One month into the 2019 hurricane season, only about 23 percent of the Woodridge Village Detention Ponds have been substantially excavated and have outflow control devices installed. At the time of the May 7th Elm Grove flood, that percentage was only 9 percent. So in a little less than 2 months, Rebel Contractors has more than doubled the percentage completed. However, as we head toward the peak of hurricane season, approximately three quarters of the detention capacity remains unexcavated, dysfunctional, or both.
Contractors also have yet to finish grading, planting, and cementing portions of the ponds that they have excavated.
Only 2 of 5 Detention Ponds Substantially Excavated
The first phase of the 268-acre Woodridge Village shows a total of 4 detention ponds. But Rebel Contractors has excavated only two on the southern end so far: S1 and S2.
Together they provide a total of 49 acre-feet of storage. Pond N1 has not yet been excavated and Pond N2 does not yet have an outflow control device that will retain the water upstream from Elm Grove.
Detention for Phase 1 of Woodridge Village
In Phase 1, Pond N2, has no additional excavation. Existing excavation was done by Montgomery County starting in 2006. The county removed approximately 3-4 feet of dirt in a 20 acre area. Ultimately, N2 will be the largest pond in the development with 154.7 acre feet of detention. Note: the figures quoted below differ slightly from those I quoted earlier because LJA Engineers presents conflicting data in its Drainage Impact Analysis for Montgomery County.See pages 7 and 54.
UltimateDetention for Woodridge Villagefrom Page 7 of the document titled Report Addendum-2027-1002.N2 currently covers about 10 acres to a depth of 6-8 feet. However, it will be enlarged and deepened so that it holds 154.7 acre feet.That’s more than half of all the detention on the property.
Ultimately, the 5 ponds will have a total of 271 acre feet of storage. An acre foot covers one acre to a depth of one foot. So the five ponds will hold a little more than one foot of rainfall per acre of development.
Woodridge Village Detention by Pond in Ultimate Phase
That means, 12 inches of water should be able to fall on the entire development without flooding any adjoining properties. But with only 23% of detention functional (S2 – green, and S1 – blue), that 12 inches of detention is effectively reduced to 3 inches right now.
How Much is Functional and Where?
The bullet points and pie chart below summarize the total storage and current status of each pond as of July 1, 2019. The figures for acre-feet are taken from the map above representing the ultimate phase of development.
N1 = 13.2 acre feet (not started)
N2 = 154.7 acre feet (started by Montgomery County circa 2002, but is not fully excavated, nor is there any outflow control device installed to detain water upstream of Elm Grove)
N3 = 42 acre feet (does not appear to be started)
S1 = 18.6 acre feet (mostly functioning, but not fully finished)
S2 = 42.5 acre feet (mostly functioning, but not fully finished)
Total detention when complete = 271 acre feet
Total detention not functional as of July 1, 2019 = 77%
Video of Woodridge Village Detention Pond S2 shot from north of Village Springs in Elm Grove at end of June. Courtesy of Jeff Miller.This shot, also by Jeff Miller, gives you a sense of the scale of the S2 detention pond.Remember, as large as it looks, it’s only designed to hold 16% of the runoff above it.Taylor Gulley below the concrete box culvert that controls the outflow from S2 is becoming badly silted.Those openings are each supposed to be 10′ x 6′. They look far less than that right nowbecause of the sediment.
N2 Will Contain More than Half of All Detention
Google Earth image showing the triangular shaped N2 detention area in March of 2011.This land was partially excavated by Montgomery County circa 2006-2012. The developer plans to widen and deepen it, but has not done so yet.Google Earth image showing same area in February of 2019.According to MCAD-tx.org, Montgomery County still owns the triangular area that will become Detention Pond N2.This is what N2 looked like at the end of May. It had not changedsince the May 7th flood.N2 from the reverse angle looking south on 7/1/19. Still no appreciable change.
N1 – Still No Excavation
This is where the N1 detention pond should be on the north section near the Webb Street entrance.No excavation in sight.
N3 – Still No Excavation Visible
Likewise, no excavation is visible near where the N3 pond should be.
In Phase 1, Figure Four, a subsidiary of PSWA and Perry Homes, will develop 30 acres in the northern section and 58 acres in southern section. Ponds N1, S1 and S2 are to be built during this phase.
The hydrologist notes that a portion of N2 is already in place (although there is nothing there yet to detain the water upstream from Elm Grove). She also notes that:
N2 will be widened during the Ultimate phase
A pilot channel within N2 and the E-W channel immediately downstream will be graded during Phase 1 to provide flow-line continuity with other proposed structures.
A concrete lined channel on the eastern side of the subdivision will be extended 150′ between the E-W junction and a 36″ plastic pipe.
Much work remains before their tables and charts on water flow can be used.
Remember, per their own report, the larger portion of Woodridge Village is in the north. It comprises two thirds of the development and the ground there slopes 10 times greater than the southern portion. (1 degree vs. 0.1 degrees).
The Woods are Gone, But We’re Not Out of the Woods Yet
As Elm Grove resident Jeff Miller said, “It sure seems to me that once they clear cut the north, that the potential for flooding rose exponentially.”
Let’s see!
More clear-cut area.
No functional detention.
Sloping toward Elm Grove.
And only one fourth of the total detention installed on the southern section.
I would agree.
As we approach the second anniversary of Harvey in 7 weeks, everybody on the periphery of this development is on edge…no pun intended.
Montgomery County needs development rules that protect neighbors from such development practices.
Posted by Bob Rehak on 7/1/19with help from Jeff Miller
671 Days since Hurricane Harvey
All thoughts expressed in this post are matters of opinion and safety involving public policy. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2019/07/Phase2-Detention.jpg?fit=1500%2C1191&ssl=111911500adminadmin2019-07-01 23:14:372019-07-02 07:29:30Only 23% of Woodridge Village Detention Ponds Now Functional
Here’s some much needed good news regarding Bens Branch. One small maintenance project began last week and an even bigger one should kick off within the next two weeks. Bens Branch cuts diagonally through Kingwood and drains a major portion of the community.
Bens Branch Between North Park and St. Martha Started Last Week
Last week, Harris County Flood Control crews began excavating Bens Branch from North Park to below the old St. Martha’s church. In recent years, the creek had become badly silted and overgrown with vegetation. When the May 7th rains hit, several local businesses flooded including the St. Martha Catholic School and Kids in Action. County maintenance should soon restore normal conveyance through this area. These photos taken last Friday by Thomas Blailock, a Bear Branch resident, show how badly the creek had become constricted.
Photo of Bens Branch taken from Woodland Hills Bridge on Friday, 6/28/2019. Kids in Action is in background. St. Martha is out of frame on the right. Courtesy of Thomas Blailock.
Another photo courtesy of Thomas Blailock showing how badly Bens Branch was constricted in this area.
Note how shallow the ditch has become. Only the bottom tread of the excavator was visible in this standing water.
Bens Branch South of Kingwood Drive Starts Next Month
Bens Branch at West Lake Houston Parkway immediately south of Amegy Bank.
Excavation of approximately 80,000 cubic yards of sediment should begin in July and last for several months. Prepare for dump trucks on the road for the next few months. It will be inconvenient and dirty, but that’s the price of restoring the conveyance of the creek.
This portion of Bens Branch contributed to the flooding of Town Center, The Enclave, Kingwood Village Estates, Kingwood Greens, the YMCA and Kings Harbor and five apartment complexes. Twelve people in Kingwood Village Estates died as a result of injuring sustained during the evacuation or the stress of losing their homes when they returned.
Jason Krahn, the project manager at Harris County Flood Control said last Friday that, “A recommendation to award Project ID # G103-33-00-X004 – Conveyance Restoration on Bens Branch to Solid Bridge Construction, LLC, has been made, and that recommendation to award is scheduled to be on the Harris County Commissioners Court (HCCC) Agenda for HCCC approval of the recommendation to award on July 9, 2019.”
Once the award has been officially voted on and approved by the Commissioners Court, the Harris County Purchasing Agent’s office will work to obtain the executed contract, and the necessary bonds from the Contractor so that the project can move forward to construction. Expect to see about 40 dump trucks per day (8600 loads in total) on the streets of Kingwood.
Money for both of these projects does not come out of the flood bond. It comes from the Harris County Flood Control District Maintenance Budget.
Posted by Bob Rehak on 6/30/19
670 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2019/06/Blailock-1.jpg?fit=1500%2C1125&ssl=111251500adminadmin2019-06-30 21:28:512019-06-30 21:29:01Maintenance and Construction Work Beginning on Bens Branch
HFD high water rescue truck trying to save Kingwood homeowners on May 7th.Perry Home’s subsidiaries and Revel Contractors are now suing the victims.
Posted by Bob Rehak on 6/28/2019
668 Days since Hurricane Harvey
Thoughts expressed in this post represent my opinions on matters of public policy. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2019/05/Rescue-Truck-1.jpg?fit=1500%2C729&ssl=17291500adminadmin2019-06-28 19:42:502019-06-28 19:42:58Tribune Story about Elm Grove Flooding Says Defendants Now Suing Flood Victims
Only 23% of Woodridge Village Detention Ponds Now Functional
One month into the 2019 hurricane season, only about 23 percent of the Woodridge Village Detention Ponds have been substantially excavated and have outflow control devices installed. At the time of the May 7th Elm Grove flood, that percentage was only 9 percent. So in a little less than 2 months, Rebel Contractors has more than doubled the percentage completed. However, as we head toward the peak of hurricane season, approximately three quarters of the detention capacity remains unexcavated, dysfunctional, or both.
Contractors also have yet to finish grading, planting, and cementing portions of the ponds that they have excavated.
Only 2 of 5 Detention Ponds Substantially Excavated
The first phase of the 268-acre Woodridge Village shows a total of 4 detention ponds. But Rebel Contractors has excavated only two on the southern end so far: S1 and S2.
Together they provide a total of 49 acre-feet of storage. Pond N1 has not yet been excavated and Pond N2 does not yet have an outflow control device that will retain the water upstream from Elm Grove.
In Phase 1, Pond N2, has no additional excavation. Existing excavation was done by Montgomery County starting in 2006. The county removed approximately 3-4 feet of dirt in a 20 acre area. Ultimately, N2 will be the largest pond in the development with 154.7 acre feet of detention. Note: the figures quoted below differ slightly from those I quoted earlier because LJA Engineers presents conflicting data in its Drainage Impact Analysis for Montgomery County. See pages 7 and 54.
Ultimately, the 5 ponds will have a total of 271 acre feet of storage. An acre foot covers one acre to a depth of one foot. So the five ponds will hold a little more than one foot of rainfall per acre of development.
How Much is Functional and Where?
The bullet points and pie chart below summarize the total storage and current status of each pond as of July 1, 2019. The figures for acre-feet are taken from the map above representing the ultimate phase of development.
Photos and Video of S2 as of End of June 2019
Jeff Miller shot his video of S2, the pond immediately north of Village Springs in Elm Grove. It shows what progress looked like at the end of June. The pond has been widened by sloping the sides even more since the last update.
N2 Will Contain More than Half of All Detention
N1 – Still No Excavation
N3 – Still No Excavation Visible
Much More to Come Per Hydrologist’s Report
In Phase 1, Figure Four, a subsidiary of PSWA and Perry Homes, will develop 30 acres in the northern section and 58 acres in southern section. Ponds N1, S1 and S2 are to be built during this phase.
The hydrologist notes that a portion of N2 is already in place (although there is nothing there yet to detain the water upstream from Elm Grove). She also notes that:
Much work remains before their tables and charts on water flow can be used.
Remember, per their own report, the larger portion of Woodridge Village is in the north. It comprises two thirds of the development and the ground there slopes 10 times greater than the southern portion. (1 degree vs. 0.1 degrees).
The Woods are Gone, But We’re Not Out of the Woods Yet
As Elm Grove resident Jeff Miller said, “It sure seems to me that once they clear cut the north, that the potential for flooding rose exponentially.”
Let’s see!
I would agree.
As we approach the second anniversary of Harvey in 7 weeks, everybody on the periphery of this development is on edge…no pun intended.
Montgomery County needs development rules that protect neighbors from such development practices.
Posted by Bob Rehak on 7/1/19 with help from Jeff Miller
671 Days since Hurricane Harvey
All thoughts expressed in this post are matters of opinion and safety involving public policy. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
Maintenance and Construction Work Beginning on Bens Branch
Here’s some much needed good news regarding Bens Branch. One small maintenance project began last week and an even bigger one should kick off within the next two weeks. Bens Branch cuts diagonally through Kingwood and drains a major portion of the community.
Bens Branch Between North Park and St. Martha Started Last Week
Last week, Harris County Flood Control crews began excavating Bens Branch from North Park to below the old St. Martha’s church. In recent years, the creek had become badly silted and overgrown with vegetation. When the May 7th rains hit, several local businesses flooded including the St. Martha Catholic School and Kids in Action. County maintenance should soon restore normal conveyance through this area. These photos taken last Friday by Thomas Blailock, a Bear Branch resident, show how badly the creek had become constricted.
Bens Branch South of Kingwood Drive Starts Next Month
For the last two months, Harris County Flood Control has also been compiling specs, soliciting vendors and receiving bids for the excavation of Bens Branch between Kingwood Drive and about 1000 feet north of the West Fork San Jacinto River. That area has also become badly silted.
Excavation of approximately 80,000 cubic yards of sediment should begin in July and last for several months. Prepare for dump trucks on the road for the next few months. It will be inconvenient and dirty, but that’s the price of restoring the conveyance of the creek.
This portion of Bens Branch contributed to the flooding of Town Center, The Enclave, Kingwood Village Estates, Kingwood Greens, the YMCA and Kings Harbor and five apartment complexes. Twelve people in Kingwood Village Estates died as a result of injuring sustained during the evacuation or the stress of losing their homes when they returned.
Jason Krahn, the project manager at Harris County Flood Control said last Friday that, “A recommendation to award Project ID # G103-33-00-X004 – Conveyance Restoration on Bens Branch to Solid Bridge Construction, LLC, has been made, and that recommendation to award is scheduled to be on the Harris County Commissioners Court (HCCC) Agenda for HCCC approval of the recommendation to award on July 9, 2019.”
Once the award has been officially voted on and approved by the Commissioners Court, the Harris County Purchasing Agent’s office will work to obtain the executed contract, and the necessary bonds from the Contractor so that the project can move forward to construction. Expect to see about 40 dump trucks per day (8600 loads in total) on the streets of Kingwood.
Money for both of these projects does not come out of the flood bond. It comes from the Harris County Flood Control District Maintenance Budget.
Posted by Bob Rehak on 6/30/19
670 Days since Hurricane Harvey
Tribune Story about Elm Grove Flooding Says Defendants Now Suing Flood Victims
Nothing like kicking people when they’re down. Evidently the defendants feel the victims should have solved their own flooding problems. Read this Tribune story and weep. http://www.ourtribune.com/headlines/22147-suit-filed-in-elm-grove-flooding.html.
Posted by Bob Rehak on 6/28/2019
668 Days since Hurricane Harvey
Thoughts expressed in this post represent my opinions on matters of public policy. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP statute of the Great State of Texas.