Initial options that the City of Houston explored for adding more flood gates to the Lake Houston Dam struggled to achieve a high enough Benefit/Cost Ratio. However, all parties involved are still hopeful that a solution can be found. They are now evaluating yet another option. It would add gates in the earthen (eastern) portion of the dam.
Looking south over eastern portion of Lake Houston Dam at area under consideration for five new tainter gates. The spillway is out of frame to the right.Picture taken on 7/22/22.
More Gates Would Create More Room For Floodwaters
Flooding devasted the entire Lake Houston Area during Harvey. Since then, Mayor Pro Tem Dave Martin has led an effort to find a way to lower the lake faster in advance of a storm. This would create extra room in the lake for floodwaters. And that would reduce the risk of flooding homes and businesses around it.
Currently, the dam has a fixed height spillway. That makes releasing water in advance of a storm difficult. The dam does have several small gates, but they have only 1/15th the release capacity of the gates on Lake Conroe. Adding more gates would help release water faster…to keep up with water coming downstream.
It would also let managers wait to start a release until they were certain a storm would not veer away. That would help avoid wasting water if forecasts are not accurate.
The Dual-Role Dilemma
The City built Lake Houston in 1953 to supply water. Making the dam play two roles – water supply and flood mitigation – poses a challenge.
In 2017, immediately after Hurricane Harvey, Martin began leading the effort to transform the dam to play a dual role. This would let Lake Houston provide our region with needed drinking water and reduce flood risk.
New Timeline Longer Than Hoped, But Still Shorter Than Usual
A project of this magnitude normally takes up to twelve years. However, Martin worked with federal, state, and local officials to shorten the timeline. Martin now hopes the project will take no longer than seven years. While acknowledging that he hoped completion would happen in as little as five years, Martin also cites unexpected technical and cost challenges related to the aging dam.
As engineers started precisely calculating costs and benefits of preferred approaches, they weighed those against environmental impacts, construction challenges, safety risks, and available budget.
During that process, engineers discovered hidden challenges with some options that initially looked promising. At this point, they have determined that all six initial options cost more than the federally funded amount of $48 million.
A Complicated Path Forward
So now engineers are focusing on finding the optimal solution while Martin and others explore options to pay for it.
Martin says the City of Houston, Texas Division of Emergency Management and Federal Emergency Management Agency are working together to find the option with the highest Benefit to Cost Ratio (BCR).
Acceptable BCRs for projects like this range from .75 to 1, according to Martin. Preliminary engineering studies found that two crest-gate alternatives (already evaluated) yielded only .48 – largely due to the aging structure of the existing spillway, which drove up costs.
City Expects Answer on Latest Option Before October
Currently, the City has paused the final-design phase of the project while engineers evaluate Alternative 1A. That now consists of five new tainter-gates (not six or twelve as previously reported) on the earthen embankment east of the spillway.
While engineers work to find the best BCR, Martin is leading an effort with BOTH state and federal partners to find additional funding for the project.
For instance, Martin is working with outgoing State Representative Dan Huberty and incoming State Representative Charles Cunningham to seek funds in the upcoming Texas Legislative Session. Martin says that state dollars do not require BCRs like federal dollars do.
While all the challenges would have discouraged many, Martin says they have fortified his resolve. He vows to find a path forward. Martin promises an update in his regular fall public meeting in October and hopes to have an attractive BCR for alternative 1A.
Interim Flood-Mitigation Measures Still In Place
In the meantime, the City of Houston will continue its existing Lake Houston pre-release strategy. It calls for lowering the lake when forecasters predict three or more inches of rain in the San Jacinto Watershed. Since Hurricane Harvey, the City has lowered the lake more than twenty times and successfully avoided flooding.
Thanks to Key Contributors
Martin acknowledges the continuing contributions of Congressman Dan Crenshaw, Governor Greg Abbott, Lt. Governor Dan Patrick, Commissioner Tom Ramsey, State Representative Dan Huberty, State Representative-Elect Charles Cunningham, TDEM-Chief Nim Kidd, Mayor Sylvester Turner, Chief Recovery Officer Stephen Costello, and Harris County Flood Control District.
Martin says, “All parties are committed to constructing these additional gates to help ensure protection against future flood events.”
Posted by Bob Rehak on 8/4/2022
1801 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2022/08/20220722-RJR_0780-1.jpg?fit=1200%2C800&ssl=18001200adminadmin2022-08-04 18:10:242022-08-04 18:17:52All Parties Still Focused on Finding Solution for Adding Flood Gates to Lake Houston Dam
A TCEQ investigation found nothing wrong with construction practices at the Preserve at Woodridge despite photographic evidence.
On April 23, 2022, I received multiple complaints about silty stormwater in Bens Branch. I confirmed discoloration in the water and followed it upstream. The source appeared to be the Preserve at Woodridge on Woodridge Parkway opposite the new St. Martha church. Photos confirmed that contractors were:
Pumping the contents of their silty detention pond into a tributary of Bens Branch.
Piling dirt on neighboring property.
Not using silt fence along their southern boundary.
Not posting permits.
I then filed a complaint with the TCEQ. They investigated on June 21, 2022, almost two months later. And found nothing wrong.
Today, August 3, 2022, I received this letter confirming they found nothing wrong.
My complaint was based on these photos (among others).
Stormwater discharge into Bens Branch from Preserve at Woodridge Forest.Note pile of sediment in front of hose (bottom center).Silty stormwater had migrated more than two miles down Bens Branch past Tree Lane.
I guess there was nothing wrong. Message received, TCEQ.
Posted by Bob Rehak on 8/3/2022
1800 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2022/04/20220420-DJI_0262.jpg?fit=1200%2C799&ssl=17991200adminadmin2022-08-03 10:34:262022-08-03 10:45:27TCEQ Finds Nothing Wrong With Preserve At Woodridge Construction
Today, the last townhome in Forest Cove was demolished – 1799 days after Hurricane Harvey, the storm that left them uninhabitable.
As of 3PM today, only one small portion of one wall remained and the demolition crew was busy loading up the last debris into waiting trucks. I may take another day or two to remove foundations and concrete driveways. But this show is over.
All that remained as of 3PM 8/2/22Excavator loads debris into waiting truck.
Before Demolition
How last complex looked on 2/24/22, before demolition.
The last complex was situated across from the Forest Cove pool on Marina Drive. 240,000 cubic feet per second coming down the West Fork during Harvey blew out doors, windows, stairs and portions of balconies. The homes became uninhabitable for structural reasons.
Photo taken on July 22, 2022 shows location of last complex relative to Forest Cove pool.
You would think that in such cases, buyouts would take little time. But some people reportedly fled mortgage obligations to avoid payments on homes they could no longer live in. Without forwarding addresses, Harris County Flood Control District (HCFCD) had no choice but to go through lengthy condemnation proceedings in several cases. And until every unit in a complex like the one above had been bought, HCFCD could not tear down the complex.
While the legal system sputtered through Covid, drug dealers, illegal dumpers, arsonists, and graffiti artists took over these buildings. But now the area can return to nature. HCFCD will use this area to help preserve the floodplain.
Thank You, HCFCD!
Thanks to the women and men of the Harris County Flood Control District and their contractors for their diligence. Today’s demolition will make a huge difference in the quality of life for everyone in Forest Cove. Residents’ pool, athletic fields and community room were in the middle of this area. Perhaps now it can be restored to a productive, recreational purpose.
There is still no word on plans for the area. The only thing we know is that the FEMA money used to buy out the Forest Cove townhomes came with strings attached. Specifically, no other “insurable structures” can every be built on the purchased property.
Posted by Bob Rehak on 8/2/2022
1799 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2022/08/20220802-DJI_0318.jpg?fit=1200%2C799&ssl=17991200adminadmin2022-08-02 16:55:532022-08-02 17:26:47Last Forest Cove Townhome Now Down
All Parties Still Focused on Finding Solution for Adding Flood Gates to Lake Houston Dam
Initial options that the City of Houston explored for adding more flood gates to the Lake Houston Dam struggled to achieve a high enough Benefit/Cost Ratio. However, all parties involved are still hopeful that a solution can be found. They are now evaluating yet another option. It would add gates in the earthen (eastern) portion of the dam.
More Gates Would Create More Room For Floodwaters
Flooding devasted the entire Lake Houston Area during Harvey. Since then, Mayor Pro Tem Dave Martin has led an effort to find a way to lower the lake faster in advance of a storm. This would create extra room in the lake for floodwaters. And that would reduce the risk of flooding homes and businesses around it.
Currently, the dam has a fixed height spillway. That makes releasing water in advance of a storm difficult. The dam does have several small gates, but they have only 1/15th the release capacity of the gates on Lake Conroe. Adding more gates would help release water faster…to keep up with water coming downstream.
It would also let managers wait to start a release until they were certain a storm would not veer away. That would help avoid wasting water if forecasts are not accurate.
The Dual-Role Dilemma
The City built Lake Houston in 1953 to supply water. Making the dam play two roles – water supply and flood mitigation – poses a challenge.
In 2017, immediately after Hurricane Harvey, Martin began leading the effort to transform the dam to play a dual role. This would let Lake Houston provide our region with needed drinking water and reduce flood risk.
New Timeline Longer Than Hoped, But Still Shorter Than Usual
A project of this magnitude normally takes up to twelve years. However, Martin worked with federal, state, and local officials to shorten the timeline. Martin now hopes the project will take no longer than seven years. While acknowledging that he hoped completion would happen in as little as five years, Martin also cites unexpected technical and cost challenges related to the aging dam.
Difficulty of Finding Best Alternative
The age of the Lake Houston Spillway, built in 1953, has proven to be a bigger obstacle than expected. Engineers initially proposed six different alternatives for adding different types of gates in different locations, with variations on several.
During that process, engineers discovered hidden challenges with some options that initially looked promising. At this point, they have determined that all six initial options cost more than the federally funded amount of $48 million.
A Complicated Path Forward
So now engineers are focusing on finding the optimal solution while Martin and others explore options to pay for it.
Martin says the City of Houston, Texas Division of Emergency Management and Federal Emergency Management Agency are working together to find the option with the highest Benefit to Cost Ratio (BCR).
Acceptable BCRs for projects like this range from .75 to 1, according to Martin. Preliminary engineering studies found that two crest-gate alternatives (already evaluated) yielded only .48 – largely due to the aging structure of the existing spillway, which drove up costs.
City Expects Answer on Latest Option Before October
Currently, the City has paused the final-design phase of the project while engineers evaluate Alternative 1A. That now consists of five new tainter-gates (not six or twelve as previously reported) on the earthen embankment east of the spillway.
The comprehensive, final BCR analysis for the embankment alternative should be completed by the end of September 2022. The preliminary engineering report suggested the 1A alternative could reduce flood heights by half a foot for a cost of $47.3 million with a BCR of .89. So initially, on the surface, this appears feasible.
Martin Widens Search for Funding
While engineers work to find the best BCR, Martin is leading an effort with BOTH state and federal partners to find additional funding for the project.
For instance, Martin is working with outgoing State Representative Dan Huberty and incoming State Representative Charles Cunningham to seek funds in the upcoming Texas Legislative Session. Martin says that state dollars do not require BCRs like federal dollars do.
While all the challenges would have discouraged many, Martin says they have fortified his resolve. He vows to find a path forward. Martin promises an update in his regular fall public meeting in October and hopes to have an attractive BCR for alternative 1A.
Interim Flood-Mitigation Measures Still In Place
In the meantime, the City of Houston will continue its existing Lake Houston pre-release strategy. It calls for lowering the lake when forecasters predict three or more inches of rain in the San Jacinto Watershed. Since Hurricane Harvey, the City has lowered the lake more than twenty times and successfully avoided flooding.
Thanks to Key Contributors
Martin acknowledges the continuing contributions of Congressman Dan Crenshaw, Governor Greg Abbott, Lt. Governor Dan Patrick, Commissioner Tom Ramsey, State Representative Dan Huberty, State Representative-Elect Charles Cunningham, TDEM-Chief Nim Kidd, Mayor Sylvester Turner, Chief Recovery Officer Stephen Costello, and Harris County Flood Control District.
Martin says, “All parties are committed to constructing these additional gates to help ensure protection against future flood events.”
Posted by Bob Rehak on 8/4/2022
1801 Days since Hurricane Harvey
TCEQ Finds Nothing Wrong With Preserve At Woodridge Construction
A TCEQ investigation found nothing wrong with construction practices at the Preserve at Woodridge despite photographic evidence.
On April 23, 2022, I received multiple complaints about silty stormwater in Bens Branch. I confirmed discoloration in the water and followed it upstream. The source appeared to be the Preserve at Woodridge on Woodridge Parkway opposite the new St. Martha church. Photos confirmed that contractors were:
Today, August 3, 2022, I received this letter confirming they found nothing wrong.
Caught on Camera
My complaint was based on these photos (among others).
I guess there was nothing wrong. Message received, TCEQ.
Posted by Bob Rehak on 8/3/2022
1800 Days since Hurricane Harvey
Last Forest Cove Townhome Now Down
Today, the last townhome in Forest Cove was demolished – 1799 days after Hurricane Harvey, the storm that left them uninhabitable.
As of 3PM today, only one small portion of one wall remained and the demolition crew was busy loading up the last debris into waiting trucks. I may take another day or two to remove foundations and concrete driveways. But this show is over.
Before Demolition
The last complex was situated across from the Forest Cove pool on Marina Drive. 240,000 cubic feet per second coming down the West Fork during Harvey blew out doors, windows, stairs and portions of balconies. The homes became uninhabitable for structural reasons.
You would think that in such cases, buyouts would take little time. But some people reportedly fled mortgage obligations to avoid payments on homes they could no longer live in. Without forwarding addresses, Harris County Flood Control District (HCFCD) had no choice but to go through lengthy condemnation proceedings in several cases. And until every unit in a complex like the one above had been bought, HCFCD could not tear down the complex.
The buyout and demolition process lasted four years. It began in 2018 and the first complex came down in 2019. Two complexes burned down.
While the legal system sputtered through Covid, drug dealers, illegal dumpers, arsonists, and graffiti artists took over these buildings. But now the area can return to nature. HCFCD will use this area to help preserve the floodplain.
Thank You, HCFCD!
Thanks to the women and men of the Harris County Flood Control District and their contractors for their diligence. Today’s demolition will make a huge difference in the quality of life for everyone in Forest Cove. Residents’ pool, athletic fields and community room were in the middle of this area. Perhaps now it can be restored to a productive, recreational purpose.
There is still no word on plans for the area. The only thing we know is that the FEMA money used to buy out the Forest Cove townhomes came with strings attached. Specifically, no other “insurable structures” can every be built on the purchased property.
Posted by Bob Rehak on 8/2/2022
1799 Days since Hurricane Harvey