Northpark Drive Expansion Project Overcoming Hurdles
8/8/24 – In the last year, the Northpark Drive expansion project hit several snags. But one by one, project partners seem to be overcoming the hurdles.
Contractors discovered utility poles and gas lines in their way. Permits to bore under the railroad and bridge over it took longer than expected. Delays forced changes in plans to keep crews busy. And eventually, when project managers ran out of alternative options, contractors had to shift crews to other jobs.
After months of delays that hampered progress, hope is finally on the horizon.
Paving the Way for Faster Progress
The pace of construction could soon accelerate again.
- CenterPoint has moved all of its facilities east of Loop 494 and only a few conflicts are left west of 494.
- Entergy is almost done removing its east-to-west poles at Northpark/494. This will let contractors complete the storm water drainage system, construct new feeder roads, and build at-grade vehicle crossings over the rail tracks.
- Comcast, Tachus, AT&T, PS Lightwave, MCI, Optimum, BrightSpeed, and Crown Castle have either finished relocating their facilities, submitted relocation plans under review at the City, or received Permits for relocation. In the last case, they have also provided schedules to the TIRZ
- A new water main will allow service to be transferred from Porter SUD to City of Houston. This same water main also serves the newly installed fire hydrants along Northpark.
- Contractors and UnionPacific have resolved right-of-way issues. Work should start on the rail crossings later this year.
- Project managers have acquired additional rights of way from private property owners
- Alternate plans are in place for rerouting traffic
- Entergy has submitted Plans for permits that will let them bury their power lines west of 494 and underneath the railroad tracks on Northpark Drive.
Most of these changes, while barely visible, are highly critical.
Improved Working Relationship with Entergy
Project Manager Ralph De Leon predicts motorists could soon see visible progress. Brian Garcia, Entergy’s customer service manager, agrees.
Both men cite an improved working relationship. Weekly meetings between their teams have reportedly resolved most technical, permitting, and scheduling issues.
Next Steps
Harper brothers has finished burying culvert down the center of Northpark. Now the company will begin installing culvert on the north side of the street westward. It will eventually connect to the system at Self-U-Storage.
The next leg will go under the railroad tracks and Loop 494. It will connect the eastern and western sections of the storm water drainage system.
In general, the next major steps for the Northpark Drive Expansion include:
- Shifting westbound traffic toward the center
- Burying drainage culverts on the north side of the street.
- Building permanent access roads on the north.
- Shifting traffic back to the permanent lanes.
Keep your fingers and tire jacks crossed. Working out many of these unforeseen issues delayed the project 188 days so far. The delays also forced Harper Brothers Construction to divert some of its crews to other jobs to keep them busy.
Photos of Work to Date and In Progress
Crews today worked on bringing power to new, temporary traffic signal locations.
Upcoming Construction Schedule
To look ahead at planned Northpark Drive expansion activities for the next few weeks, see a schedule on the Lake Houston Redevelopment Authority project page.
For More Information
For more information about Northpark Drive expansion and a history of the project, see these posts on ReduceFlooding.
- 24/06/21 Northpark Expansion Obstacles Finally Being Addressed
- 24/04/21 Northpark Floods at Russell-Palmer Road
- 24/04/19 Entergy Makes Some Progress on Northpark but Significant Issues Remain
- 24/04/07 Northpark Entergy Saga: New Power Poles Slowly Going Up
- 24/04/02 New Entergy Power Poles Finally Arrive on Northpark
- 24/03/29 Northpark Expansion Update; Still No Sign of Entergy
- 24/03/16 First Concrete Poured for Northpark Expansion
- 24/03/09 Entergy Ignores City Deadline to Move Power Lines
- 24/03/08 TXDoT, LHRA Engage Kingwood at Northpark Phase II Meeting
- 24/03/05 Details of Phase II Meeting
- 24/02/27 February ’24 Northpark Expansion Update Including Lane Closures
- 24.02/24 Save the Dates: Public Input Meetings for Diversion Ditch, Northpark Expansion Phase II
- 24/02/20 Entergy Escalates Battle with COH over Northpark
- 24/02/16 Excavation of Second Northpark Detention Basin Well Underway
- 24/02/10 Entergy in City’s Crosshairs, Lane Closures Announced
- 24/02/02 Northpark Tree Transplantation Finished, Drainage Updates
- 24/01/13 Excavation of Northpark Detention Basins Starts
- 24/01/07 What Some Utilities Don’t Understand About the Northpark Expansion Project
- 24/01/04 Northpark Tree Moving Starts; Pond Excavation Next
- 23/12/03 Northpark Expansion Presses Forward While Fighting Entergy Obstacle
- 23/11/17 Contractors Strike Oil at Entry (Illegally dumped years ago)
- 23/11/05 City Approves Northpark Expansion Agreement with Union-Pacific.
- 23/10/26 Project moving forward on multiple fronts
- 23/10/12 Transplanting first tree
- 23/10/02 Clearing of south-side entry for second pond
- 23/09/30 Clearing north-side entry for first pond
- 23/09/23 How plan balances flood mitigation, costs, saving trees
- 23/09/02 New entry design, change in construction plans forced by utility conflicts
- 23/08/17 More drainage for Northpark
- 23/08/02 Ditch clearing stretches halfway to 59 in less than week
- 23/07/25 Northpark construction starts in earnest
- 23/04/13 Groundbreaking
- 22/02/19 Update on expansion project
- 21/07/28 Plan details
Posted by Bob Rehak on 8/8/24
2536 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.