New West Fork High School Opens

New Caney ISD’s new West Fork High School on Sorters-McClellan Road south of Kingwood Drive celebrated its grand opening on August 23, 2022. Here’s a video of the event. I’ve been following the construction of the school since early 2020.

Construction is the riskiest period in a project as we saw with the aborted Woodridge Village project. Sheet flow during heavy rains flooded Elm Grove Village and North Kingwood Forest twice in 2019, largely because of the failure to follow best practices. Contractors cleared 270 acres before building required detention ponds.

No Flooding During Construction

However, New Caney ISD built a large detention pond at the low end of the site when it started construction. They also planted grass in it right away. Luckily, TA DA, no one flooded during construction. And no major erosion problems were observed. Amazing how safety improves when you follow best practices.

Pictures of Completed Campus

Here are pictures of the school taken 9/4/22, Sunday morning when no students were around. The campus looks beautiful and will make a welcome addition for New Caney ISD students in the area.

Wide shot showing whole campus including detention pond. Looking NE across Sorters-McClellan Road toward HCA Kingwood Medical Center in background.
Closer shot looking in same direction.
Looking NW from SE corner of site over the detention basin.
Track, field events, baseball and a dedicated athletic facility on the left.
Looking directly west at back of new high school.
Looking south from north end of main complex.
Central open-air courtyard, a signature feature of the new school. Gives more classrooms sunlight.
Completing the circle. Looking NE again from SW corner of main building.

Historical Photos of Construction Progress

To look back at the sequence of construction photos starting in June 2020, see the links below.

Congratulations to New Caney ISD, its students, and all the neighbors who survived construction.

There’s still a little work left to do. The road in front of the high school is widening. A pile of dirt at the north end needs to be removed. And pipe, most likely for irrigation, still remains in places. But I think we can safely close the books on this project.

Posted by Bob Rehak on 9/4/22

1832 Days since Hurricane Harvey

Nephew Izzy Considering Homelets

My weird nephew Izzy wants to rent one of those new 660-square-foot homelets going up in the Preserve at Woodridge. He came to me so excited the other day that he was gesturing wildly and sloshed beer all over his Mötley Crüe T-shirt.

“Uncle Bob,” he enthused, “You gotta see these places! I can maybe actually possibly afford one!”

131 homes under construction, 13 to the acre. Photo taken 9/2/22.

That’s saying a lot. Or a little. Izzy isn’t exactly the top earner down at the Crystal Pistol. The owner demoted him from bartender to sweeping up beer nuts and cigarette butts. That happened after the owner learned Izzy had applied to be the head of the Flood Control District. Something about not showing loyalty and appreciation.

“A lease is a pretty big obligation, Izzy,” I said.

“It’s better than living outa the back seat of my Oldsmobile,” Izzy shot back.

“I thought you told me it would be a collector’s item someday.”

All the Amenities

“True,” said Izzy, “but these homelets, they got flush toilets.”

“I can see the advantage there. But they’re so close together, Izzy.”

“That’s one of the big pluses, Uncle Bob.”

“Why is that?”

“No trees to water. No grass to mow. More time for the ladies.”

Some of the homelets are more than 4 feet apart. Density is about 13 homelets to the acre.

“But Izzy. People commute all the way to Kingwood because they like nature.”

“Well, I heard they give you a geranium.”

“Will it fit?”

“Them homelets, they got plenty of room. Some even gots a study.”

“Do you own a book, Izzy?”

“No, but I got me a library card.”

“Have you ever used it?”

“I see your point, Uncle Bob. “

“Izzy, what you really need is a washer and drier.”

“They got them!”

“A shower?”

“Included!”

“When do you move in?”

Posted by Bob Rehak on 9/3/2022

1831 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Update on new Woodridge Village Detention Pond

At the end of August, I checked with Harris County Flood Control District (HCFCD) to see how excavation of the new Woodridge Village detention pond was coming and what the next steps are.

Before and After Photos

The two photos below show the extent of excavation at the end of July and today.

Woodridge Village Excavation
The far end of the pond reached slightly past the second cluster of storm sewers at the end of July.
By the end of August, excavation had reached the far end of the second pile of storm sewers.

Eventually, the new detention basin could reach to or past the cluster of trees in the background.

Rough layout for new Woodridge basin.
Rough layout showing the excavation limits for Sprint. Right now, they’re in the lower left of the green area.

Progress by the Numbers

From February through August, 2022, Sprint Sand and Clay has removed 55,167 Cubic Yards of dirt from the area where a new detention pond will eventually be built.

Eventually, they could double the amount of detention on the site. Sprint’s contract lets them remove up to 500,000 cubic yards and sell the dirt at market rates. In exchange, HCFCD will pay them only $1,000. The minimum amount to be removed under the contract is 5,000 cubic yards per month.

Since January, Sprint has managed to beat the minimum each month. But regular reports show the rate of excavation slowing with the housing market.

Sprint began work on January 27, 2022.

By mid-April, Sprint was averaging a little more than 14,000 cubic yards per month.

But by the end of July, the average fell to 8,000 cubic yards per month.

And in August, Sprint removed only 6,307 cubic yards.

At 6,000 cubic yards per month, Sprint exceeds the contract minimum. But it would take the company another six years to reach 500,000 cubic yards. Flood-weary Elm Grove and North Kingwood Forest residents pray it doesn’t take that long.

Slowing Rates Reflect Slowdown in Housing

The slowing rates of removal reflect a slowdown in the housing market. The Census Bureau reports that privately‐owned housing starts in July were 9.6 percent below June and 8.1 percent below July 2021. TradingEconomics.com reports that the housing sector has been cooling down amid soaring prices of materials and rising mortgage rates. The Census Bureau has not yet released August rates.

Luckily, this project and others in the Kingwood Area could potentially accelerate soon.

Status of Preliminary Engineering Review on Taylor Gully

Idcus should be done with the Taylor Gully preliminary engineering review this fall. However, the Idcus contract does not include design of the detention basin that Sprint is working on. According to Alan Black, HCFCD Director of Operations, that design will need to go under a separate contract.

Funding for Design and Construction

That’s because US Congressman Dan Crenshaw secured a $1.6 million earmark earlier this year that will pay for design. Crenshaw has also requested another $10 million earmark to complete the actual construction of the Woodridge Basin when design is finalized.

According to Black, HCFCD can’t just extend the Idcus contract. HCFCD will have to start over with a request for qualifications (RFQ) for final design of the Woodridge Village detention basin and other improvements along Taylor Gully.

“That’s because the money that we’re going to use is coming from this year’s earmark from Congressman Crenshaw,” said Black. “Because federal funds are involved, we have to issue a new RFQ. We can’t use the consultant we already have just by default. So it will take us a little bit longer. By the end of this year or the beginning of next, we need to get a consultant selected, based on qualifications, once those grants come to fruition. In this case, they will be through the EPA.”

Other Crenshaw Requests to Help Lake Houston Area

As reported last night, in the immediate future, funding for projects in the Lake Houston Area will likely have to come from the Federal, State or City governments. Crenshaw has requested $10 million for construction of the Woodridge Basin, $8 million for the Lake Houston Dam Spillway Improvement Project, and another $10 million to construct another detention basin along Cedar Bayou. Crenshaw already secured another $1.6 million for final engineering of improvements to the Kingwood Diversion Ditch.

Posted by Bob Rehak on 9/2/22

1830 Days since Hurricane Harvey