Tag Archive for: Northpark power lines

Entergy Ignores City Deadline to Move Northpark Power Lines

Today, Entergy missed yet another deadline in a long series of deadlines to move its power lines to make room for Northpark Drive expansion.

On February 6, the City of Houston sent a letter to Entergy, demanding that the company move its power lines out of the City’s right of way within 30 days. That would have given them until March 8 to comply. But as of today, March 9, 2024, not one of the poles had moved.

The City’s agent, Lake Houston Redevelopment Authority/TIRZ 10, first asked Entergy to move the poles four years ago. This is just another in a long line of disappointments that have delayed the Northpark Drive Expansion Project – driving up taxpayer costs, increasing flood risk, and snarling traffic.

Last month, Entergy refused to provide ReduceFlooding.com with a copy of its response to the City. And today, Entergy did not return a phone call explaining why the company ignored the City deadline.

Before/After Photos

Here’s how the north-side/west-bound expansion area near the UP tracks looked before the City sent its demand letter.

Entergy power poles in the way of Northpark expansion
Photo taken Jan. 13, 2024, before City sent letter to Entergy.

And here’s how the same area looked this morning. Not one pole has moved as a result of the City’s February 6 letter.

Photo taken around noon on March 9, more than 30 days after letter was sent. Nothing has moved.
Reverse angle. Looking E along Northpark at endless backups and poles still in original locations. Also taken March 9th.

As I took these photos Saturday near noon, traffic was backed up more than a mile!

Clash over Cash

In the past, Entergy asked for compensation to move its poles. But according to an LHRA spokesperson, compensation is not allowable under Texas law because the poles were in a City right of way and not covered by an easement. Thus, any payment would have constituted a “gift of public funds,” which the Texas Constitution prohibits

Entergy was, however, legally entitled to compensation for moving buried wires in an easement near the Exxon station at US59. Entergy had agreed to move them for $711,000 near Christmas last year. However…

Entergy still has not moved buried wires or a transformer near the Exxon station at US59.

…within days after the disagreement about payment for relocating the poles, Entergy’s asking price to move the underground wires mysteriously increased by half a million dollars. Simultaneously, their cost estimate went from line item to lump sum – without itemization. Since then, the asking price has increased another $200,000 without explanation.

Previous Communications with Entergy

City of Houston held Utility Coordination Meetings with Entergy on 10/8/20, 12/10/20, 01/14/21, 2/11/21, 3/11/21, 2/10/22, 3/10/22, and 4/14/22.

In addition, the City also emailed Entergy’s Utility Relocation consultant on 12/07/20, 06/21/21, 06/30/22, 07/22/22, 08/19/22, 09/20/22, 10/21/22, 01/11/23, 01/24/23, 03/03/23, 05/17/23, 07/19/23, 08/23/23, 10/16/23, 10/26/23, 12/01/23, and 12/13/24, 01/16/24.

I don’t care to speculate on the motives for Entergy’s lethargy. However, I’m pretty certain that if this goes to court, the entire project could be delayed years.

You can draw your own conclusions and point fingers where you will.

If there was ever any doubt, Entergy now knows that one of the main goals of Northpark Expansion is to provide an all-weather evacuation route for 78,000 Kingwood and Porter residents. Personally, I hate feeling like a pawn in Entergy’s game.

Posted by Bob Rehak on 3/9/24

2384 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.