Northpark Expansion

Northpark Planners Seek to Relieve US59 Feeder Congestion

11/28/25 – Turning from the northbound US59 feeder these days onto eastbound Northpark Drive can test one’s patience. Last Wednesday – near midday – traffic was backed up for four blocks. And it took several cycles of a very long traffic light to make the turn. See below.

Looking S at traffic backed up on US59 northbound feeder at mid-day on Wednesday, 11/26/25

Note how the two turn lanes on the feeder are temporarily blocked off.

Fortunately, the Lake Houston Redevelopment Authority/TIRZ 10 is actively working on solutions to the problem.

Why Northbound Turn Lanes are Closed

The two northbound turn lanes are blocked off because of the current shortage of inbound merging lanes on Northpark. Four lanes of traffic (two turning and two coming from under the freeway) must squeeze into two lanes. And those two lanes swerve within feet of the intersection. See below.

Looking W at US59 from over Northpark. Note step-shaped piece of old pavement near intersection.

Reportedly, the new paving stopped short of the freeway at this location to avoid a closure of the road for inbound traffic.

But at some point that odd “step-shaped” area of old concrete and blacktop will have to be replaced with new concrete. And at this point, project manager Ralph De Leon thinks that should happen sooner rather than later. So he’s looking at alternatives.

“This odd area of original concrete immediately east of the intersection of the I-69 and Northpark is the issue,” said De Leon. “It needs to be torn out and replaced with new concrete. And due to its difficult location, the contractor has held off. They will probably need to close that area beginning on a Friday night, reopening on a Sunday. It will take three days.”

Engineers Studying Fix

De Leon added, “The engineers are evaluating shifting the inbound traffic northward to the current outbound lanes while the activity is taking place.  Thus, instead of four westbound lanes, they will go down to two lanes both directions, but only for the weekend. And after that, we are good for the remainder of the project,” he added. 

The engineers and contractor are also looking at creating “merge lanes” further to the east. They would be located roughly in the vicinity of What-a-Burger. Moving the merge area eastward, away from the intersection may improve safety. 

De Leon says the engineers are now working on a Traffic Control Plan. However, before they can implement it, the contractors we will need to fabricate traffic signs that guide traffic to the merging lanes.

Regardless of which option the engineers recommend, that odd shaped piece of old pavement will need to shut down from a Friday night to a Sunday afternoon to replace the old concrete with new panels.  The wider shot below shows where turning traffic could merge.

Looking W from farther back shows where traffic turning off US59 could merge with other inbound traffic.

Reconstruction of a major thoroughfare is never easy. However, when this is complete, it will provide major improvements to both mobility and safety.

Posted by Bob Rehak on 11/28/25

3013 Days since Hurricane Harvey