Correction to Revised 2025 First-Quarter Flood-Bond Update Story
7/14/25 – I incorrectly reported four totals in my 7/12/25 story about the revised 2025 first-quarter, flood-bond update. I would like to set the record straight. I would also like to apologize to people at the Harris County Flood Control District (HCFCD) and my readers. I take great pains to present accurate, reliable information that readers can count on. And I want to correct the historical record for future reference.
What Happened
In the first iteration of the 2025 Q1 report, I found a billion-dollar discrepancy. HCFCD admitted the mistake and corrected it in the revised report.
While double checking the revised report, I thought I discovered some other inconsistencies between the high-level, summary information at the front and the backup documentation at the end. They included:
- “Bond Funds”
- “Partner Funds”
- “Secured Funds”
- “Funds Spent”
Unfortunately, the discrepancies resulted from an inaccurate automated export of data from a PDF file to Microsoft Excel. Four lines out of hundreds did not translate properly. Using different, third-party software, HCFCD did the same export/import operation and encountered the same problem.

So, the incredibly dedicated person I talked to manually copied and pasted hundreds of figures to double check the totals in a ten-page spreadsheet.
That led to the discovery of the translation error, which explained the inaccurate totals.
During the translation, the programs shrank the size of the type. So, the figures no longer appeared in their proper columns. They also became virtually invisible because of their small size.
New Totals Agree
After hours of checking, I’m confident that the totals in the documentation now agree with the claims in the introduction. For the record:
- 2018 Bond Funds = $2.5 billion
- Partner Funds = $2,697,565,889 (rounded to $2.7 Billion)
- Total Funds = $5,227,103,996 (rounded to $5.2 billion)
- Total Spent to Date = $1,569,557,746.
Questions about Other Figures Still Unanswered
In my 7/12/25 post, I also raised other questions that HCFCD has not yet answered.
First, where does the half-billion dollar increase in work in progress during the first quarter come from? I don’t see it in construction activity on the ground, in bids, or in work approved by Commissioners Court.
Second:
- Where does the $1.3 billion funding shortfall came from that HCFCD Executive Director Tina Petersen claimed in Commissioner Court?
- Why did no mention of the shortfall appear in the 2024 Year-End Bond Update or either of the two first-quarter updates?
A Start on Answers
HCFCD is starting to work on answers to those questions. Regarding the $1.3 billion shortfall, an HCFCD spokeswoman said, “One of the big asks was to produce our (sometimes rough) estimates of unmet need. That fell into two categories:
- Current unmet need – Funding needed to take current projects through construction, even if the bond only originally provided funds for a study or engineering work. A good example of this is the projects included in Bond ID F-14. (Planning, Right-Of-Way Acquisition, Design and Construction of General Drainage Improvements Near Kingwood.)
- Future unmet need – Funding needed to take the next phase of a project through construction. Examples would include engineering work that showed we need channel conveyance improvements and a stormwater detention basin in an area, but we currently only have funding for the stormwater detention basin. Or if studies showed we could construct a four-compartment basin, but we currently only have funding for two compartments.
“That is not how we have managed the bond program to date, so it represented a shift in thinking. These were meant to be high-level estimates for discussion, not an actual estimate of need associated with the bond program.”
Working to Make Financial Reporting More Transparent
In working with HCFCD to resolve these an other questions, I found them very open and collaborative. At this point, I no longer feel they are trying to hide something.
I also have a greater appreciation for the complexities the 2018 bond program. Finding a way to summarize changes in scope on hundreds of projects and Bond IDs is difficult, especially when tracking money from multiple sources. From a communication point of view, it all comes down to inspiring trust instead of raising skepticism.
HCFCD has not yet agreed to any specific changes. But they did accept the challenge to find clearer ways to communicate.”
Posted by Bob Rehak on 7/14/2025
2876 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.