieces of the Great Lakes dredge, dredge pipe, booster pumps, construction trailers, cranes and more.
Nothing Remains But Sand and Memories.
As I flew over the site on 2/13/2020, men were removing two small bulldozers, the last pieces of equipment. Here’s how it looked from the upstream side.
Here’s how it looked from the downstream side.
How Same Site Looked Three Weeks Ago
Less than a month ago, on my January 20th flyover, the site still bustled with activity. Demobilization was in full swing.
They say, “It ain’t over till it’s over.” Well, I’d say that the Emergency West Fork Dredging program that started in 2018 is now over.
Altogether they removed approximately 2.3 million cubic yards of sediment clogging the West Fork that Hurricane Harvey deposited.
Moving On to Next Phase of Dredging
This, however, does not affect the current mouth bar dredging program. That is a separate effort mounted by the State of Texas. Harris County and the City of Houston.
Grants from FEMA and the Texas Water Development Board, plus money from the 2018 Harris County Flood Bond fund the current program.
It uses mechanical, not hydraulic dredging equipment. The focus of activity is farther downstream closer to the West Fork Mouth Bar.
More on that in my next post.
Posted by Bob Rehak on February 14, 2020
899 Days since Hurricane Harvey
Bald Eagle Sighted Over Romerica Property
While photographing the West Fork from a helicopter Thursday, I saw something large from the corner of my eye. I looked up and was treated to a magnificent sight – a bald eagle in flight … right beside us. I quickly zoomed my lens out to 300mm and snagged this air-to-air shot.
We were in the vicinity of the Romerica property just downstream from River Grove Park. You may remember a year ago that two developers from Mexico wanted to build 500-foot high-rises right next to the river. The community rose up in protest. One of the biggest concerns: the effect on bald eagles nesting in the area.
The US Fish and Wildlife Service wrote a scathing letter urging the Corps to deny Romerica’s application to fill in wetlands.
After 770 more letters of protest to the Corps, the Corps withdrew Romerica’s permit application.
The company reserved the right to refile in the future. In the meantime, it appears that the eagle(s) living there have no intent to move.
The Herons Kingwood recently took down its website. However, the domain name is still registered. I have contacted the agent for the company to inquire about the project’s status. Emails have not yet been returned.
Posted by Bob Rehak on 2/13/2020
899 Days after Hurricane Harvey