Entergy Makes Some Northpark Progress, but Significant Issues Remain
Entergy has made more progress on the Northpark Drive expansion project in the last two weeks than in the previous four years. But despite what you see in the photos below, significant issues remain to clear the way for the first all-weather evacuation route from Kingwood.
Some Progress, But…
Last week, Entergy, a $4 billion company in Texas, erected nine new power poles outside of the City’s right of way. This week, their contractor, Primoris Services, started the process of stringing wire. That’s good news. Really!
But unseen obstacles could still delay the project significantly. For instance:
- Who will pay for moving Entergy’s ground-mounted transformer and associated power lines near the Exxon Station at US59? Entergy reportedly still wants the Lake Houston Redevelopment Authority (LHRA) to pay for upgrading and moving the transformer and buried cables. LHRA insists that’s an illegal ask because it would constitute a gift of public funds.
- More power poles remain near Loop 494 that will be difficult to move because of conflicts with new storm drains.
- Entergy must tunnel under rail tracks.
- Entergy reportedly still refuses to commit to completion dates for moving its equipment.
Will Entergy Beat Union Pacific?
If Entergy does not resolve issues near the railroad tracks before Union Pacific crews arrive to install new signals and improve the road bed, the project could be delayed years.
Union Pacific reportedly has two crews that rotate through 27 states handling such issues. If we miss them this year, the Northpark project goes to the back of a very long line, according to Ralph De Leon, Northpark project manager for LHRA.
Entergy has already blown a City deadline to move its equipment by March 8. So they have already missed a 30-day deadline by 42 days. But according De Leon, Entergy still refuses to commit to any completion dates.
Ray of Hope
According to Houston Public Works (HPW), Entergy has assigned a new project manager and team to the project. This could be a sign of good things to come.
HPW Senior Division Manager Patrick Nguyen says the City is working with Entergy to resolve easement issues that could result in construction delays and cost escalation. Mayor John Whitmire, who is committed to seeing the project through, has reportedly asked Nguyen to act as an arbitrator.
In an email received today, Nguyen said that “Entergy has assigned a new project manager along with a team to the project.” While diplomatically expressing hope, he did not elaborate further.
Progress Last Week
All nine poles erected last week had pulleys and rope or cables threaded through them when I took these photos today. According to one expert I talked to, crews will use the rope or cables to “pull wire.”
Compare old and new poles in lower left. Once wire is pulled to a pole, it will be attached to the tip of the insulator.
Moving the poles farther from the street will create room for a six lane bridge plus two turn lanes on each side of the bridge (to meet TXDoT requirements).
LHRA first notified Entergy to move its equipment in 2020. Entergy still won’t commit to a completion date.
Other Northpark News
Contractors are smoothing out the dirt placed over the culverts between the Kingwood Diversion Ditch and Russell Palmer Road.
Northpark will expand inwards. Contractors will pour two lanes of concrete in the dirt-covered area above. If I read the schedule correctly, paving in the area above could start within the next two weeks.
West of Russell Palmer (below), contractors buried almost another hundred yards of 6’x8′ culvert last week. Weather permitting, and if they can keep up that same rate of progress, they should be to the railroad tracks in another three months or so.
However, the culvert will not go all the way to the tracks down the median. As it approaches the point where the bridge starts to rise, it will veer to the right and go under the turn lanes where Entergy is moving back its poles.
For More Information
For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:
- 24/04/07 Northpark Entergy Saga: New Power Poles Slowly Going Up
- 24/04/02 New Entergy Power Poles Finally Arrive on Northpark
- 24/03/29 Northpark Expansion Update; Still No Sign of Entergy
- 24/03/16 First Concrete Poured for Northpark Expansion
- 24/03/09 Entergy Ignores City Deadline to Move Power Lines
- 24/03/08 TXDoT, LHRA Engage Kingwood at Northpark Phase II Meeting
- 24/03/05 Details of Phase II Meeting
- 24/02/27 February ’24 Northpark Expansion Update Including Lane Closures
- 24.02/24 Save the Dates: Public Input Meetings for Diversion Ditch, Northpark Expansion Phase II
- 24/02/20 Entergy Escalates Battle with COH over Northpark
- 24/02/16 Excavation of Second Northpark Detention Basin Well Underway
- 24/02/10 Entergy in City’s Crosshairs, Lane Closures Announced
- 24/02/02 Northpark Tree Transplantation Finished, Drainage Updates
- 24/01/13 Excavation of Northpark Detention Basins Starts
- 24/01/07 What Some Utilities Don’t Understand About the Northpark Expansion Project
- 24/01/04 Northpark Tree Moving Starts; Pond Excavation Next
- 23/12/03 Northpark Expansion Presses Forward While Fighting Entergy Obstacle
- 23/11/17 Contractors Strike Oil at Entry (Illegally dumped years ago)
- 23/11/05 City Approves Northpark Expansion Agreement with Union-Pacific.
- 23/10/26 Project moving forward on multiple fronts
- 23/10/12 Transplanting first tree
- 23/10/02 Clearing of south-side entry for second pond
- 23/09/30 Clearing north-side entry for first pond
- 23/09/23 How plan balances flood mitigation, costs, saving trees
- 23/09/02 New entry design, change in construction plans forced by utility conflicts
- 23/08/17 More drainage for Northpark
- 23/08/02 Ditch clearing stretches halfway to 59 in less than week
- 23/07/25 Northpark construction starts in earnest
- 23/04/13 Groundbreaking
- 22/02/19 Update on expansion project
- 21/07/28 Plan details
Posted by Bob Rehak on 4/19/24
2425 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.