5/19/26 – Contractors working on the Woodridge Village-Taylor Gully Project finally appeared yesterday and started working today. Construction on the site had been paused since November, 2023.
That’s when Harris County Flood Control District (HCFCD) cancelled an Excavation and Removal Contract with Sprint Sand & Clay to apply for a Community Development Block Grant (CDBG) from the Texas General Land Office and US Department of Housing and Urban Development.
This particular CDBG project falls in the Mitigation Category. That means, HCFCD and the contractors have until March 31, 2028 to finish it – about a year and ten months.
History of Project
All this comes seven years after Perry Homes cleared approximately 270 acres on its Woodridge Village property, and sloped the land toward Taylor Gully … without building the required detention basins. Then the flooding problems started. Taylor Gully flooded up to 600 homes twice in 2019, once on May 7 and once in September during Tropical Storm Imelda.
Harris County and City of Houston bought the property from Perry Homes in 2020. That let Sprint Sand & Clay start excavating a giant detention basin on Woodridge. They removed 156,478 cubic yards of sediment. That brought the total detention on the site up to Atlas-14 requirements, But per HUD requirements, HCFCD had to stop Sprint while it applied for a grant, which Congressman Dan Crenshaw helped secure.
However, work stopped before the basin was finished and it was never connected to the rest of the drainage on the site. See below.
Woodridge Village in November 2023 when E&R contract ended. Note storm sewer pipe scattered around excavation.
Sprint removed all that dirt for less than a thousand dollars. The picture above shows how the site looked the day Sprint left. They gave the current contractors a giant head start.
Site Clean Up Started Today
Today, after a hiatus of almost three years, a new contractor started by cleaning up the site. I photographed them breaking up the old storm sewer pipe unearthed by Sprint.
Woodridge Village on 5/19/2026. Note contractors breaking up storm sewers that Perry had installed near detention basin excavation.
I counted three pieces of construction equipment onsite today: a small bulldozer, an excavator that was breaking up the pipe. And a forklift that ferried pipe to the excavator.
Restart of construction on 5/19/2026
I didn’t see any other equipment on Woodridge or along Taylor Gully.
Looking upstream along Taylor Gully from West Lake Houston Parkway toward Rustic Elms and Woodridge.Looking downstream toward the end of Taylor Gully.
What Project Includes
On 10/6/25, the Texas General Land Office (GLO) approved approximately $42 million to construct Taylor Gully Channel Conveyance Improvements and a Woodridge Stormwater Detention Basin.
On 3/26/26, the county purchasing agent approved a $29,387,654 bid from Bryce Construction & Design, LLC to finish constructing the Woodridge and Taylor Gully flood mitigation projects in Kingwood
The Woodridge portion of the project (above the county line) includes 421.6 acre feet of additional stormwater detention capacity (See Compartment 1 above).
Other planned improvements along Taylor Gully include:
13,118 feet of channel conveyance improvements
Placing a concrete channel along the base of it
Replacing the concrete culverts at Rustling Elms with an open-span bridge.
Altogether the plan should reduce the water surface elevation by up to 5 feet and help 24,000 thousand people who live near or commute through the area.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/05/DJI_20260519142939_0131_D.jpg?fit=1100%2C619&ssl=16191100adminadmin2026-05-19 17:37:092026-05-20 13:19:06Woodridge-Taylor Gully Construction Starts Again
3/26/26 – A $29,387,654 bid from Bryce Construction & Design, LLC has been approved by the county purchasing agent to construct the Woodridge and Taylor Gully flood mitigation projects in Kingwood. See Item 45 on the agenda. Here is their bid transmitted to Commissioners Court. It was the low bid.
To streamline approval of US Housing and Urban Development Department Community Development Block Grants (CDBG), several months ago Commissioners Court approved a proposal to let the County Purchasing Agent approve CDBG projects. They all have tight deadlines.
The contractor will mobilize within two weeks according to Emily Woodell, a Harris County Flood Control District (HCFCD) spokesperson. We should see dirt flying this Spring.
History of Project
Up to 600 families in Kingwood flooded twice in 2019 when Perry Homes’ contractors cleared approximately 268 acres for Woodridge Village just north of the Harris County line. Then they sloped the land toward Taylor Gully. Many of the families had just recovered from the first flood on May 7th when they flooded again in September before the stormwater detention basins had been built.
Subsequently, in 2020, Harris County and the City of Houston purchased the land so that it couldn’t be developed and flood Kingwood again. Before the purchase, Perry Homes built five stormwater detention basins on the Woodridge property. However, Montgomery County regulations at the time required much less detention capacity that Harris County – about 40% less.
That was because Harris County had already adopted Atlas 14 and because Montgomery County averaged rainfall estimates across the entire county, even though annual rainfall increases as you move south toward the county line.
Elements of Solution
So, Harris County Flood Control set out to study what it would take to properly reduce flood risk using Atlas 14 data near the county line. The studies recommended:
More upstream detention
Increasing conveyance of Taylor Gully
Replacing a culvert bridge at Rustic Elms with a clear-span bridge
Project overview from construction plans
The project limits of the proposed Taylor Gully Channel Improvements stretch from the Montgomery County boundary on the west to approximately 700 feet upstream of the confluence with White Oak Creek – a length of approximately 12,630 linear feet.
This portion of the project includes replacing the bridge at Rustling Elms.
At Rustling Elms, HCFCD will replace a culvert bridge with a clear-span bridge to remove a bottleneck.
HCFCD also plans to finish one more large stormwater detention basin upstream from Taylor Gully in Montgomery County.
HCFCD started work on the pond in January 2022 under an Excavation and Removal contract with Sprint Sand & Clay. The contract to remove up to 500,000 cubic yards of soil would have more than doubled the previous detention capacity on the site and more than made up for the 40% Atlas 14 shortfall.
However, HCFCD paused the Sprint contract when it applied for a U.S. Department of Housing and Urban Development (HUD) grant. That’s because HUD rules stipulate that a project cannot change during the grant application period.
HCFCD later terminated the contract in November 2023 when it became clear the project would qualify for the grant. At that point, Sprint had already removed 160,000 cubic yards, an amount equivalent to approximately 100 acre feet. So if the figures in the construction drawing are accurate, the capacity of the basin will quadruple compared to what you see below.
Woodridge Village on May 31, 2025. The final basin will extend down past the trees near the end of the entry road.
Expected Impact
Contractually, work must finish within 552 days from the notice to proceed – approximately 18 months. That would make a great 2027 Christmas present for a lot of Kingwood families.
Under HUD’s Community Development Block Grant for Mitigation, all work must finish and billing must be completed by March 31, 2028. That should be doable.
The project will give Taylor Gully a 100-year level of service.
HCFCD
That means it should only come out of its banks in a hundred-year storm.
The improvements would reduce water-surface elevation (WSE) along Taylor Gully up to 6.9 feet in places and 4 to 5 feet on average for a 100-year storm event.
Also, this project will remove approximately 276 structures from a 100-year flood plain. Without the project, area residents would continue to flood in lesser storms.
Taylor Gully bridge at Rustling Elms during May 7, 2019, storm.
That means we should NOT see many more scenes like the one above until Noah’s comeback tour.
Thanks to Precinct 3 Commissioner Tom Ramsey PE, for continuing to push this project when things seemed bleak.
Posted by Bob Rehak on 3/26/26
3131 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/03/Overview.jpg?fit=2550%2C1650&ssl=116502550adminadmin2026-03-26 16:35:252026-03-27 08:08:45$29 Million Construction Contract for Woodridge, Taylor Gully Project Approved
1/28/26 – People living near the Kingwood Diversion Ditch and the Woodridge Village/Taylor Gully area have been asking what happened to their flood-mitigation projects. Good news: Both are moving forward. Here’s some historical context, where the projects currently stand, and what comes next.
Kingwood Diversion Ditch
The Kingwood Diversion Ditch splits off Bens Branch between Northpark Drive and the new St. Martha Catholic Church. It runs down the western side of North and South Woodland Hills past the fire station on Kingwood Drive. Then it continues south past Trailwood, Deer Ridge Park and finally joins the San Jacinto West Fork at River Grove Park. Along the way, it goes under four bridges.
Neel-Schaffer completed a preliminary engineering study in early 2025. The company recommended widening the Diversion Ditch and building a new outfall to West Fork west of River Grove Park. They projected the cost to be almost $41 million, but it would reduce the floodplain size by 177 acres and remove 34 structures from the floodplain.
Diversion Ditch shown in white, proposed new outfall in green, and Bens Branch in red.
The improvements would divert enough stormwater from Bens Branch to take it from a 2-year level of service to a 100-year level. That’s good news for the merchants in Kingwood Town Center. They all flooded during Harvey and 12 seniors died at Kingwood Village Estates.
The project almost died last year when Democratic County Commissioners voted to redeploy all remaining flood bond funds to the highest scoring projects on their equity prioritization framework. However, they later reconsidered that motion. The Diversion Ditch already had federal partnership funds allocated to it thanks to the work of Congressman Dan Crenshaw. His earmark for the Walnut Lane Bridge saved it from the chopping block.
Now the project is moving again. In late 2025, Harris County awarded a contract to Halff Associates, Inc. for the final engineering and design of the project.
In its January 22 board meeting, the Texas Water Development Board authorized an agreement with Harris County Flood Control District for a $5 million grant that State Representative Charles Cunningham obtained during the 89th Legislative Regular Session. (See item 12.)
HCFCD spokesperson Emily Woodell said the District expects the design work to start by March 1. She also says that additional funding will come from EPA grants to cover design and the 2018 bond to cover construction. Woodell expects construction to begin in late 2027.
Woodridge Village/Taylor Gully
The Kingwood Area Drainage Analysis ranked the Diversion Ditch and the Woodridge Village/Taylor Gully Project as the two most important projects in Kingwood because they help the largest numbers of people.
The 270-acre Woodridge Village Project is the aborted Perry Homes development purchased by Harris County and the City of Houston in 2020. It lies north of Sherwood Trails and Elm Grove in Montgomery County. Except for a few acres on the extreme western end, virtually all of it drains into Taylor Gully.
Perry’s contractors clearcut the Woodridge site starting in 2017 and sloped it toward Taylor Gully. Then before they installed detention ponds and drainage systems, runoff from the site flooded up to 600 homes twice in 2019. Residents had not even finished repairing their homes from the first flood in May, when they flooded again in September. A massive class action lawsuit resulted in a substantial settlement for the victims.
Taylor Gully flooding near Rustling Elms on May 7, 2019.
Before purchasing Woodridge Village from Perry, HCFCD stipulated that they had to finish building all of the stormwater detention basins planned as part of the buildout. However, those detention basins only brought the property up to pre-Atlas 14 standards. They fell 40% short of Atlas 14 requirements.
Shortly after the purchase, HCFCD started building an additional detention basin to bring the total detention capacity onsite up to and beyond Atlas-14 requirements. Sprint Sand and Clay began the work under an excavation and removal (E&R) contract. E&R contracts give HCFCD a head start on production. They let contractors begin removing dirt for a nominal fee and then sell it on the open market to make up their profit margin.
Woodridge Village on May 31 2025. The beginning of a new detention basin was never completed or connected.
However, when HCFCD applied for a HUD CDBG-MIT grant through the Texas General Land Office, HCFCD was forced to pause the project. That’s because projects cannot change while the GLO and HUD consider a grant request.
Scope of project outlined in preliminary engineering review. Compartment 1 is in current bid and will take project up to and slightly beyond Atlas 14 requirements. Compartment 2 will be treated as a separate project in the future if/when needed.
Expand a portion of Taylor Gully and line it with concrete.
Build another stormwater detention basin on Woodridge Village holding 412 acre-feet.
Replace the culverts at Rustling Elms with a clear-span bridge.
Fast forward: GLO and HUD approved grants for $42 million in October, 2025. HCFCD put the project out for bids. And proposals are due by Feb. 16, 2026. See screen capture from County purchasing below.
Screen capture supplied by Precinct 3 Engineer Eric Heppen
Even though the bid above is listed as “channel conveyance improvements,” according to Woodell, it also includes the Woodridge Village Stormwater Detention Basin(s). “Since Woodridge mitigates Taylor Gully, those two projects have been combined forever after,” she said.
The HUD/GLO deadline for finishing the project is March 31, 2028. That’s do-able if everyone hustles.
Additional funding for this project came from U.S. Representative Dan Crenshaw. He secured federal funding for Taylor Gully improvements in March 2022. And Representative Charles Cunningham helped secure state funding through the TWDB.
At a September 2024 press conference where Woodridge meets Taylor Gully. Left to Right, Harris County Precinct 3 Commissioner Tom Ramsey PE, US Rep. Dan Crenshaw, HCFCD Exec. Dir. Dr. Tina Petersen, Houston City Council Member Fred Flickinger and State Rep. Charles Cunningham.
More news to follow when we see the bids.
Posted by Bob Rehak on January 28, 2026
3074 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/01/Kingwood-Flood-Mit.jpg?fit=1100%2C670&ssl=16701100adminadmin2026-01-28 14:44:172026-01-28 17:05:33Update on Two Kingwood Flood-Mitigation Projects
3/10/25 – In the last week, Harris County Flood Control District (HCFCD) launched a new interactive map at the bottom of its homepage. In it, HCFCD calls many projects complete that have not even started.
The map supposedly contains the status of each project in the county along with links to more project details.
However, the information is riddled with errors. The map also contains several usability issues that place barriers between people and information.
Together, the issues show a disturbing lack of attention to detail and quality control that undermines the credibility of HCFCD.
Examples of Incorrectly Coded Projects
For instance, you may be pleased to know that the project to add more floodgates to the Lake Houston Dam is “complete.” It’s not. Ask Houston City Council Member Fred Flickinger who just provided an update on the ongoing engineering of the gates.
This and all other screen captures below taken on 3/10/25. Note project status in lower right corner.
Neither are the projects complete to add stormwater-detention capacity to Woodridge Village and to improve Taylor Gully. However, the map shows them completed also.
HCFCD also marked the Kingwood Diversion Ditch Project “in progress.” It’s not.
“None of this information is true!”
– Bob Rehak
With the exception of the Woodridge project, the District has not turned one shovel of dirt on any of the projects above.
The District tabled the Woodridge project in November 2023 when it decided to seek HUD funding to complete it. Here’s how HCFCD left the site.
“Completed” Woodridge Village Detention Basin. Photo taken today, 3/10/25.
HCFCD even marked the TC Jester Detention Basins on Cypress Creek complete.
HCFCD did not respond to questions about the errors, nor did it take the error-ridden, interactive map down as of close of business today.
Usability Flaws, Too
In addition to the project-status errors, the map also contains some serious usability flaws.
For instance, clicking on the link for more information about a project sometimes takes one to a page that asks you to sign into “ArcGIS Online.”
But that requires HCFCD employee credentials.
However, take heart. If you wait several minutes, information may eventually load OFFSCREEN and ABOVE the sign-in prompt…where few would ever bother to look for it. Very clever!
A source familiar with Harris County Universal Services, the county’s IT department, attributed the bizarre performance of the map, in part, to incompetent coders and project managers with forged credentials working on H1-B visas.
That may be an even bigger problem! If you think Elon Musk rummaging through IRS data is an issue, imagine foreign nationals rummaging through your Harris County tax information. But I digress.
In the meeting, Commissioners adopted several measures to limit the financial impact to the county in case DOGE rescinds $1.1 billion of previously promised HUD disaster-relief and flood-mitigation funding.
In the same meeting, Commissioners also demanded an update from HCFCD Executive Director Tina Petersen about the status of every project. The reason: so they could make sure so-called “equity projects” were completed in low-to-moderate income areas before those in more affluent areas.
Precinct 1 Commissioner Rodney Ellis said he didn’t want to wait “until all the money was gone.” He added, “I know there’s not enough money to do all the projects we talked about and everybody else knows it.”
I hope Ms. Petersen provides better information to her bosses than to the public. She just received a $90,000 raise. You could hire several proofreaders for that!
No telling how many errors are embedded in the interactive HCFCD map; I am not familiar with every project in the county. If you know of other errors in projects near you, please send me a note through the contact form on this website.
Posted Bob Rehak on 3/10/25
2750 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2025/03/20230812-RJR_2246.jpg?fit=1100%2C733&ssl=17331100adminadmin2025-03-10 20:29:092025-03-10 23:38:55HCFCD Calls Projects Complete that Have Not Even Started
1/25/25 – Yesterday, Harris County Flood Control District (HCFCD) released two lists ofprojects proposed for $863 million in funding.
The lists correspond to Community Development Block Grants for Mitigation (CDBG-MIT) and Disaster Recovery (CDBG-DR) programs from the U.S. Department of Housing & Urban Development (HUD). The Texas General Land Office (GLO) administers the funds at the state level.
Per HUD rules, at least 50% of the funding for all projects taken together must benefit Low-to-Moderate Income (LMI) citizens. However, HCFCD is working towards a goal of 70% mandated by Harris County Commissioners Court.
Differences Between DR and MIT Funds
Of the total $863 million awarded, $322 million will go to Disaster Recovery programs and $541 million will go to Mitigation programs.
CDBG-DR dollars fund areas impacted by Hurricane Harvey. CDBG-DR projects must be completed by May 31, 2026.
CDBG-MIT dollars fund projects that mitigate future disasters and flooding. They must finish by March 31, 2028.
You can review one-page summaries of each recommended project on these pages:
HCFCD’s release of the lists yesterday opened public comment, which closes at 4:30 p.m. on Monday, February 24, 2025.
Email comments to CDBG@hcfcd.hctx.net or mail them to Harris County Flood Control District, ATTN: CDBG Communications, 9900 Northwest Freeway, Houston, TX 77092.
Only One Project in Lake Houston Area
HCFCD has proposed one project in the Lake Houston Area out of all this money: Taylor Gully Channel Improvements/Woodridge Village Stormwater Detention Basin. HCFCD estimates the project at $33 million. It will serve a population that’s 26% LMI.
The project overview says, “This project will improve the stormwater conveyance in Taylor Gully and increase the volume of detained stormwater with the construction of the Woodridge stormwater detention basin. The stormwater detention basin will be constructed on undeveloped land the Flood Control District owns and adjacent to three existing stormwater detention basins. This part of the project will be completed before the channel conveyance improvements on Taylor Gully start.”
Taylor Gully starts in MoCo on the Woodridge Village Property and runs through the northern part of Kingwood to the East Fork. Hundreds of families flooded twice in 2019 in this area after Perry Homes clearcut the Woodridge Property.
Shortly after purchasing the Woodridge property in 2021, HCFCD got a head start on the detention basin portion of the project when it entered an excavation and removal contract with Sprint Sand and Clay. But the contract ended and work stopped when HCFCD decided to apply for the HUD grant. Under HUD rules, work cannot continue while a grant application is being evaluated. That left a gaping, disconnected hole in the ground.
Start of Woodridge Village stormwater detention basin as of October 25, 2024. When complete, it will extend to small grove of trees near top of frameand the diagonal channel that bisects the property. See map above.
Other Mitigation Projects
See the other Projects in the screen captures below.
Notice that the Kingwood Diversion Ditch did not make either list. HCFCD’s Kingwood Area Drainage Analysis named it one of the two most important projects in the Kingwood Area, which suffered the worst flood in the county during Harvey.
Regardless, I look forward to seeing the Woodridge detention basin resume construction.
Posted by Bob Rehak on 1/25/25
2706 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2025/01/20241025-DJI_20241025151123_0019_D.jpg?fit=1100%2C619&ssl=16191100adminadmin2025-01-25 16:49:262025-08-30 16:46:16HCFCD Recommends Projects for $863 Million in HUD Funding
1/16/2025 – Harris County Precinct 3 Commissioner Tom Ramsey, PE, and Distict E Houston City Council Member Fred Flickinger discussed the status of numerous flood projects at a meeting of the Kingwood Area Republican Women today at the Oakhurst Golf Club.
Ramsey addressing Kingwood Area Republican Women’s Club today.
Among the projects they covered were:
Taylor Gully Improvements/Woodridge Village Detention
Legal Changes Governing Pre-Release of Water from Lakes
Edgewater Park
Dredging
Medians
Flood Tunnels
Subsidence
Below are the highlights. They also discussed other issues such as median maintenance, vine control, crime, taxes, government waste, elections and more. But I will focus primarily on infrastructure issues related to flooding – especially Taylor Gully and Woodridge Village, because of pending approvals this month.
Taylor Gully/Woodridge Village
After Perry Homes clearcut approximately 270 acres in Montgomery County, hundreds of Kingwood homes flooded twice in 2019 along Taylor Gully. Taylor Gully runs through the northern part of Kingwood from Kingwood Park High School to White Oak Creek.
Harris County Flood Control District (HCDFC) began working on mitigation plans in 2021 and presented preliminary recommendations to the community in December, 2022.
The county had high hopes for funding from the Texas General Land Office (GLO) and U.S. Department of Housing and Urban Development (HUD), but those ran into a potential snag. Taylor Gully improvements fit within available HUD funding, but Woodridge Village (the former Perry Homes Property) did not. HCFCD hoped to build more stormwater detention basin capacity on Woodridge to help control Taylor Gully expenses downstream.
Regardless HCFCD pressed forward. They combined the two projects. And according to HCFCD, both now fit with available funding capacity (see “above the line” list on page 2) of the list being presented to Commissioners Court next week on 1/23/25.
The county purchased Woodridge Village in February 2021. Shortly thereafter, HCFCD began an excavation and removal (E&R) contract to get a “head start” on the basins. Indeed, the head start brought the total stormwater detention on the site almost to Atlas-14 standards.
However, HCFCD was forced to terminate the E&R contract before the basins could be completed. That was to comply with HUD requirements while HUD considered the grant application.
This is potentially great news for the people who live in Sherwood Trails, Elm Grove, Mills Branch and Woodstream.
Watch commissioner’s court closely next Thursday. The Kingwood area drainage study named this project as one of the two most important in Kingwood.
Kingwood Diversion Ditch and Upstream Detention
The Kingwood Diversion Ditch was the other of the two most important projects. The Diversion Ditch takes floodwaters out of Bens Branch, which runs diagonally through the center of Kingwood from St. Martha Catholic Church to River Grove Park.
Improving the Diversion Ditch would reduce flood risk for hundreds of homes and apartments, Kingwood High School, Town Center, and Kings Harbor. Both Bens Branch and the Diversion Ditch currently have a two-year level of service. That means they have a 50% chance of coming out of their banks in any given year.
Ramsey estimated today that the project could cost $60 million. However, he also indicated that U.S. Congressman Dan Crenshaw “got us enough money so we can do the final engineering.”
Eric Heppen, Precinct 3 engineer, later stated that once Commissioners Court approves the preliminary report, it will be made public.
Flickinger emphasized that he is talking with Montgomery County, trying to get them to retain more of their floodwaters. He raised concerns about a new 200,000 sq. ft. convention center planned for US59 at Valley Ranch. “That will generate a lot of runoff that could come down to us, unless we work together to find a way to hold that water up there.”
Houston City Council Member Fred Flickingerat same meeting.
Additional Floodgates for Lake Houston
Shortly after Harvey, many people pinned their flood-mitigation hopes on additional floodgates for the Lake Houston dam. The idea: to lower the lake faster when it becomes certain that a storm will flood the area. The existing gates have 1/15th the capacity of Lake Conroe’s. So Lake Houston must start releasing far earlier in advance of storms than Lake Conroe. And by the time Lake Houston is lowered, storms can veer away, wasting valuable water.
So Conroe tends to hold its water back until it is absolutely certain. At that point, it has no other choice than to release water at high rates that flood people downstream.
Being able to lower Lake Houston faster would let Lake Conroe release earlier and slower, smoothing out flood peaks downstream.
Ramsey estimated the cost of 11 new floodgates that could release 80,000 cubic feet per second at $150 million. He said the final engineering should be completed this year. He also said that bidding and construction could start in 2026.
Legal Changes Governing Pre-Release of Water
Flickinger addressed a related legal issue. State law limits the release of water from lakes; it must be only for defined beneficial uses and flood control is not one of them.
So, Flickinger is working with State Rep. Charles Cunningham to change that and increase the limit. “Bottom line,” he said, “is that we need to release more water sooner rather than holding it back until we’re adding to the crest of the flood.”
Flickinger is also working with the San Jacinto River Authority on these changes.
Edgewater Park
After Harvey, the County acquired land on the northeast corner of the West Fork and US59, which will turn into Edgewater Park. It will also connect the Houston Parks Board’s West Fork Greenway with the Spring Creek Nature Trail. Ramsey said the plans will be made public very soon. After the meeting, Precinct 3 engineer Eric Heppen confirmed the plans were 99% complete.
Ramsey said, “Soon, you’ll be able to go from Kingwood to Tomball and not cross a road.” That should be a tremendous draw for hikers and bikers and the entire area.
Dredging
Flickinger discussed two aspects of dredging not covered in last night’s post. First, he is seeking additional funding to continue the current program while the dredge is on the lake. Second, he feels opportunities exist to increase efficiency.
I asked what he meant by that. FEMA restrictions on the funds currently being used limit the dredging to “pre-Harvey” conditions. That means, Callan Marine, the contractor, must dredge to different depths to match the exact bottom profile that existed before Harvey. And that requires repositioning the dredge more than if you were just dredging to a uniform depth across wide areas.
The search for additional funding has led Flickinger to the City, the Coastal Water Authority (CWA) and former State Representative Dan Huberty. Huberty was appointed to the board of CWA last last year by Houston Mayor John Whitmire.
Medians
Several people from the audience questioned Flickinger about the medians along Kingwood Drive. He touted the success of his first Median Madness event in November 2024 and announced another on February 22, 2025. Mark your calendar now.
More than 50 volunteers participated in the last vine-cutting extravaganza. He hopes for many more volunteers this time.
Flood Tunnels
The county is getting ready to launch the next phase of its flood tunnel study. Ramsey emphasized that there isn’t enough room in Harris County to poke enough holes in the ground to solve all of our flooding problems. He sees tunnels that carry floodwater from strategic locations as essential parts of the solution.
Eric Heppen, Ramsey’s engineer said that by burying the 40 foot tunnels 80 feet underground, you can double the conveyance in some watersheds, sidestep environmental issues, and avoid having to condemn property.
But many issues have yet to be worked out. For instance, will tunnels be constructed to relieve 2-year, 5-year, 10-year, 25-year or 50-year flooding? More to follow when details become available.
Subsidence
Harris County estimates the area east of Lake Houston will grow by 18,000 homes in the next 10 years. But there currently are no plans to provide them with surface water. So, they will pump groundwater. That means subsidence. And subsidence means flooding, according to Ramsey. He pointed to Conroe as an example. The City’s groundwater pumping has caused subsidence as far south as Harris County.
Posted by Bob Rehak on 1/16/25
2697 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2022/12/20221206-Taylor-Gully.jpg?fit=1200%2C1200&ssl=112001200adminadmin2025-01-16 21:37:172025-01-17 14:29:08Ramsey, Flickinger Discuss Status of Flood Projects
10/10/24 – Buried within a Harris County Flood Control District (HCFCD) eight-page status report submitted to Commissioners Court last Tuesday is a potential conflict that could torpedo Taylor Gully conveyance improvements.
Taylor Gully is the lone Kingwood project that HCFCD submitted to the US Department of Housing and Urban Development and the Texas General Land Office for Community Development Block Grant funding. The list of disaster relief and hazard mitigation projects totals $863 million.
Taylor Gully during May 7, 2019 flood
HUD Funds via Texas GLO
The HUD/GLO money focuses on projects stemming from Hurricane Harvey that are designed to mitigate future disasters and flooding.
The money is in two buckets: disaster relief ($322 million) and mitigation ($541 million).
DR vs MIT, Above-the-Line vs Below-
Of the 39 projects listed in the status report, Northeast Harris County has three. But the three actually relate to only one project – Taylor Gully Drainage Improvements in Kingwood.
The main Taylor Gully project falls into the Disaster Mitigation (MIT) category.
Two related stormwater detention basins in Woodridge Village at the head of Taylor Gully fall into the disaster relief (DR) category.
A note on page six of the HCFCD status report explains the relationship between the three items. Basically, Flood Control needs the two detention basins to make the Taylor Gully improvements work within the available space.
Green basin was started under an E&R contract then paused after HUD funding application. A second basin would need to be built from scratch somewhere within the area designated as G-503-06-00.Taylor Gully is blue line labeled G103-80-03.1.
Now, here’s where it gets interesting. The Taylor Gully project is above the funding line. That means there’s room for it in the budget. But…
Potential Conflict
The two detention basins, which are prerequisites, fall below the funding line. That means there is no budget for them unless another above-the-funding-line project falls out of contention or comes in much lower than expected. (Editorial comment: Good luck with that!)
Taylor Gully Channel Conveyance Improvements (G103-80-03.1-E002), Woodridge Stormwater Detention Basin, Compartment 1 (G503-06-00-E003), and Woodridge Stormwater Detention Basin, Compartment 2 (G503-06-00-E004): Woodridge Stormwater Detention Basin, Compartment 1 (G503-06-00-E003) and Woodridge Stormwater Detention Basin, Compartment 2 (G503-06-00-E004) were originally below the funding line for CDBG-DR. The original engineering analysis indicated that only Woodbridge Basin Compartment 1 was needed for the Taylor Gully mitigation. As the analysis has progressed, it indicates that Compartment 2 (or a portion of it) may also be needed. Due to other projects potentially reducing in budget from the initial estimates, there may be funding available to include the Woodbridge basin in the Taylor Gully project. [Color added for emphasis.] (Bond ID: F-14; Precinct 3).
It’s like saying, “We’ll recommend the highway expansion. But we may not approve the concrete for it.”
Deadlines Looming
To make matters worse, the two detention basins are in the Disaster Relief category. That had a tight deadline – mid 2026. However, the GLO and HUD say that they are granting extensions on a case-by-case basis. HCFCD says they are asking for one. And these two particular projects seem to be in the pipeline under review.
The Taylor Gully conveyance improvements will cost an estimated $25.5 million. The two Woodridge detention basins together will cost an estimated $30.8 million.
The GLO says it is working closely with Harris County Flood Control to process applications and resolve issues as quickly as they arise.
However, unless HUD and the GLO grant a deadline extension, the two basins would need to be completed and all the billing submitted for payment by roughly mid-2026. That would be ambitious, even if they started today.
Worse, if the issue is “available funding,” they’ll need to finalize 14 other projects first to see how much money they have left over before the detention basins can even start.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2019/05/Taylor-Gully-at-Peak-e1728600738227.jpg?fit=1100%2C327&ssl=13271100adminadmin2024-10-10 18:22:562024-10-11 13:42:23Potential Funding Problem for Taylor Gully Mitigation Project
4/23/24 – In a transmittal to Harris County Commissioners Court today, Harris County Flood Control District (HCFCD) updated commissioners on how it hopes to spend $863 million in U.S. Department of Housing and Urban Development (HUD) funds.
Two projects in the Kingwood Area remain funding priorities: Taylor Gully Channel Improvements and Woodridge Village Stormwater Detention. However, the stormwater detention, currently listed as an alternate backup project, is being split up into two smaller projects to help improve funding chances for the most critical component. See more details below.
Ins and Outs of Funding
The HUD money comes in two “buckets” with different requirements – Disaster Relief ($322 million) and Mitigation ($541 million). Both buckets fall under HUD’s Community Development Block Grant Program (CDBG). CDBG’s flexibility lets people and communities design and implement strategies tailored to their own needs and priorities.
When I last reported on the CDBG lists, the Lake Houston Area had one project in each bucket.
In Disaster Relief, the Woodridge Village Stormwater Detention Basin was “below the line.” That means it was an alternate on the backup list; a primary project would have had to have been canceled for it to receive funding.
In Mitigation, Taylor Gully Improvements were above the line, i.e., primary recommendations.
Extent of Woodridge excavation when paused before applying to HUD
Changes Outlined in Transmittal
The latest updated project lists feature five main changes. They affect both Lake Houston Area projects. But first, let me explain the others that are changing, because their financial impact affects everything else.
Transferred the Boudreaux Basin (Phase 1) from the DR list to Mitigation, so that it could benefit from the longer timeline for Mitigation projects. This project is between Willow Creek and SH99 at Huffsmith Kohrville Road. The transfer will free up another $38.6 million on the DR list.
Thus, you would think approximately $21.3 million was freed up on the DR list. That would theoretically let the Woodridge Stormwater Detention Basin move up from “below the funding line.” However, it remains below…at least for now.
Moreover the Woodridge Stormwater Detention Basin has morphed into two projects. One provides the detention required to help mitigate Taylor Gully now. The other provides an extra safety margin as a hedge against future developments.
Splitting the detention up into two smaller pieces gives HCFCD more flexibility and greater confidence that the most important part will get funded.
The Woodridge/Taylor Gully discussion in the document is a bit confusing unless you speak HUD.
“The second basin will provide additional regional stormwater detention. Splitting the project helps us ensure the compartment of the Woodridge basin that mitigates Taylor Gully can move forward,” said Crouser.
She concluded, “The ultimate goal is to eventually construct both compartments. This follows our traditional rationale for phasing projects when possible and practicable. Both compartments will be advanced to bid-ready state using local dollars. That will give us the maximum flexibility to advance the projects.”
Congressman Dan Crenshaw has helped secure Federal funding that supports 10 Lake Houston Area projects. Crenshaw submitted requests for the earmarks in 2023. After review by several different congressional committees, some of the earmark requests were modified and some sailed through for the full amounts.
The table below shows requested and approved amounts.
Project
Originally Requested
Finally Approved
Walnut Lane Bridge over Kingwood Diversion Ditch
$4 million
$4 million
New Caney Active Shooter Defense Training Facility
According to sources familiar with the process, Crenshaw is one of the few if not the only representatives to secure funding for all projects he has submitted in the last three years.
Reportedly, this is because Crenshaw restricts his requests to projects that save lives and/or money in the long term. Said another way, the requests he submits justify the expenditures. They are usually for infrastructure and save the government money by preventing future flood damage.
Crenshaw in black shirt visiting with Elm Grove flood victims in 2019 near Taylor Gully.
For descriptions of all 10 earmarks requested by Crenshaw, see below.
Project Descriptions
Kingwood Diversion Channel – Walnut Lane Bridge Project
Recipient: City of Houston
Purpose: The project includes the widening and reconstruction of Walnut Lane Bridge in Kingwood. This bridge, in its current configuration, will restrict flood flows unless widened to accommodate the future expansion of the Kingwood Diversion Channel currently being designed by the Harris County Flood Control District. The purpose of the overall project is to route drainage from Montgomery County to Lake Houston and reduce flood damage to residents of Kingwood along Bens Branch. The funding is needed to construct improvements needed to facilitate the expansion of the Kingwood Diversion Ditch and rebuild the Walnut Lane Bridge.
Active Shooter Defense Training Facility
Recipient: Montgomery County
Purpose: Purpose: To assist with the operations of our regional active shooter rapid response training facility by purchasing training supplies/aids, equiping graduates with medical response supplies, and ballistic equipment for actual threats. To date, graduates include 1,600 law enforcement personnel, fire and EMS first responders.
San Jacinto River Wastewater System Replacement Project
Recipient: Army Corps of Engineers
Purpose: To increase the reliability of the San Jacinto River Authority Woodlands Division wastewater conveyance system and repair damage from recent storms. List stations were damaged by flooding during Hurricane Harvey and have yet to be repaired. Both on-site lift stations, the control building, and the emergency generator were flooded and need to be replaced. This request would fund the demolition of the existing structure and build new systems.
Goose Creek Channel Conveyance Improvements and Stormwater Detention Project
Recipient: Harris County Flood Control District
Purpose: This project is designed to reduce flood risk within the Goose Creek Watershed by creating a detention basin and improving stormwater conveyance. The project is estimated to remove approximately 28 acres of inundated land, up to 77 structures, and 1.44 miles of inundated roadways from the 100-year event. Preventing flooding will avoid the need for more costly recovery efforts after flooding events.
Taylor Gully Flood Mitigation Project
Recipient: Harris County Flood Control District
Purpose: To reduce flood risk in the Kingwood area. This area experienced widespread flooding from recent storm events, including Hurricane Harvey and Tropical Storm Imelda. This project will create a detention basin and improve stormwater conveyance to minimize flood risks. Engineering studies show that completion of this project will result in substantial reductions in flooding along Taylor Gully. The studies show that this project will remove the 100-year floodplain from more than 276 structures and 115 acres of flood area.
Goose Creek Channel Conveyance Improvements and Stormwater Detention Project
Recipient: Harris County Flood Control District
Purpose: This project is designed to reduce flood risk within the Goose Creek Watershed by creating a detention basin and improving stormwater conveyance. The project is estimated to remove approximately 28 acres of inundated land, up to 77 structures, and 1.44 miles of inundated roadways from the 100-year event. Preventing flooding will avoid the need for more costly recovery efforts after flooding events.
Ford Road Improvement Project
Recipient: Montgomery County
Purpose: Support Ford Road improvements from US 59 in Montgomery County to the Harris County line. The current road is undersized and serves as one of only three evacuation routes for the Kingwood area. All three routes have drainage issues and Ford Road is only a two-lane road. The proposed project would make Ford Road a four-lane road, improve local drainage, and improve driver and pedestrian safety in the corridor.
Montgomery County Bridge Project
Recipient: Montgomery County
Purpose: Provide funding for five rural wooden bridges in Montgomery County that are past their design life and need to be replaced. The bridges were not built to current criteria and increase the risk of flooding by backing up water during large storms. One bridge serves as the only way in and out of a subdivision presenting a safety hazard. The funding request is for engineering, surveying, and permitting services to develop construction plans to replace five bridges.
Tamina Economic Development Planning Project
Recipient: Montgomery County
Purpose: The Tamina area is not served by modern street and stormwater management systems. The streets are in disrepair and the area drains very poorly, creating an elevated risk of flooding. The first phase of economic development planning, which this request would support, is to complete detailed engineering and environmental studies, provide new driveways and culverts, and re-grade all of the ditches to allow them to drain.
FM1488 Area Street Rehabilitation and Drainage Improvement Project
Recipient: City of Conroe
Purpose: The project will fund roadway resurfacing, drainage improvements, and storm sewer upgrades of roadways connecting to FM1488 near IH-45 (southern part of Conroe). The City of Conroe has experienced severe weather and rainfall which causes considerable wear and tear on the roads and drainage network. The project will benefit residential areas, including the Arella Forrest at Woodland Senior Living Center and Stillwater neighborhood. It will also improve access to the WG Jones State Forest, which serves a community located in a Historically Disadvantaged Community Tract.
Purpose: Reconstruction of multiple poorly paved roads in subdivisions throughout the Highlands, Crosby, and Huffman areas of northeast Harris County. Existing gravel roads and inadequate drainage will be replaced with asphalt pavement, driveway culverts, and roadside ditches that will greatly improve residents’ quality of life. The projects will also improve accessibility for law enforcement and emergency services, reduce flood risk, and bring the local infrastructure to a standard acceptable for long-term County maintenance.
Reason for Some Cutbacks
Earmarks come out of a specific percentage of each committee’s overall budget. The more requests that representatives submit, the less money there is to go around. And congressmen have no control over what others submit.
Overall, Congressman Crenshaw did very well. Many of these projects would not be going forward without his assistance.
Posted by Bob Rehak on 4/4/24
2410 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2019/09/CrenshawElmGrove-e1690218032150.jpg?fit=1100%2C825&ssl=18251100adminadmin2024-04-04 12:14:522024-04-04 12:25:24Crenshaw Secures Funding for 10 Lake Houston Area Projects
(Note: Within an hour of posting this, I received additional information from a source familiar with Federal grants and have updated the section on Funding below.) Harris County Flood Control District (HCFCD) and Sprint Sand & Clay have ended their Woodridge Village excavation and removal (E&R) contract. As of Friday afternoon, 11/24/23, Sprint had removed all of its equipment from the worksite, including the construction trailer at the entrance. See photos below.
Empty entrance on Woodland Hills where construction trailer once stood.Looking NE at extent of excavation for new detention basin.Same basin, but looking in opposite direction toward SW.
This will pause construction of additional stormwater detention capacity on Woodridge Village property.
Why did the contract end?
Funding Played Role in E&R Contract Termination
The new stormwater detention basin on HCFCD’s Woodridge Village property was part of a much larger project involving improvements to Taylor Gully. The combined Taylor Gully/Woodridge Village project involved funding from multiple sources:
U.S. Representative Dan Crenshaw secured federal funding for Taylor Gully improvements in March 2022.
The Texas Water Development Board approved additional state funding in May.
Last summer, HCFCD also recommended the Taylor Gully/Woodridge project(s) for GLO/U.S. Department of Housing and Urban Development (HUD) CDBG-MIT funding.
The last comes with a firm, tight deadline for spending the money – Jan. 12, 2027 – three years away. It also comes with other “process” restrictions dictated by the CDBG-MIT funding.
Harris County requested a deadline extension. But because of the holiday, it is not clear whether HUD granted it.
Also, since originally posting this, an expert in Federal grants wrote to say, “The excavation and removal at Woodridge had to stop because Federal funds require a process to be followed. The excavation project that will be funded by CDBG mitigation funds has to follow NEPA (the National Environmental Policy Act). It does not allow any activity until NEPA has been cleared. Once the site was officially approved for CDBG mitigation funds, everything had to stop. The agreement with GLO was executed a week or two ago.”
“A similar thing happened to the Sprint excavation and removal at the Dinner Creek Basin,” he added. “It’s one of those sad facts about federal grants. You have to follow their process and everything is done in a linear fashion.”
Flexible E&R Contracts Allow Early Termination
HCFCD’s excavation and removal contracts are very flexible. They let HCFCD get a head start on construction as it worked out financing, design and other project details.
The terms of Sprint’s E&R contract let Sprint excavate up to 500,000 cubic yards of material and sell the dirt on the private market to make a profit. Sprint was meeting its 5,000 cubic-yard/month minimum. They averaged 6,000 to 7,000 cubic yards per month during the last two years.
By the end of October, the company excavated 156,478 cubic yards – about a third of the maximum. However, the additional two-thirds at the current rate would have missed the HUD deadline by at least two years.
If there’s good news here, it’s that:
The amount excavated to date already puts the site very close to meeting Atlas-14 requirements. The “head start” worked.
Once construction resumes, it could sharply accelerate.
Final HCFCD Recommendations Not Yet Revealed
In December 2022, engineers presented their preliminary plans to the Kingwood community and sought public input on four alternatives. Their recommended alternative included:
Expanding a portion of Taylor Gully and lining it with concrete.
Building yet another 412 acre-foot stormwater detention basin on Woodridge Village.
Replacing the culverts at Rustling Elms with a clear-span bridge.
HCFCD has not yet revealed final construction plans to the community. But it appears that the pot is starting to boil. Stay tuned. More news will follow soon.
Posted by Bob Rehak on 11/26/23
2280 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2023/11/20231124-DJI_0161.jpg?fit=1100%2C733&ssl=17331100adminadmin2023-11-26 14:04:332023-11-26 16:19:04Woodridge Village Excavation and Removal Contract Ends