Northpark Contractors Start Boring Under Railroad Tracks
5/17/25 – Contractors have finally started boring under UnionPacific Railroad (UPRR) tracks to connect Northpark drainage east and west of Loop 494. That crucial connection is a key to beginning many other parts of the Northpark expansion project.
Lake Houston Redevelopment Authority first contacted UPRR about running Northpark drainage under their tracks ten years ago. And for those keeping track, it was eight years ago that the two parties signed their first contract.
Fifth Contract is the Charm
If you’re wondering why it’s taken so long, the two parties are now working on their fifth contract. But all that is in the past. So are the special UPRR training sessions that contractors and LHRA staff had to attend. So is the years-long wait for UPRR to weld single 200-foot-long sections of track into place across the ten lanes of Northpark.
All energies are positive now and the project is moving forward.

One Pole Blocking Bore Must Move
Note, however, a CenterPoint pole is still in the way. See below.

CenterPoint needs to transfer the energized lines from the existing wood poles on each side of Northpark to the newly installed and adjacent fiberglass poles. Those are designed to route the electricity underground at that location – out of the way of the bridge. Once electricity is rerouted, the old pole blocking progress can be removed.
Yesterday, I received word from City Councilman Fred Flickinger’s District E office that CenterPoint and UPRR are close to signing a contract that will let CenterPoint enter UPRR’s right of way to move the pole. Good news!

Steel, Not Concrete Pipe Needed
After completing the bore pit, contractors will run six-foot steel pipes under the tracks. The tolerance is exceedingly tight. The tracks cannot move more than one-quarter inch despite the weight and vibration of mile-long trains carrying heavy loads. Hence the steel.

Bore Pit Built Like Underground Fortress
From the ground, construction of the bore pit looked like this.



Junction Boxes Will Tie Drainage Together
When this operation is complete, we will have two junction boxes on either side of the tracks.
Some time ago, a third junction box was placed underground near the Shell station on the opposite side of Loop 494. Before contractors paved the new southbound lanes on Loop 494, they already connected giant 8’x8′ reinforced concrete pipe under the paving. So now, all they have to do is connect that to the center junction box west of the tracks (foreground above).
Contingent Operations
Many subsequent operations rely on the successful completion of the bore under the tracks. They include:
- Completing detention ponds at US59.
- Routing drainage to Ditch One behind the businesses north of Northpark.
- Paving northbound lanes on Loop 494.
- Paving westbound lanes on Northpark from Russell-Palmer Road to the railroad.
- Building the bridge over the railroad tracks and Loop 494.
Posted by Bob Rehak on 5/17/25