Railroad Commission Completes First Part of Noxxe Cleanup in Forest Cove Already
The Texas Railroad Commission (TRRC) completed the first part of the Noxxie Oil & Gas post-Harvey cleanup on Tuesday, 1/19/21, just hours after the operation started. TRRC contractors began early in the morning near the Forest Cove Townhomes on Marina Drive. By 11 a.m., they had removed the heater treater; begun dismantling two storage tanks; and loaded up rusted pipe and twisted scaffolding. Before the end of the day, they had scarified the site and cleaned up after themselves. Scarification involves cutting and removing debris by breaking up the surface of the soil.
Before, During, After Pictures
Here’s what the Marina Drive area looked like before, during and after the cleanup there.
Plugging of Old Wells Scheduled in Two Weeks
Two pump jacks near the tanks remain. TRRC plans to remove those and plug the wells with a separate crew in a couple weeks, depending on the crew’s availability. That crew was responding to an emergency involving a potential blowout with some wells near Corpus Christi this week.
By Wednesday morning, operations had shifted to the far larger portion of the Noxxe field south and east of the Forest Cove little league fields. Dean Southward, a TRRC spokesperson and project manager, estimates cleanup of that area will take approximately two weeks.
The wells on the eastern portion of Noxxe’s lease will be plugged at the same time as the others near Marina Drive.
Posted by Bob Rehak on 1/22/2021