Entergy Ignores City Deadline to Move Northpark Power Lines

Today, Entergy missed yet another deadline in a long series of deadlines to move its power lines to make room for Northpark Drive expansion.

On February 6, the City of Houston sent a letter to Entergy, demanding that the company move its power lines out of the City’s right of way within 30 days. That would have given them until March 8 to comply. But as of today, March 9, 2024, not one of the poles had moved.

The City’s agent, Lake Houston Redevelopment Authority/TIRZ 10, first asked Entergy to move the poles four years ago. This is just another in a long line of disappointments that have delayed the Northpark Drive Expansion Project – driving up taxpayer costs, increasing flood risk, and snarling traffic.

Last month, Entergy refused to provide ReduceFlooding.com with a copy of its response to the City. And today, Entergy did not return a phone call explaining why the company ignored the City deadline.

Before/After Photos

Here’s how the north-side/west-bound expansion area near the UP tracks looked before the City sent its demand letter.

Entergy power poles in the way of Northpark expansion
Photo taken Jan. 13, 2024, before City sent letter to Entergy.

And here’s how the same area looked this morning. Not one pole has moved as a result of the City’s February 6 letter.

Photo taken around noon on March 9, more than 30 days after letter was sent. Nothing has moved.
Reverse angle. Looking E along Northpark at endless backups and poles still in original locations. Also taken March 9th.

As I took these photos Saturday near noon, traffic was backed up more than a mile!

Clash over Cash

In the past, Entergy asked for compensation to move its poles. But according to an LHRA spokesperson, compensation is not allowable under Texas law because the poles were in a City right of way and not covered by an easement. Thus, any payment would have constituted a “gift of public funds,” which the Texas Constitution prohibits. 

Entergy was, however, legally entitled to compensation for moving buried wires in an easement near the Exxon station at US59. Entergy had agreed to move them for $711,000 near Christmas last year. However…

Entergy still has not moved buried wires or a transformer near the Exxon station at US59.

…within days after the disagreement about payment for relocating the poles, Entergy’s asking price to move the underground wires mysteriously increased by half a million dollars. Simultaneously, their cost estimate went from line item to lump sum – without itemization. Since then, the asking price has increased another $200,000 without explanation.

Previous Communications with Entergy

City of Houston held Utility Coordination Meetings with Entergy on 10/8/20, 12/10/20, 01/14/21, 2/11/21, 3/11/21, 2/10/22, 3/10/22, and 4/14/22.

In addition, the City also emailed Entergy’s Utility Relocation consultant on 12/07/20, 06/21/21, 06/30/22, 07/22/22, 08/19/22, 09/20/22, 10/21/22, 01/11/23, 01/24/23, 03/03/23, 05/17/23, 07/19/23, 08/23/23, 10/16/23, 10/26/23, 12/01/23, and 12/13/24, 01/16/24.

I don’t care to speculate on the motives for Entergy’s lethargy. However, I’m pretty certain that if this goes to court, the entire project could be delayed years.

You can draw your own conclusions and point fingers where you will.

If there was ever any doubt, Entergy now knows that one of the main goals of Northpark Expansion is to provide an all-weather evacuation route for 78,000 Kingwood and Porter residents. Personally, I hate feeling like a pawn in Entergy’s game.

Posted by Bob Rehak on 3/9/24

2384 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

TxDOT, LHRA Engage Kingwood at Northpark Phase II Meeting

On 3/7/24, TxDOT, the Lake Houston Redevelopment Authority/TIRZ10 and the City of Houston hosted an open house at the Kingwood Community Center to share detailed project plans at a Northpark Phase II Meeting. The informal “come-and-go-when-you want” style of the meeting gave authorities a chance to mingle with residents and solicit their feedback on plans.

Two hundred and forty-six people attended the Phase II meeting in person or virtually.

Objectives of Project

In addition to reducing traffic congestion, one of the main goals is to elevate Northpark Drive above the 100-year floodplain to create an all-weather evacuation route for area residents. Other goals include preparing for anticipated growth and improving pedestrian/bicycle safety.

Different Lanes for Different Pains

As with Phase I, roads will be elevated. Lanes will be both added and widened. Eleven-foot-wide lanes will expand to 12 feet. And 10-foot-wide sidewalks will be added, enabling bicyclists and pedestrians to pass each other easily.

Proposed improvements to Northpark Drive extend from 750 feet east of Russell Palmer Road to 800 feet east of Woodland Hills Drive, in Harris and Montgomery Counties. The project would include the reconstruction and widening of approximately one mile of Northpark Drive from a four-lane to a six-lane roadway.

TXDoT broke Phase II into three sections based on current lane configurations and traffic conditions.

  • Section A starts about halfway between Russell-Palmer and the Kingwood Diversion Ditch and goes up to the Ditch. “A” also includes the Woodland Hills/Northpark Drive Intersection.
  • Section B goes from the Ditch to the start of the Northpark Place Commercial Association.
  • Section C includes businesses inside Kingwood almost to Woodland Hills, where Section A restarts.

The three lanes would include two 12-foot-wide main lanes in each direction; left and right turning lanes; and 1-foot-wide outside/inside shoulders.

The area where the grassy median is today would be repurposed to use as turning lanes or additional travel lanes.

TxDOT

The wooden pylon sign that says “Kingwood” will go. However, according to Dee Price, KSA President, the serpentine wall that heralds “The Livable Forest” would remain after construction.

Reconstruction will also include new signals at the Woodland Hills Drive and Hidden Pines Drive intersections.

To reduce flooding, the project also includes new drainage features, such as open ditches, curb-and-gutter, and one stormwater-detention basin in a location yet to be determined.

See additional details about what will happen in each section in this presentation or these meeting handouts.

Still Time to Provide Public Comment

If you missed the meeting last night, you can still provide public input. Review the materials above and send your comments via:

  • Email to: hou-piowebmail@txdot.gov
  • Mail to:
    • TxDOT Houston District
    • Advanced Project Development Director
    • P.O.Box 1386
    • Houston, Texas 77251-1386

If you own a business along Northpark, don’t miss this preliminary schematic construction diagram that shows rights of way and more plan details.

Business owners especially need to understand how a change in traffic patterns could affect their businesses.

Construction is still several years away. The most likely start date: 2027. Between now and then, project managers will focus on environmental surveys, detailed design, and right-of-way acquisition.

Upcoming Schedule

LHRA has also provided a three-week look-ahead schedule to show you what will happen when.

Two important items on it include:

  • Starting on March 11, one lane will close on Russell Palmer during installation of the temporary signals.
  • The water line to Parkwood Baptist Church which held up construction has now been repaired. A crew will soon splice in the missing piece of culvert with a concrete sleeve to tie adjacent sections together.

For More Information

For more information about the project including Phase I, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 3/8/24

2383 Days since Hurricane Harvey

Preliminary Recommendations for Kingwood Diversion Ditch Announced

On 3/6/24, Harris County Flood Control District (HCFCD) revealed its preliminary recommendations for the Kingwood Diversion Ditch. The recommendations come out of a preliminary engineering report (PER) for the project. And HCFCD is still soliciting public comments.

Recommendations from Preliminary Engineering Report

HCFCD initially considered three alternative scenarios and dismissed one. It then spent most of last night’s meeting comparing the other two and discussing why it preferred one.

The proposed project alternative recommends:

  • Channel conveyance improvements to the Diversion Ditch
  • A diversion structure at the intersection of the Diversion Ditch and Bens Branch to take enough water out of Bens Branch to bring it up from a 2-year level of service to a 100-year level.
  • Bridge replacements at Kingwood Drive, Walnut Lane, Deer Ridge Estates Boulevard and the pedestrian bridge at Lake Village Drive
  • A new outfall to the West Fork San Jacinto River.

The bridges at Northpark Drive will also be rebuilt, but as part of the Northpark Expansion Project.

The ultimate goal of the Kingwood Diversion Ditch Project is to reduce the risk of structural flooding associated with the Bens Branch channel.

HCFCD

Improvements to One Channel Improve Another

The Kingwood Diversion Ditch is a man-made channel that was constructed prior to 1978. The channel diverted excess stormwater from Bens Branch and gave it an alternate route to the West Fork of the San Jacinto River.

The two channels largely operate as one unit. But HCFCD has room to expand the ditch and not Bens Branch. That’s because large portions of the Bens Branch Channel remain natural and are flanked by greenbelt trails, near and dear to the hearts of residents.

The Kingwood Diversion Ditch, however, has ample right of way and room for expansion. Even though, the Diversion Ditch operates at 100% of its design capacity, expansion of the Diversion Ditch can reduce the water surface elevation along Bens Branch without destroying the natural character of the stream.

The two alternatives that made the initial cut each recommended widening and deepening the Diversion Ditch channel. Exact dimensions/increases, however, will not become clear until final construction plans are developed.

Proposed widths for the bottom of the channel could vary from 10-80 feet. Top of channel widths could vary from 150-190 feet.

HCFCD said only that widths would vary along different portions of the channel and that, altogether both channels should be able to handle 100-year rains when the project is complete. The Kingwood Area Drainage Analysis revealed that portions of Ben’s Branch flooded in a 2-year rain.

The screen capture below shows benefits of the recommended alternative (#3).

HCFCD recommended Alternative #3 because of savings on maintenance.

Money Not Yet Identified to Fund Improvements

However, money does not currently exist to fund ANY of the three options. Almost seven years after Harvey, only $3.9 million has been committed. But costs are estimated at $54.5 million.

Screen capture from PER review meeting.

HCFCD emphasized that it always looks for funding. The District laid out a sequence of future events. Next steps:

  • Present the preliminary engineering report to commissioners court in two weeks.
  • Commission final design
  • Additional community engagement meeting
  • Secure funding
  • Begin construction

Need for Local Disaster-Mitigation Funding

The funding challenges, almost seven years after Harvey when the sense of urgency has dissipated, underscore the need for communities everywhere to plan for their own flood mitigation.

We can’t expect the federal government to ride to the rescue for every issue in every community. People in Kentucky don’t want to pay for our Diversion Ditch any more than people in Kingwood want to pay for a Diversion Ditch in Kentucky.

Still Time for Public Comment

You can see video of the meeting and the full presentation here. HCFCD will accept public comments through March 20:

  • At hcfcd.org/F-14, or
  • Via phone at 855-925-2801 with Meeting Code: 6701

Northpark Phase II Meeting Tonight

Switching gears, the Lake Houston Redevelopment Authority will hold a separate meeting tonight at the Kingwood Community Center from 5-7PM to discuss plans for the second phase of Northpark Drive Expansion. Hope to see you there.

Posted by Bob Rehak on 3/7/2024

2382 Days since Hurricane Harvey