Transparency Issues Undermining Trust in Harris County Government

1/10/25 – Sometimes it seems transparency issues with Harris County government just never cease. For instance…

You go to the Harris County Flood Control District (HCFCD) website to look for “active construction projects” in your area. But the “Active Construction Projects” page is not working. And it hasn’t worked for months.

You wanted to know what HCFCD had done for you before voting on a 63% tax increase they requested. But the latest document posted in the download section of their website is from 2020 – more than four years ago.

Screen capture from HCFCD.org on 1/10/25 at 6:30PM showed last update to Document section was in 2020.

You lead a flood coalition representing hundreds of thousands of people and seeking to participate in public online meetings about flood control. You repeatedly ask for notice of the meetings, but get none.

You file a Freedom of Information Act (FOIA) Request for a preliminary engineering report that HCFCD wants public comments on. But they refuse to give it to you and protest the request to the State Attorney General.

All of these scenarios are real. And current.

The Deeper You Dig, the More You Suspect

What are they trying to hide? Do they really want public input? Are they trying to cover up embarrassing incompetence? Government waste? Is this a case of bureaucratic laziness? Or do they just not want to deal with a public that might dare to disagree.

Two things are certain. The harder you push, the more they talk about how transparent they are. And the penchant for secrecy undermines trust in Harris County Government.

Let’s dissect just one of the examples above – the FOIA request.

Details on Kingwood Diversion Ditch FOIA Request

After Hurricane Harvey, Harris County Flood Control District commissioned a Kingwood Area Drainage Study. Commissioners approved it on August 13, 2019.

HCFCD held a Community Engagement Meeting to discuss the study on October 20, 2020. It found 85% of the storm water runoff from Montgomery County went into the natural channel of Bens Branch rather than being diverted into the Kingwood Diversion Ditch. 

The Drainage Study also found the Bens Branch drainage channel has less than a 2-year level of service. This translates to a greater than 50% chance of structural flooding in any given year. 

Where Kingwood Diversion Ditch splits off from Bens Branch
Looking E at where Kingwood Diversion Ditch (horizontal) splits off from Bens Branch (vertical) just north of Northpark Drive (out of frame to right).

The Drainage Study recommended increasing the conveyance capacity of the Diversion Ditch and completely blocking flow from Montgomery County into the natural channel of Bens Branch through Kingwood. The Study listed improvement of the Kingwood Diversion Ditch and Taylor Gully as the two top priorities to avoid future flooding in Kingwood. 

Excessive flow entering the natural channel of Bens Branch is the root cause of the erosion of the Bens Branch channel. The Diversion Ditch is supposed to siphon water out of Bens Branch, but it’s obviously not working as planned,

After release of the Kingwood Drainage Study, Harris County Commissioners authorized a preliminary engineering study for improvement of the Kingwood Diversion Ditch. Neel-Schaffer, Inc. received the contract on June 29, 2021. The value was $437,685 and specifications called for the report to be issued in 300 days.

Excessive Delays

However, HCFCD held a Virtual Community Engagement Meeting on March 7th, 2024, to discuss the results of this study. This was 982 days after the contract – more than three times the duration specified. 

The stated purpose of the meeting was to obtain questions and solicit public comment. 

To formulate reasonable questions and comments, Chris Bloch, a retired Kingwood engineer and flood fighter, filed a FOIA request on March 6th to obtain the full report. But HCFCD denied his request.

HCFCD said the report was still in draft form and had the County Attorney send a letter to The Texas Attorney General objecting to disclosure of some of the information included in the Preliminary Engineering Report.

The Attorney General allowed HCFCD to keep the draft secret. But public comments on the secret report were due on March 20, 2024, two weeks after the meeting that presented only high-level findings.

Bloch’s beef? “As an engineer familiar with Kingwood drainage conditions, it is impossible to make reasonable questions or comments on a Study which cannot be seen.” He concluded, “It is clear, the priority of improving Kingwood Drainage does not seem to have any urgency.”

Block wrote me on December 14, 2024 about his ordeal.  That was:

  • 283 days after the close of public comments
  • 1,264 days after the contract for the Preliminary Engineering Report was authorized
  • 1,516 days after the Kingwood Drainage Study Community Engagement Meeting.

Block says he requested a meeting with Flood Control personnel responsible for the report, but they did not respond. He still hasn’t received the report.

Ray of Light

There is a ray of light, however. 1318 days after the study was commissioned, HCFCD says they have plans to finally review it with Harris County Commissioners Court on February 6, 2025. HCFCD indicates they may give the report to Bloch after that … if commissioners approve it.

Do you have a similar story about government transparency? Please send it to me using the contact form of this website.

Posted by Bob Rehak on 1/10/25 using information from Chris Bloch

2691 Days since Hurricane Harvey