The 3/9/2021 meeting of Harris County Commissioners Court started with a presentation by the Harris County Budget Management Director David Berry on the County’s Capital Improvement Plan. Mr. Berry asserted early in the meeting that the County had a shortfall of approximately $900 million to $1.35 billion needed to complete projects in the Flood Bond passed by voters in 2018. Is there really a shortfall? It depends on the exact way you phrase any number of possible questions.
Confusing, Unexplained Map Triggers Almost 2 Hours of Discussion
Near the start of the meeting, Mr. Berry put up a very confusing map (below) that frequently heated the next 100 minutes of discussion to the boiling point. The discussion made every front page in town and many of the TV news shows.
The map showed the projected funding shortfalls by watershed as a percentage of the total funding allocated to each in the 2018 flood bond.
The stories featured sensational quotes by Precinct One Commissioner Rodney Ellis (We will have blood on our hands if this stands.) and Precinct 2 Commissioner Garcia (I feel like someone hit me across the back with a baseball bat.)
The map implied that construction had started on projects that the County did not have enough money to finish, especially the ones in yellow and red below.
Map from Page 16 of Harris County CIP Budget for Fiscal Year 2021/2022.
Was Flood Control Not Following Equity Guidelines?
To add more context to this discussion, understand that Halls and Greens Bayous rank among the poorest in the county. That they seemed so far behind more affluent watersheds in funding rankled Ellis and Garcia. The two had argued to prioritize flood bond spending by a “social equity” formula that addressed the poorest neighborhoods first. To say that the map above was like waving a red flag in front of two bulls would understate its effect.
So What’s Really Going on Here?
Did prices of flood-bond projects suddenly escalate, causing the shortfall? No.
Did Flood Control underestimate costs? No.
The reason has to do with the delayed arrival of long-awaited federal matching funds.
But Berry did not make that apparent in his setup. Commissioners Garcia and Ellis then peppered Russ Poppe, head of the Flood Control District, with angry, accusatory questions for more than 40 minutes. At one point, they asked 11 questions in a row before they gave Poppe a chance to answer one.
Poppe then explained that Flood Control relies on matching funds from the U.S. Department of Housing and Urban Development (HUD) for low-income areas. Why? Unlike FEMA which requires a positive benefit/cost ratio, HUD does not. Flood Control is currently waiting for answers on HUD grant applications totaling almost half a billion dollars for mitigation work in the Halls and Greens Bayou watersheds.
Commissioners Court then spent another 40 minutes trying to understand the chances of getting those grants. They also crafted a motion directing the Flood Control District to develop a backup plan in case grant money didn’t arrive by June 30.
Text Of Motion
The motion reads as follows: “To direct the Flood Control District to work with Budget Management in developing a plan by June 30, 2021 to address the funding gap in flood mitigation projects under the 2018 bond while maintaining an equitable approach to the expenditure of funds, including plans to lobby federal, state, and local partners for funding, identification of alternative funding options, a description of projects that are currently stalled due to incomplete funding and how that affects timing of project completion, and a potential timeline for a future potential bond election regarding the funding of current and future flood control projects. If the County is unable to secure funding to complete all proposed projects, the plan should address how the County should prioritize the investment of existing resources to ensure equitable flood protection and comply with the prioritization framework adopted by Harris County.”
The motion eventually passed unanimously at 1 hour and 32 minutes into the meeting.
Answers to Questions About “Underfunding”
Is construction money in Halls or Greens Bayous invested so far at risk?
No. Money spent so far, according to Poppe, has only been for land acquisition and preliminary engineering studies. The County will need both regardless of how it pays for construction. So the County didn’t waste a penny of flood-bond money invested to date. Construction can start later when a path to funding becomes clear.
Did Flood Control try to hide a shortfall?
No. The partial reliance on partner funding now characterized as a “shortfall” was shown in the Bond Program from Day One. The projected shortfall was never greater than on the day voters approved the flood bond. At that point we had secured no partnership funding for those watersheds or any others. We still haven’t for Halls and Greens.
Have we found partnership funding faster in other watersheds?
Yes. Especially in watersheds where the U.S. Army Corps of Engineers plays a leadership role in construction or where partners could demonstrate a positive benefit/cost ratio for FEMA. In 2018, Poppe estimated Harris County Flood Control could find $2.3 to $2.4 billion in matching funds based on $872 million allocated for seed money in the Flood Bond. But Berry estimates the budget shortfall at $900 million to $1.35 billion. Subtracting one estimate from the other indicates Flood Control has already found a billion dollars or more in matching funds for other watersheds. That’s great work. And that accounts for the differences in colors on the map.
Can Harris County count on the HUD money?
No. The Texas General Land Office (GLO) is still reviewing Flood Control’s grant applications to HUD. We could get some, all, or none of the requested grants.
When will we know how much HUD money, if any, we get?
Initial indications were that we would get answers by late April or early May. Today, I learned from an independent source who requested anonymity that the answer may not come until October.
If the money doesn’t come from HUD, where will it come from?
It depends. Commissioners floated several ideas in the meeting. They included self-funding with another Flood Bond and shifting money from existing sources within Harris County, such as the Toll Road Authority. They could have mentioned Texas Senate Bill 7 (from 2019), but didn’t. Among other things, SB7 provided partial reimbursement for local matching funds for federal grants. The motion approved by Commissioners Court today requires Flood Control and the Budget office to explore all the possibilities and lay out options for consideration.
Another flood bond? Seriously?
Yes and no. According to former Judge Ed Emmett, the $2.5 billion approved by voters in 2018 was always pitched as a “down payment.” Even with partnership funding potentially doubling the size of that, it still would not be likely to solve all of Harris County’s flood woes. So what’s the real total? During the meeting, the Judge and Commissioners tossed out figures ranging from $10-$40 billion. But no one believes another bond is politically feasible. Especially at this time. First, COVID has siphoned off valuable funds. And some of the commissioners have seen fit to redefine equity in the bond language in a way that benefits their constituents at the expense of all others. Now, they may not be able to deliver for their constituents. And they’ve managed to honk off everyone else. Everyone believes the likelihood of passing another bond is zero at this point.
Why is HUD taking so long?
It depends (on whom you talk to). Reportedly, the GLO and HUD have had concerns about the City of Houston and Harris County administering flood-disaster-relief funds to homeowners (separate from mitigation money for flood control projects). Even though Harris County Flood Control wasn’t involved in that program, HUD decided to have the Texas General Land Office (GLO) administer/oversee a giant pot of mitigation money for the entire state instead of sending a portion of it directly to Harris County. That created an extra step. And Harris County must compete with the rest of the state, a process that has inevitably delayed announcements.
Is it worth waiting for a half billion dollars?
Again, it depends. On whom you ask. If your home is flooding and you can get someone else to foot the bill, hell no. If your home is not flooding and there’s still a chance that HUD could come through, why hurry?
Partnership funding maximizes the amount of projects Flood Control can develop, but it can also delay some projects. This is a glass-half-full debate.
Shouldn’t we be captains of our own fate?
It depends on when you ask. When the flood bond passed in 2018, Flood Control was applauded for aggressively chasing all of the Federal funding it could. Yet during Tuesday’s Court meeting, some commissioners criticized Flood Control for going after any partner funds – a complete 180 from just two and a half years ago.
Will funding shortfalls discussed above affect additional gates for the Lake Houston Dam?
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/03/Page-16-Budget-Shortfall.jpg?fit=1200%2C901&ssl=19011200adminadmin2021-03-10 20:20:512021-03-12 13:19:17Is There a Shortfall in Harris County Flood Bond Money? Yes. No. Maybe. It Depends.
At the 3/9/2021 meeting, Harris County Commissioners Court approved the final members and a coordinator for the Community Flood Resilience Task Force. Commissioners established the Task Force last October to ensure “equity” in flood bond spending after months of debate. At the time, Harris County Judge Lina Hidalgo and the four commissioners each appointed one member. Those five members then advertised the twelve remaining positions on the task force. More than 120 applications poured in during November and December. During January, the five core members reviewed applications and extended invitations to new members.
Resilience and ingenuity in the face of flooding.Photo courtesy of Denise Faulkner.
The pool of candidates was exceptionally strong and diverse, making selection difficult. The five core members debated candidates for weeks. They moved candidates in and out of the final group based on credentials, geography, and whom they represented. Ensuring gender, racial, and professional diversity was also a top priority.
Inaugural Task Force Members
Below is a list of the 17 inaugural Task Force representatives approved today in commissioner’s court. Commissioners unanimously approved them. In alphabetical order, including the original five:
Marissa Aho
As the City of Houston representative on the CFRTF, Marissa Aho is the Chief Resilience Officer (CRO) for the City of Houston. She leads the city’s partnership with 100 Resilient Cities, as well as city-wide resilience-building efforts to help Houston prepare for, withstand, and bounce back from the “shocks” –catastrophic events like hurricanes, floods, and cyberattacks – and “stresses” – slow-moving disasters like aging infrastructure, homelessness, and economic inequality, which are increasingly part of 21st century life.
Michael Bloom
Michael F. Bloom, P.E., ENV SP, CFM, directs the sustainability practice of R. G. Miller Engineers, Inc. and is Vice President – Technical of the Houston Branch of the American Society of Civil Engineers. He is a nationally recognized expert in resilient and sustainable infrastructure planning and design with 29 years of professional experience.
Bill Callegari
Bill Callegari is a long-time citizen of Harris County, including 40 years residence on the Katy Prairie. He is a Licensed Professional Engineer, and also served as the Texas State Representative representing Katy and Cypress for fourteen years, from 2001 to 2015.
Dr. Joseph Colaco
Dr. Joseph Colaco holds a Ph.D. in Engineering from the University of Illinois, Urbana-Champaign and is President of Colaco Engineers and Professor of Architecture at the University of Houston. Dr. Colaco brings over 50 years of engineering experience related to flood resilience and mitigation and was a founding member of the Hurricane Research Center at Texas A&M. Most recently he served as an expert panelist for the webinar on Hurricanes and Tornadoes through Florida International University.
Yasmeen Dávila
Yasmeen Dávila is a multi-diciplinary non-binary queer artist and organizer in Houston, Texas. Having lived through various hurricanes that passed through Houston, they have set their pursuits to advocate for the neglected neighborhoods that experience floods and chemical exposures before, during, and after hurricane season.
Iris Gonzalez
Iris Gonzalez is the founding Coalition Director for The Coalition for Environment, Equity and Resilience (CEER), an advocacy collaborative working on environmental justice policy solutions in the greater Houston region. She has over 10 years experience in program development, program management, coalition building, grant-making, fundraising, and community engagement.
Lisa Gonzalez
Lisa Gonzalez is President of the Houston Advanced Research Center (HARC), a nonprofit sustainability research organization. Lisa is a longtime resident of East Harris County and as a coastal scientist, focuses on climate resilience and intersections between natural ecosystems and the built environment.
Billy Guevara
Billy Guevara is a member of the Northeast Action Collective, a community organizer, and twice-over flood survivor. He is totally blind and represents the interests of the neighborhoods in Northeast Houston.
Denae King
Dr. Denae King is a native Houstonian and an environmental justice researcher at Texas Southern University. She earned a Ph.D. in environmental science/toxicology from the University of Texas Health Science Center – Houston, School of Public Health and works on environmental health projects in Houston’s underserved communities plagued with cumulative environmental exposures and recurring flooding.
Elaine Morales-Díaz
Elaine Morales-Díaz is a Community Development Officer at LISC Houston, where she manages the GO Neighborhoods and Capacity Building Programs. With a background in Architecture and Community Design, Elaine has worked on equity building initiatives that address affordable housing, disaster recovery and community development issues through participatory design and planning.
Jimmy Morales
Jimmy Morale has long lived in North Harris County. He has worked in the insurance industry for over 10 years, handling a variety of insurance policies which includes flood insurance. He has earned a Bachelor of Business Administration degree with a concentration in Insurance and Risk Management from the University of Houston-Downtown.
Earthea Nance
Dr. Earthea Nance is a published author, scholar, registered civil engineer, and certified floodplain manager with over 30 years of experience. She earned her PhD from Stanford University, and after Hurricane Harvey she served on the Greater Houston Flood Mitigation Consortium.
Mary Anne Piacentini
Mary Anne Piacentini, President and CEO, Katy Prairie Conservancy, coordinates its land protection programs and conservation assistance to landowners, establishes community partnerships and relationships with diverse stakeholders, and oversees the operations and programs of the agency. She has a master’s degree in planning from Harvard University and is currently a board member of the Partnership for Gulf Coast Land Conservation, a member of the steering committee of the Coalition for Environment, Equity and Resilience,a member of the Land Trust Alliance’s Leadership Council, the chairperson of the Stream Corridor Restoration Committee of the Bayou Preservation Association, and previously served on the steering committee for Harris County Flood Control District’s Cypress Creek Overflow Management Plan.
Bob Rehak
Bob Rehak has more than 50 years of experience in communications. After seeing thousands in his area flooded during Harvey, he launched ReduceFlooding.com, a website dedicated to helping people understand the causes of flooding as well as mitigation possibilities.
Tracy Stephens
Tracy Stephens is the President of Sunnyside Civic Club, Gulfgate TIRZ Board Vice Chairman, Infrastructure Rehab and Development Chairman for South Park Community, ACTS Board Research Coordinator, and worked for the City of Houston Public Works and Engineering Specialized Maintenance District Supervisor for Streets, Drainage Construction and Rehab.
Adriana Tamez
Adriana Tamez is a Houston Community College Trustee, and President and CEO for the Tejano Center for Community Concerns (TCCC) providing overall management of the non-profit organization and its nine service programs. Essential to this work has been nurturing and creating partnerships at all levels to meet the needs of our most vulnerable populations in our county.
Kenneth Williams
Ken Williams is a founding director of the Northeast Houston Redevelopment Council, Vice-President of Super Neighborhood 48 Trinity-Houston Gardens, and a community servant/activist/resident.
Congratulations to all. Now the hard work begins.
Task Force Coordinator Also Approved
Commissioner’s Court also unanimously approved the appointment of Holloway Environmental and Communications Services as the task force facilitator. Holloway is a frequent contractor with Harris County Flood Control and helped develop the massive San Jacinto River Basin Master Drainage Study. The facilitator’s responsibilities will include coordination of the task force and public outreach.
The Guiding Values developed by the first five members of the Task Force include:
Diverse Collaboration
Holistic Solutions
Paradigm Shifting
Inclusive Community Engagement
Ethical Foundation
Commitment and Accountability
Social Understanding
Nature and Environment
Emphasis on Action and Momentum
Posted by Bob Rehak on March 10, 2021
1289 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/03/Screen-Shot-2021-03-09-at-6.53.11-PM-e1615337931914.jpg?fit=1200%2C800&ssl=18001200adminadmin2021-03-09 19:15:432021-03-09 19:19:46Harris County Commissioners Approve Final Members and Coordinator for Community Flood Resilience Task Force
11) Receive information from District’s technical consultants regarding subsidence studies and/or discussion regarding the same – Samantha Stried Reiter and/or District’s technical consultant(s)
a) Discussion, consideration, and possible action to approve Subsidence Study Phase 2 Scope of Work.’
12) Groundwater Management Area 14 – update the board on the issues related to joint planning activities and development of desired future conditions in GMA 14 –Samantha Reiter and/or District’s technical consultant(s)
a) Discussion, consideration, and possible action on any items related to Lone Star GCD’s proposal(s) to and/or participation in GMA 14.
The Hollywood talent scouts should be tuning in tonight. Acting just doesn’t get much better than this. After all, these are the people who promised to “restore affordable water” but in three years have yet to reduce rates.
John Yoars, a Woodlands resident submitted a three-page letter in tonight’s board packet that is so plain-spoken and common sense that the talent scouts will probably ignore him. But you shouldn’t. See pages 23-25.
Mr. Yoars begins by challenging the board to “own your problems.” Specifically, he defines the B-52 sized fly-in-the-ointment as, “How will the Board control subsidence in southeast Montgomery County?”
Map showing projected subsidence in Southern MOCO if LSGCD pumps 115,000 acre-feet per year of groundwater.
Plain-Spoken Recommendations from Woodlands Resident
Yoars advocates:
Acknowledging that 2-3 feet of subsidence in southeast MoCo is not acceptable. It’s an average across the entire county. The average includes 0 subsidence in the northern parts and more than 3 feet in the south. There’s no way to justify the latter.
Dividing southern Montgomery County into three segments to isolate the problem.
From Magnolia west, there’s no problem, he says.
The south-central Conroe/Woodlands corridor already has access to surface water and has shown they can acceptably manage subsidence with it … when they aren’t at war with the SJRA.
Southeast MoCo is where the real problem is. He advocates working with the Porter Special Utility District to bring East Fork San Jacinto River water into their system to reduce the projected 3-3.75 feet of subsidence there.
Pumping groundwater only in the less populated areas where subsidence will not really be an issue in the foreseeable future.
Starting to talk about solutions instead of arguing about irrelevant issues.
That’s the kind of thinking that could help Texans win back their reputation for straight talk. Even if you don’t buy every one of Yoar’s points, his hypothesis is testable and could get us further down the trail than the current crew has.
Porter probably doesn’t not have enough money to build its own surface water treatment plant. Extending the SJRA pipeline from the Woodlands to Porter might be more cost effective. But again, engineers can easily estimate those tradeoffs.
Participate Via Zoom: https://us02web.zoom.us/webinar/register/WN_oqaz9Z_5SJyQRd_9dynxwQ Register beforehand. You will then receive a confirmation email with a password. Use the password to join the webinar. You WILL have the opportunity to provide live comments during the designated portion of the hearings or meeting.
Dial in: Call +1 346 248 7799; enter the meeting ID: 854 2178 5781#. You will then be prompted to enter a participation code or press #. Press #. You do not need a participation code.
Posted by Bob Rehak on 3/9/2021
1288 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/11/Screen-Shot-2020-11-20-at-10.43.20-AM.png?fit=1318%2C920&ssl=19201318adminadmin2021-03-09 17:29:132021-03-09 18:43:42LSGCD to Discuss Issue of Subsidence Tonight
Is There a Shortfall in Harris County Flood Bond Money? Yes. No. Maybe. It Depends.
The 3/9/2021 meeting of Harris County Commissioners Court started with a presentation by the Harris County Budget Management Director David Berry on the County’s Capital Improvement Plan. Mr. Berry asserted early in the meeting that the County had a shortfall of approximately $900 million to $1.35 billion needed to complete projects in the Flood Bond passed by voters in 2018. Is there really a shortfall? It depends on the exact way you phrase any number of possible questions.
Confusing, Unexplained Map Triggers Almost 2 Hours of Discussion
Near the start of the meeting, Mr. Berry put up a very confusing map (below) that frequently heated the next 100 minutes of discussion to the boiling point. The discussion made every front page in town and many of the TV news shows.
The map implied that construction had started on projects that the County did not have enough money to finish, especially the ones in yellow and red below.
Was Flood Control Not Following Equity Guidelines?
To add more context to this discussion, understand that Halls and Greens Bayous rank among the poorest in the county. That they seemed so far behind more affluent watersheds in funding rankled Ellis and Garcia. The two had argued to prioritize flood bond spending by a “social equity” formula that addressed the poorest neighborhoods first. To say that the map above was like waving a red flag in front of two bulls would understate its effect.
So What’s Really Going on Here?
Did prices of flood-bond projects suddenly escalate, causing the shortfall? No.
Did Flood Control underestimate costs? No.
But Berry did not make that apparent in his setup. Commissioners Garcia and Ellis then peppered Russ Poppe, head of the Flood Control District, with angry, accusatory questions for more than 40 minutes. At one point, they asked 11 questions in a row before they gave Poppe a chance to answer one.
Poppe then explained that Flood Control relies on matching funds from the U.S. Department of Housing and Urban Development (HUD) for low-income areas. Why? Unlike FEMA which requires a positive benefit/cost ratio, HUD does not. Flood Control is currently waiting for answers on HUD grant applications totaling almost half a billion dollars for mitigation work in the Halls and Greens Bayou watersheds.
Commissioners Court then spent another 40 minutes trying to understand the chances of getting those grants. They also crafted a motion directing the Flood Control District to develop a backup plan in case grant money didn’t arrive by June 30.
Text Of Motion
The motion reads as follows: “To direct the Flood Control District to work with Budget Management in developing a plan by June 30, 2021 to address the funding gap in flood mitigation projects under the 2018 bond while maintaining an equitable approach to the expenditure of funds, including plans to lobby federal, state, and local partners for funding, identification of alternative funding options, a description of projects that are currently stalled due to incomplete funding and how that affects timing of project completion, and a potential timeline for a future potential bond election regarding the funding of current and future flood control projects. If the County is unable to secure funding to complete all proposed projects, the plan should address how the County should prioritize the investment of existing resources to ensure equitable flood protection and comply with the prioritization framework adopted by Harris County.”
The motion eventually passed unanimously at 1 hour and 32 minutes into the meeting.
Answers to Questions About “Underfunding”
Is construction money in Halls or Greens Bayous invested so far at risk?
No. Money spent so far, according to Poppe, has only been for land acquisition and preliminary engineering studies. The County will need both regardless of how it pays for construction. So the County didn’t waste a penny of flood-bond money invested to date. Construction can start later when a path to funding becomes clear.
Did Flood Control try to hide a shortfall?
No. The partial reliance on partner funding now characterized as a “shortfall” was shown in the Bond Program from Day One. The projected shortfall was never greater than on the day voters approved the flood bond. At that point we had secured no partnership funding for those watersheds or any others. We still haven’t for Halls and Greens.
Have we found partnership funding faster in other watersheds?
Yes. Especially in watersheds where the U.S. Army Corps of Engineers plays a leadership role in construction or where partners could demonstrate a positive benefit/cost ratio for FEMA. In 2018, Poppe estimated Harris County Flood Control could find $2.3 to $2.4 billion in matching funds based on $872 million allocated for seed money in the Flood Bond. But Berry estimates the budget shortfall at $900 million to $1.35 billion. Subtracting one estimate from the other indicates Flood Control has already found a billion dollars or more in matching funds for other watersheds. That’s great work. And that accounts for the differences in colors on the map.
Can Harris County count on the HUD money?
No. The Texas General Land Office (GLO) is still reviewing Flood Control’s grant applications to HUD. We could get some, all, or none of the requested grants.
When will we know how much HUD money, if any, we get?
Initial indications were that we would get answers by late April or early May. Today, I learned from an independent source who requested anonymity that the answer may not come until October.
If the money doesn’t come from HUD, where will it come from?
It depends. Commissioners floated several ideas in the meeting. They included self-funding with another Flood Bond and shifting money from existing sources within Harris County, such as the Toll Road Authority. They could have mentioned Texas Senate Bill 7 (from 2019), but didn’t. Among other things, SB7 provided partial reimbursement for local matching funds for federal grants. The motion approved by Commissioners Court today requires Flood Control and the Budget office to explore all the possibilities and lay out options for consideration.
Another flood bond? Seriously?
Yes and no. According to former Judge Ed Emmett, the $2.5 billion approved by voters in 2018 was always pitched as a “down payment.” Even with partnership funding potentially doubling the size of that, it still would not be likely to solve all of Harris County’s flood woes. So what’s the real total? During the meeting, the Judge and Commissioners tossed out figures ranging from $10-$40 billion. But no one believes another bond is politically feasible. Especially at this time. First, COVID has siphoned off valuable funds. And some of the commissioners have seen fit to redefine equity in the bond language in a way that benefits their constituents at the expense of all others. Now, they may not be able to deliver for their constituents. And they’ve managed to honk off everyone else. Everyone believes the likelihood of passing another bond is zero at this point.
Why is HUD taking so long?
It depends (on whom you talk to). Reportedly, the GLO and HUD have had concerns about the City of Houston and Harris County administering flood-disaster-relief funds to homeowners (separate from mitigation money for flood control projects). Even though Harris County Flood Control wasn’t involved in that program, HUD decided to have the Texas General Land Office (GLO) administer/oversee a giant pot of mitigation money for the entire state instead of sending a portion of it directly to Harris County. That created an extra step. And Harris County must compete with the rest of the state, a process that has inevitably delayed announcements.
Is it worth waiting for a half billion dollars?
Again, it depends. On whom you ask. If your home is flooding and you can get someone else to foot the bill, hell no. If your home is not flooding and there’s still a chance that HUD could come through, why hurry?
Partnership funding maximizes the amount of projects Flood Control can develop, but it can also delay some projects. This is a glass-half-full debate.
Shouldn’t we be captains of our own fate?
It depends on when you ask. When the flood bond passed in 2018, Flood Control was applauded for aggressively chasing all of the Federal funding it could. Yet during Tuesday’s Court meeting, some commissioners criticized Flood Control for going after any partner funds – a complete 180 from just two and a half years ago.
Will funding shortfalls discussed above affect additional gates for the Lake Houston Dam?
No. At least not if the City can prove up its initial benefit/cost ratio. FEMA has already provisionally allocated funds for gate construction.
For More Information
See these links to:
The entire 358-page Capital Improvement Plan
Video of the Commissioners Court Meeting. Click on Departments (Part 1 of 4) and start about 7:36 in.
The final Prioritization Framework for the Flood Bond projects according to “social equity” criteria.
Posted by Bob Rehak on 3/10/2021
1289 Days since Hurricane Harvey
Harris County Commissioners Approve Final Members and Coordinator for Community Flood Resilience Task Force
At the 3/9/2021 meeting, Harris County Commissioners Court approved the final members and a coordinator for the Community Flood Resilience Task Force. Commissioners established the Task Force last October to ensure “equity” in flood bond spending after months of debate. At the time, Harris County Judge Lina Hidalgo and the four commissioners each appointed one member. Those five members then advertised the twelve remaining positions on the task force. More than 120 applications poured in during November and December. During January, the five core members reviewed applications and extended invitations to new members.
The pool of candidates was exceptionally strong and diverse, making selection difficult. The five core members debated candidates for weeks. They moved candidates in and out of the final group based on credentials, geography, and whom they represented. Ensuring gender, racial, and professional diversity was also a top priority.
Inaugural Task Force Members
Below is a list of the 17 inaugural Task Force representatives approved today in commissioner’s court. Commissioners unanimously approved them. In alphabetical order, including the original five:
Marissa Aho
As the City of Houston representative on the CFRTF, Marissa Aho is the Chief Resilience Officer (CRO) for the City of Houston. She leads the city’s partnership with 100 Resilient Cities, as well as city-wide resilience-building efforts to help Houston prepare for, withstand, and bounce back from the “shocks” –catastrophic events like hurricanes, floods, and cyberattacks – and “stresses” – slow-moving disasters like aging infrastructure, homelessness, and economic inequality, which are increasingly part of 21st century life.
Michael Bloom
Michael F. Bloom, P.E., ENV SP, CFM, directs the sustainability practice of R. G. Miller Engineers, Inc. and is Vice President – Technical of the Houston Branch of the American Society of Civil Engineers. He is a nationally recognized expert in resilient and sustainable infrastructure planning and design with 29 years of professional experience.
Bill Callegari
Bill Callegari is a long-time citizen of Harris County, including 40 years residence on the Katy Prairie. He is a Licensed Professional Engineer, and also served as the Texas State Representative representing Katy and Cypress for fourteen years, from 2001 to 2015.
Dr. Joseph Colaco
Dr. Joseph Colaco holds a Ph.D. in Engineering from the University of Illinois, Urbana-Champaign and is President of Colaco Engineers and Professor of Architecture at the University of Houston. Dr. Colaco brings over 50 years of engineering experience related to flood resilience and mitigation and was a founding member of the Hurricane Research Center at Texas A&M. Most recently he served as an expert panelist for the webinar on Hurricanes and Tornadoes through Florida International University.
Yasmeen Dávila
Yasmeen Dávila is a multi-diciplinary non-binary queer artist and organizer in Houston, Texas. Having lived through various hurricanes that passed through Houston, they have set their pursuits to advocate for the neglected neighborhoods that experience floods and chemical exposures before, during, and after hurricane season.
Iris Gonzalez
Iris Gonzalez is the founding Coalition Director for The Coalition for Environment, Equity and Resilience (CEER), an advocacy collaborative working on environmental justice policy solutions in the greater Houston region. She has over 10 years experience in program development, program management, coalition building, grant-making, fundraising, and community engagement.
Lisa Gonzalez
Lisa Gonzalez is President of the Houston Advanced Research Center (HARC), a nonprofit sustainability research organization. Lisa is a longtime resident of East Harris County and as a coastal scientist, focuses on climate resilience and intersections between natural ecosystems and the built environment.
Billy Guevara
Billy Guevara is a member of the Northeast Action Collective, a community organizer, and twice-over flood survivor. He is totally blind and represents the interests of the neighborhoods in Northeast Houston.
Denae King
Dr. Denae King is a native Houstonian and an environmental justice researcher at Texas Southern University. She earned a Ph.D. in environmental science/toxicology from the University of Texas Health Science Center – Houston, School of Public Health and works on environmental health projects in Houston’s underserved communities plagued with cumulative environmental exposures and recurring flooding.
Elaine Morales-Díaz
Elaine Morales-Díaz is a Community Development Officer at LISC Houston, where she manages the GO Neighborhoods and Capacity Building Programs. With a background in Architecture and Community Design, Elaine has worked on equity building initiatives that address affordable housing, disaster recovery and community development issues through participatory design and planning.
Jimmy Morales
Jimmy Morale has long lived in North Harris County. He has worked in the insurance industry for over 10 years, handling a variety of insurance policies which includes flood insurance. He has earned a Bachelor of Business Administration degree with a concentration in Insurance and Risk Management from the University of Houston-Downtown.
Earthea Nance
Dr. Earthea Nance is a published author, scholar, registered civil engineer, and certified floodplain manager with over 30 years of experience. She earned her PhD from Stanford University, and after Hurricane Harvey she served on the Greater Houston Flood Mitigation Consortium.
Mary Anne Piacentini
Mary Anne Piacentini, President and CEO, Katy Prairie Conservancy, coordinates its land protection programs and conservation assistance to landowners, establishes community partnerships and relationships with diverse stakeholders, and oversees the operations and programs of the agency. She has a master’s degree in planning from Harvard University and is currently a board member of the Partnership for Gulf Coast Land Conservation, a member of the steering committee of the Coalition for Environment, Equity and Resilience,a member of the Land Trust Alliance’s Leadership Council, the chairperson of the Stream Corridor Restoration Committee of the Bayou Preservation Association, and previously served on the steering committee for Harris County Flood Control District’s Cypress Creek Overflow Management Plan.
Bob Rehak
Bob Rehak has more than 50 years of experience in communications. After seeing thousands in his area flooded during Harvey, he launched ReduceFlooding.com, a website dedicated to helping people understand the causes of flooding as well as mitigation possibilities.
Tracy Stephens
Tracy Stephens is the President of Sunnyside Civic Club, Gulfgate TIRZ Board Vice Chairman, Infrastructure Rehab and Development Chairman for South Park Community, ACTS Board Research Coordinator, and worked for the City of Houston Public Works and Engineering Specialized Maintenance District Supervisor for Streets, Drainage Construction and Rehab.
Adriana Tamez
Adriana Tamez is a Houston Community College Trustee, and President and CEO for the Tejano Center for Community Concerns (TCCC) providing overall management of the non-profit organization and its nine service programs. Essential to this work has been nurturing and creating partnerships at all levels to meet the needs of our most vulnerable populations in our county.
Kenneth Williams
Ken Williams is a founding director of the Northeast Houston Redevelopment Council, Vice-President of Super Neighborhood 48 Trinity-Houston Gardens, and a community servant/activist/resident.
Congratulations to all. Now the hard work begins.
Task Force Coordinator Also Approved
Commissioner’s Court also unanimously approved the appointment of Holloway Environmental and Communications Services as the task force facilitator. Holloway is a frequent contractor with Harris County Flood Control and helped develop the massive San Jacinto River Basin Master Drainage Study. The facilitator’s responsibilities will include coordination of the task force and public outreach.
Guiding Values
Work of the task force should now begin in earnest.
The Guiding Values developed by the first five members of the Task Force include:
Posted by Bob Rehak on March 10, 2021
1289 Days since Hurricane Harvey
LSGCD to Discuss Issue of Subsidence Tonight
The Lone Star Groundwater Conservation District will meet tonight starting at 6PM. On the agenda are two items of interest for those concerned about subsidence in Montgomery and Harris Counties.
A Not-So-Instant Replay of Last Month’s Meeting?
Both sound similar to two items on last month’s agenda. However, the board deferred discussion and action on Phase 2 of the subsidence study because a large number of public comments and excessively long technical and historical presentations by staff. The presentations tried to convince any viewers still awake that LSGCD was still seriously examining subsidence – despite the fact that they had just told the GMA-14 board that they rejected any mention of subsidence in their Desired Future Conditions (DFCs). Since the last LSGCD board meeting, the same presenters again told GMA-14 that they soundly rejected any mention of subsidence…and always had.
Acting Worthy of Hollywood
The Hollywood talent scouts should be tuning in tonight. Acting just doesn’t get much better than this. After all, these are the people who promised to “restore affordable water” but in three years have yet to reduce rates.
John Yoars, a Woodlands resident submitted a three-page letter in tonight’s board packet that is so plain-spoken and common sense that the talent scouts will probably ignore him. But you shouldn’t. See pages 23-25.
Mr. Yoars begins by challenging the board to “own your problems.” Specifically, he defines the B-52 sized fly-in-the-ointment as, “How will the Board control subsidence in southeast Montgomery County?”
Plain-Spoken Recommendations from Woodlands Resident
Yoars advocates:
That’s the kind of thinking that could help Texans win back their reputation for straight talk. Even if you don’t buy every one of Yoar’s points, his hypothesis is testable and could get us further down the trail than the current crew has.
Porter probably doesn’t not have enough money to build its own surface water treatment plant. Extending the SJRA pipeline from the Woodlands to Porter might be more cost effective. But again, engineers can easily estimate those tradeoffs.
View Discussion Starting at 6PM
LSGCD has three ways for you to participate
Posted by Bob Rehak on 3/9/2021
1288 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.