Can HCFCD Finish DR Projects Worth $323 Million Before Deadline?

8/3/2025 – HCFCD is running out of time to bid and complete Community Development Block Grant Disaster Relief projects before a firm and looming deadline. The county could lose hundreds of millions of dollars in aid if it misses the deadline. Yet, it won’t even bid most of the projects for months.

Where Has the Time Gone?

Former Texas General Land Office Commissioner George P. Bush first announced hundreds of millions of dollars in HUD Community Development Block Grant funds for Harris County in May 2021. But it took Harris County almost four years – until January 25, 2025 – to finalize its list of projects for GLO approval.

While it took Harris County years to develop its list, it took the GLO approximately four months to review and approve 10 of the ll disaster-relief (DR) projects on it. DR projects all have a tight, firm deadline of February 28, 2027 – just 19 months away.

But subtract from those 19 months three to six months for bidding and mobilizing a project. Also subtract another two months for closing it out and turning in all the billing. That means you’re losing another five to eight months out of the 19 months. But some of these jobs could take years to complete.

The Greens Bayou Mid-Reach Program, for instance, is huge. It could require several years to build according to one construction expert I consulted.

In September, 2023, HCFCD held a press conference celebrating the funding of the TC Jester Stormwater Detention Basins. But that won’t even go out for bids until the fourth quarter of this year.

And even though it’s not part of the DR package below, another project is also illuminating. HCFCD awarded the bid on the Mercer Basin construction contract on August 4, 2023. It’s comparable in size to many of these projects and construction is still not finished.

Only One Project Bid So Far

So far, HCFCD has announced only one bid award among the group of 11 CDBG-DR projects. That’s for the Arbor Oaks detention basin on White Oak Bayou. And that should begin construction any day now if it hasn’t already.

Ten Others Could Take Months to Start Bidding

The latest bid outlook sheet posted on HCFCD.org shows when the ten other disaster relief projects in the HUD package should be advertised for bids.

It typically takes three to six months from when HCFCD first advertises a project until the winning bidder starts turning dirt. For instance, the county’s purchasing database shows that HCFCD advertised Arbor Oaks beginning April 18, 2025 – 3.5 months ago.

Using these examples as barometers, HCFCD will have little time to complete some of the jobs above. And the county could lose hundreds of millions of dollars.

Who’s to Blame?

We haven’t lost the money yet. But when/if the house of cards collapses on itself, I suspect the head of HCFCD and the county officials who hired her will start pointing fingers at each other.

Shortly after Dr. Tina Petersen took over as Executive Director of HCFCD, I had a prophetic lunch with her. She told me how she wanted to slow things down and become “more intentional” about the way HCFCD did business. And did she ever slow things down!

  • The previous management team executed projects at twice the speed she is.
  • Adjusted for inflation, she’s now spending at a rate lower than before the 2018 flood bond, with billions at her fingertips.
  • She lost seasoned professionals and replaced them in many cases with political hacks.
  • And she has refused to tap knowledgeable resources in the local engineering community that could have helped her.

Lest this sound like a totally self-inflicted wound, commissioners court sat back and tolerated delays even when she missed deadline after deadline for explanations about a $1.3 billion shortfall in the 2018 bond program and whether CDBG projects were in danger. And in the “mixed-message” department, Commissioners gave her an almost $90,000 raise to $434,000 per year…shortly after publicly lambasting her performance in commissioners court.

Posted by Bob Rehak on 8/3/2025

2896 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

After Five Weeks, Culverts under Kingwood Drive Still Clogged

8/1/2025 – After a month of supposedly working to restore conveyance of blocked culverts under Kingwood Drive, the culverts remain blocked and crews seem in no hurry to remove the sediment. They may be disputing whether they were hired to do that.

City Met With Community Representatives in June

Five weeks ago, on 6/24/2025, representatives of the Houston City Council District E office, Houston Public Works, Kings Forest and the Bear Branch Trail Association met to discuss clearing a ditch that had not been cleaned out for more than 20 years.

The ditch cuts through Kings Forest between Valley Manor and Twin Grove, next to Kingwood High School. Then it crosses under Kingwood Drive and empties into Kingwood Lake.

Valley Manor Ditch
Ditch has no name. Just a number – G103-35-01.

One week after City and community representatives met, a contractor started clearing trees around the ditch.

Looking north up the ditch from over Kingwood Drive.

However, after a full month, the contractor has yet to address the ditch itself, especially the critical blocked culverts under Kingwood Drive. And crews appear to be on hold. Activity has virtually ceased.

Confusion Re: Scope of Work

In talking with the contractor and the City, it has become clear that there is a misunderstanding regarding the project scope. No one at the City will send me the scope document or a contract outlining responsibilities despite repeated requests – both in person and via email. And the contractor keeps saying, “Talk to the City.”

The best I’ve been able to get is a suggestion that the scope may have been “vague.” Meanwhile, equipment has been mostly idle for two weeks.

The contractor has seven work days left before school starts on August 13. At that point, the logistics of working around thousands of high school students will make the work infinitely more complicated because of the need to close down at least one lane of Kingwood Drive.

Blockages Under Kingwood Drive Remain

Restoring conveyance will require removing lots of muck from areas around the culverts and in the median itself.

North of the westbound lanes on Kingwood Drive, culverts are half blocked with sediment. See below.

Entry to culverts leading to median. Water drains toward top of frame.
Exit from same culverts. Looking N across median toward westbound Kingwood Drive.
Looking S again at opposite side of median. Eastbound lanes in distance.

Clearly, plenty of sediment must be removed before conveyance of the culverts is fully restored. Based on the photos above, I estimate conveyance has been reduced 50 percent.

Half of Outfall Blockage Remains

The first photo below shows what the outfall on the south side of Kingwood Drive looked like before the start of work at the end of June. The second shows what it looked like today.

Before start of project on 6/29/25.
Today.

Comparing the pre- and post shots, it appears that the contractor removed half the sediment blocking the outfall. One of the workers told me they intended to finish this portion of the job. However, he didn’t know what they intend to do about the median and culverts. He also said they had finished removing brush.

Waiting On…?

For the past few days, I’ve seen unmarked contractor vehicles parked next to the job site. Periodically, someone leaves one and walks into the woods. One even sat in the excavator above while I photographed it.

But as of quitting time today, the excavator had not moved. I went back and checked it three hours later.

To my knowledge, it has not moved for several days. It’s hard to imagine why workers would go to work and not work.

City Council Member Fred Flickinger has vowed to find out next week whether the City is being billed for downtime.

Posted by Bob Rehak on 8/1/25

2894 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Major Northpark Traffic Change Coming Next Week

7/31/2025 – According to the Lake Houston Redevelopment Authority website, contractors will soon move all eastbound traffic on Northpark Drive between Italiano’s and GS Tire & Auto to newly constructed lanes on the south side of the thoroughfare. This will eliminate two major swerves within 3,000 feet and straighten out inbound traffic east of Loop 494.

The Lake Houston Redevelopment Authority website indicates the change will happen on the night of 8/5/2025. However, I have been unable to confirm that.

Photos of Lane-Change Areas Taken Today

All photos below were taken today starting from the east and moving west.

Looking West from G&S. Inbound traffic will move to the south (left).

The shift to the south will go past Russell Palmer … all the way to Italiano’s.

Looking west from Russell Palmer (lower left). From this point, traffic in BOTH directions will shift south and demo of old outbound lanes will begin.
Still looking west. This detour will also straighten out. Italiano’s is out of frame in upper left. Through this stretch, traffic in both directions will shift left (south)

After contractors open up the new eastbound lanes, they will shift westbound traffic to the south from NextCare Urgent Care to Russel Palmer. They will then begin demolition of the old westbound lanes between those two points.

Use extra caution as people get used to the changes and as traffic increases with people returning from vacation.

Bore Under Railroad Tracks Still Stalled

For several weeks now, boring for the twin 60″ pipes underneath the UnionPacific Railroad Tracks has been stalled due to the discovery of utility conflicts. The Lake Houston Redevelopment Authority website simply says, “All work on UPRR ROW has been halted due to further unknown conditions found in the field on 7/25/2025.”

The originating pit for the bores east of the UnionPacific tracks.
A few feet west of the tracks, the bores have not yet reached the receiving pit.

The project planners intended to convey excess stormwater west of the tracks under them to the Kingwood Diversion Ditch and Bens Branch. But contractors must resolve the utility conflicts (shown above) and place junction boxes for the drainage in both pits before they can connect the drainage on each side of the tracks.

So close and yet so far. Only a few feet separate the two pits. But the utility conflicts are holding up a major part of the job.

Loop 494 Progress

Meanwhile contractors have made good progress on Loop 494 both north and south of Northpark.

Looking S across Northpark at new northbound lanes (left) one of which is mostly finished..

Looking north from the other side of Northpark…

Contractors have begun placing rebar to expand the roadbed.

After crews finish paving the northbound lanes of Loop 494, they will begin the eastbound lanes of Northpark west of Loop 494.

Between 59 and Loop 494

Between Loop 494 and 59, contractors are currently placing junction boxes for drainage underneath where the inbound surface lanes will go. Today, you could see them placing one of the boxes in front of Whataburger.

Drainage junction box in front of Whataburger on right.

According to the Lake Houston Redevelopment Authority, “They will then move into the center median of Northpark west of LP 494, to begin work on the storm laterals and structures, which include the detention-pond equalizer pipe.” See below.

Recently demolished center section of Northpark will be focus of next phase of drainage work.

To see progress since the last update, compare photos in this post from 7/21/2025.

In Other Northpark News

Crews have started preparing the base for what will become new inbound surface lanes just east of the UP Railroad Tracks.

Looking E across from Public Storage and Dunkin’ Donuts

It’s not easy to see how the pieces of this jigsaw puzzle come together when you’re driving. Keep your eyes on the road and check back here periodically for progress reports.

Yesterday, as I came in on Northpark from 59, it took almost a half hour to get the one block from 59 to Loop 494. Because of the construction near Whataburger, inbound traffic was down to one lane for a short while. But it was back open this morning.

Such closures can be hard to predict and frustrating. To the degree you can, I would try to avoid Northpark during construction hours. But also be sensitive to the hardships placed on local merchants. Go out of your way to patronize them when you can.

Posted by Bob Rehak on 7/31/2025

2893 Days since Hurricane Harvey