Tag Archive for: Loop 494

TIRZ Provides Northpark Update at Kingwood Town Hall

9/24/26 – At Houston City Council Member Fred Flickinger’s town hall meeting in Kingwood on 9/22/26, Tom Broad, the chair of the Lake Houston Redevelopment Authority/TIRZ 10 Board, gave an update on the progress of its Northpark expansion project including its purpose, timeline and the project’s next phases.

Tom Broad, Chair of Lake Houston Redevelopment Authority/TIRZ 10 speaking to town hall meeting about Northpark expansion

Phase One Now 75% Complete

Broad characterized Phase One (US59 to Russel Palmer) as 75% complete. “We ought to be substantially complete with that phase by the end of the first quarter of 2027,” he said.

“This first project has been a long time coming,” Broad continued, “considering that the magnitude of what we were asked to do – construct an all-weather evacuation route out of Kingwood that doesn’t flood.”

He added, “I will give you an example of the difficulty. It took us two years and 11 months to construct a storm sewer drainage system that meets federal standards and that will prevent flooding along North Park. This is something that Kingwood residents have requested for years – an evacuation route out of Kingwood.“

Other major routes out of Kingwood, such as Kingwood Drive, Hamblen, West Lake Houston Parkway Woodland Hills and Mills Branch can flood during high-water events. During Harvey, many people became trapped by rising floodwaters. Below are several ReduceFlooding.com file photos.

4000 Students at Kingwood High School
Looking west at Kingwood High School and Kingwood Drive (left) during Harvey.
Evacuation Route during Harvey
Photo by Jim Balcom of Hamblen Road during Harvey evacuation
Harvey evacuation. Sally Geiss
Rescue boats evacuating people along West Lake Houston Parkway at Kingwood Town Center during Harvey
Photo by Kilee Northrup. Looking south down Woodland Hills Drive, south of Kingwood Dr. toward Deer Ridge Park and stables. Taken on Wednesday August 30, late afternoon, "once I was able to drive out of my village (Miulls Branch). Horses OK."
Photo by Kilee Northrup. Looking south down Woodland Hills Drive, south of Kingwood Dr. toward Deer Ridge Park and stables. Taken on Wednesday August 30, 2017.

Need to Finish Detention Basins First to Compensate for Additional Impervious Cover

Broad explained why the project started at US59 and is moving east. “We needed to complete that part of the project first because our bridge over the railroad tracks at Loop 494 is essentially six additional lanes of impervious cover. We couldn’t build that bridge until we had a place for all the water to go,” he said referring to multiple drainage improvements.

Stormwater management became a major challenge. “We even had to install stormwater pipes under the railroad tracks. That was a life experience! But we got it done, and we are moving into the exciting phase of constructing the bridge.”

Complexity of Drilling 90-Foot Deep Piers in Middle of Major Traffic

That has proven tricky, according to Broad. “Council Member Flickinger has committed to keeping two lanes of Northpark open in both directions at all times,” he said. “But we still need enough area for a construction zone for the contractor.”

“That’s not easy to do. You’ve noticed that the intersection of Loop 494 and Northpark has still not been opened. Our contractor needs that area to build the bridge columns.”

“These bridge columns have very deep underground piers. We had to drill 90 feet below ground. Once those bridge columns are secured, we can open the intersection. Soon, we will begin constructing the bridge columns and the caps that go on top of the columns that support the bridge beams,” he said.

Northpark bridge supports under construction
Caps over 90-foot deep piers now under construction

“In October, we expect to start hanging bridge beams,” said Broad. “We will also begin installing street lights on top of the bridge and begin painting the bridge. That activity, of course, will trigger closing lanes as well. But by November, most of the major construction should be completed…” Then he quickly added, “…at least everything east of the new bridge. We’ll have a six lane roadway with sidewalks and street lights for the first time.”

Street Lights Scheduled by Thanksgiving

Broad says that the new street lights won’t be turned on until Thanksgiving. “There are three circuits. The first one on the east side of Russell Palmer, will be illuminated first. Then the middle section closer to King’s Mill goes on second. And the third circuit on the bridges will have to wait until the bridge is constructed.”

Phase 2 and Detention Basin South of St. Martha

Phase Two of the Northpark Expansion goes from Russell Palmer eastward to Woodland Hills. “We are at the 30% design benchmark for Phase Two,” said Broad. “And this fall we will begin acquiring the right of way.”

In concluding his remarks, Broad said, “We’ve created something new for our budget this year. This is the Regional Detention Basin Project. It will be located where Bens Branch and the Kingwood Diversion Ditch meet. This basin when complete will hold approximately 90 acre feet of water, which will help reduce downstream flooding on both the Diversion Ditch and Bens Branch.”

Thirteen people died along Ben’s Branch as a result of flooding during Harvey.

For More Information

To learn more about the project, Broad referred the audience to Lake Houston Redevelopment Authority project pages. “You can see plans for Phase One, Phase Two and the Detention Basin as well as a three-week lookahead schedule,” he said.

He also invited the public to visit board meetings at the Kingwood Community Center at 8 AM, nine months a year. Usually, they’re second Thursdays, but this month, the meeting is today (the fourth Thursday). So, check the website for exact days.

Can’t attend but still have questions? Email info@lakehousonra.com.

Posted by Bob Rehak on 9/24/26

3313 Days since Hurricane Harvey

 

Steelwork Starts on Northpark Bridge

9/18/2026 – Steelwork has started on the Northpark Bridge over the UnionPacific Railroad tracks and Loop 494. When complete, the bridge will form a critical link in the first all-weather evacuation route for the 78,000 people of Kingwood.

See the pictures below.

Note steel I-beam bisecting frame from left to right.
Wider shot shows progression of work. Note bar connecting three completed bridge supports in distance, additional supports in middle, and more supports under construction on left.
Northpark bridge
Intricate rebar structures getting ready for concrete pours will eventually support crossbeams and road bed. They are built on columns sunk deep underground.

Elsewhere on Northpark

More noticeable progress is taking place elsewhere on Northpark.

New stoplights being activated at Russell Palmer Road and Northpark on 9/16/26
Holes being drilled for stoplight poles at Loop 494, also on 9/16/26

Next Steps

According to the Lake Houston Redevelopment Authority project pages, the next steps in coming weeks will be:

  • The dirt crew will continue with clean-up and backfill sidewalks and pavement across the project.
  • Installation of the US59 pond liners is substantially complete at the north pond. After the liner is fused, crew will backfill dirt over the liner, and then do the same in the south pond. However, the liner needs to be completely dry in order to fuse the sections. As a result, rainfall has delayed completion.
  • The structures crew will continue working on streetlight “spread-footing” locations this week. When completed, they will demobilize from the project.
  • The column-structures crew will continue work on columns east of the railroad tracks and then move to the west side.
  • A separate structures crew will continue working on the bottom forms for the support-column caps. Last pour should happen during the last week of September.
  • The drill shaft crew continues to be on hold. They are waiting on an approved work plan for the drill shafts adjacent to the UPRR ROW. After UPRR approves the plan, they have approximately 10 days of work left on the project until completion.

Loop 494 Intersection to Remain Closed Longer than Planned

The Loop 494 intersection will remain closed for the time being because of the UPRR drill shaft issue mentioned above. Once completed, the heavy-duty cranes can be removed from the project. Then the intersection can be safely re-opened, according to project manager Ralph De Leon.

Posted by Bob Rehak on 9/18/26

3307 Days since Hurricane Harvey

East-West Northpark Drainage Under 494, UPRR Now Connected

1/17/2026 – Northpark Expansion Project contractors have now officially completed connecting drainage on both sides of Loop 494 and the UnionPacific Railroad.

Contractors begin backfilling hole after last section of 5’x8′ culvert was connected to junction box west of railroad. Photo 1/16/26.

By today, the work area had been completely filled in and leveled. See below.

Highlighted area shows where final drainage connection above was made yesterday. Photo 1/17/26.

Now stormwater west of Loop 494 has a path to the Kingwood Diversion Ditch and the San Jacinto West Fork.

Path from ponds to Diversion Ditch via Ditch One behind the businesses on the north side of North Park.

Project Manager Ralph De Leon emailed the Lake Houston Redevelopment Authority Board yesterday to inform them. He wrote, “Just wanted to share that we’ve reached a milestone. The contractor poured the collar on the west side of the rail tracks yesterday, functionally connecting the 8’ x 5′ boxes coming from the junction box at the Shell Station and going underneath Loop 494 to the junction box west of the rail tracks.”

The bore under the tracks finished several weeks ago. The culvert shown above plugged the last gap.

De Leon did not indicate whether contractors sealed the last junction box with a Golden Spike.

Meaning of Milestone

With the east/west subsurface work completed, contractors can now begin building the bridge over the railroad tracks and Loop 494. De Leon concluded his email to the board with “We are officially there now.”

When complete Northpark Expansion will represent the first all-weather evacuation route from Kingwood for 78,000 people.

However, while reaching the milestone is a huge accomplishment, it will also mean some inconvenience next week.

Westbound Lane Closure Weekend of 1/23/26

On Friday, January 23, the eastbound entrance to Northpark from the northbound I-69 feeder road will be reduced to one lane eastbound. The constriction will start at 8 p.m. and remain until 5 a.m., Monday, January 26th. 

During that time, the contractor will demolish and replace the remaining section of old roadway and install the last storm sewers at that location. 

Looking E over entry from US59. The red crosshatched area will be demolished and repaved next weekend.

On Friday starting at 8PM, contractors will close one lane per the diagram above and begin demolition of the old concrete and an old 24″ storm sewer lateral pipe in the red L-shaped box.

On Saturday, they will replace the pipe, then begin grading and preparing for “Fast-Track” paving. Fast Track uses special techniques and materials that minimize traffic disruption. Contractors hope to begin pouring the concrete by 7-8PM.

On Sunday, they will stripe the newly constructed concrete and reopen lanes in their original configuration before the weekend.

The new lanes should reopen by 5AM Monday at the latest.

For more information on other facets of the project, see the latest 3-week look ahead schedule.

Posted by Bob Rehak on 1/17/26

3063 Days since Hurricane Harvey

More of Old Northpark Drive Disappears

1/23/25 – In an effort to build the first all-weather evacuation route from Kingwood along Northpark Drive, contractors this week took a brief break – for the weather. But today, they were back at it. Here’s where things stand in the last full week of January.

Demolition, Drainage and Weather Delay

The Lake Houston Redevelopment Authority/TIRZ 10 has resumed demolishing more of the old Northpark Drive pavement. Contractors already demolished and removed the old northbound lanes on Loop 494 south of Northpark. This afternoon, they were busy scraping away the old eastbound lanes on Northpark itself between the entrance to Kings Mill and Russell Palmer Road.

In other news:

  • Installation of culverts on the north side of Northpark has almost reached the UnionPacific Railroad tracks.
  • A concrete pour between Loop 494 and US59 was only partially completed before the big freeze. It was paused, but rebar is ready when the temperature becomes warm enough to pour concrete again. The ideal temperature for safely pouring concrete is typically between 50°F and 70°F.

Pictures Taken 1/23/25

Here are pictures of the progress taken this afternoon.

Looking east from in front of Northpark Christian Church. Old lanes have been demolished and removed all the way to Russell Palmer Road.
Reverse angle from same location. Demolition extends to Kings Mill entrance.
Drainage on outbound Northpark now extends almost to UPRR tracks visible at top of frame.
Looking South at Loop 494 northbound lanes, also demolished.

Only one of two westbound lanes were poured before cold weather set in.

But another is ready to go when temperatures improve.

Coming Soon

In the next couple weeks, the look-ahead schedule posted on the LHRA website shows that, weather permitting:

  • As soon as the main drainage reaches the UPRR, crews will drop back and begin working on laterals to businesses.
  • After the eastbound roadway is removed, a small storm sewer crew will begin the installation of laterals to the new inlets at the new curb line.
  • Paving crews will continue westbound work between 59 and Loop 494.
  • Crews will demolish the Northbound lanes on Loop 494 north of Northpark.

For More Information

See the Lake Houston Redevelopment Authority project web pages. For a history of the project, see these select posts on ReduceFlooding.

Posted by Bob Rehak on 1/23/25

2704 Days since Hurricane Harvey

Northpark, Loop 494 Lane Switches Happen Tonight

12/19/24 – Northpark and Loop 494 lane switches happen tonight to accommodate new construction. Two large lane switches will begin at 9PM.

One will be on the eastbound lanes between Kings Mill and the eastern end of the project at the Kingwood Diversion Ditch. The second will be on Loop 494 about a block north and south of the Northpark intersection.

In both areas, Harper Brothers Construction will switch traffic to new or temporary lanes to accommodate demolition of the old lanes, installation of drainage, and reconstruction of new lanes.

The project has two overall goals: accommodate increased traffic and create an all-weather evacuation route for 78,000 Kingwood residents when floods cut off other exits.

Eastbound NorthPark Drive Traffic Switch

Lake Houston Redevelopment Authority’s (LHRA’s) contractor, Harper Brothers Construction will shift east bound NorthPark Drive traffic from the existing eastbound lanes to the newly constructed center lanes.  The shift of eastbound traffic to the center lanes will occur between Kings Mill Park Drive and the Kingwood diversion ditch, approximately 0.3 miles east of Russell Palmer Road. 

No new changes to the westbound traffic will occur during this phase. The contractor will be installing new storm sewer pipes and inlets along the south side of NorthPark Drive along with new concrete roadway. 

This shift is planned to last approximately 6 months.

For a printable map of the lane changes, see this PDF.

The pictures below may help you visualize the changes coming tonight.

Looking east from near Kings Mill Entrance. Lanes on right will be closed off and traffic diverted to center. Italianos is just out of frame on right.
Eastbound traffic will continue in the center lanes past Russell Palmer Road.
Eastbound traffic will merge back onto the existing lanes between the large dirt pile on left and Jiffy Lube, lower right. Kingwood Diversion Ditch parallels tree line at top of frame.

Loop 494 Traffic Switch:

Harper Brothers will also shift traffic from the east side of Loop 494 to the newly constructed concrete pavement on the west side.  This shift of traffic to the newly constructed concrete lanes will occur between Northpines Drive and the east entrance to Kroger, approximately 0.2 Miles north of Northpark Drive.

This shift will last approximately four months while the contractor installs new storm sewer pipes and inlets along the east side of Loop 494, and new concrete roadway. 

Here’s a second high-resolution, printable map of the lane changes on 494. See this PDF.

This photo may help you visualize the changes.

Looking S along Loop 494 across Northpark. Traffic on the gray, older roadbed on left will shift to the new concrete on right from the foreground, all the way to the top of the frame where road narrows.

One thing to note re: Loop 494. Southbound traffic turning west onto Northpark will have a dedicated right-hand turn lane separate from the southbound lanes. That was not there before. 

Traffic will shift left/west to new lanes along the red line while existing lanes are reconstructed.

I would definitely avoid these areas tonight as contractors erect new traffic barriers. And use extra caution in coming days as drivers get used to the changes.

For More Information

The Lake Houston Redevelopment Authority offers a 3-week look-ahead schedule here.

For a history of the project, see these select ReduceFlooding posts.

Posted by Bob Rehak on 12/19/24 at 2PM

2669 Days since Hurricane Harvey

Kingwood Drive and Loop 494 Intersection Closed This Weekend

City of Houston Mayor Pro Tem Dave Martin announced this afternoon that the Texas Department of Transportation (TxDOT) will close the intersection of Kingwood Drive and Texas Loop 494 this weekend. The closure starts Friday evening, April 17 and, weather permitting, will last through early Monday morning, April 20.

Purpose of Closure

This is a bit off topic for a flood blog, but Kingwood Drive affects half my readers and 494 affects many more. Here’s what’s happening.

TxDOT will raise the intersection of Kingwood Drive and 494 with two feet of asphalt. The purpose: to remove the dip by the UP railroad tracks.

Weather permitting, construction should start at 9:00 p.m. on Friday. Crews will work continuously until 5:00 a.m. Monday.

Please watch for flagmen and orange traffic cones indicating detours. Detours at Crescent Springs, Butterfly Lane, Royal Forest and Northpark Drive are shown below.

For more information, contact TxDOT at (936) 538-3300.

Posted by Bob Rehak on 4/15/2020

960 Days since Hurricane Harvey

Porter Dam Rapidly Becoming Porter Trench

Two days ago, I posted about the “Porter Dam.” The dam was actually an undersized culvert under a road to nowhere that backed water up for blocks. After the December 7th rain, dozens of properties flooded. Yesterday, demolition of the offending culvert started. The demo gave residents an early Christmas present. I went by there again this morning to check the progress. I saw this.

As of Saturday, Dec. 22, 2018, at 10:15 a.m., the Porter Dam had turned into the Porter Trench. Excavation of the undersized culvert continued.

Hopefully, their removal, will eliminate flooding like you see below after the 4.5 inch rain we had on Dec. 7.

Flooding on East Knox in Porter near Loop 494 after a 4.5″ rain on December 7th. Caused by an undersized culvert that backed water up for blocks. Photo courtesy of Mike Eberle.

Mike Eberle of Mike’s Hobby Shop on East Knox sent me these pics at the end of Saturday. They show the progress that the crew made during the day.

Downstream trench at end of Saturday. Photo courtesy of Mike Eberle.
Mid-trench at end of Saturday.  Photo courtesy of Mike Eberle.
Upstream end of trench at end of day on Saturday. Photo courtesy of Mike Eberle.

It’s unclear at this time whether workers will install a larger culvert or just eliminate the Road to Nowhere altogether. I will continue to follow the story.

Street flooding, such as this blockage caused, can devastate homes and businesses every bit as much as river flooding. It only takes an inch of water to cause months worth of repair work.

This morning I learned of several more instances of tragic street flooding in Porter near Sorters Road. Apparently a broken or collapsed storm drain flooded the homes below repeatedly. Montgomery County has not fixed the drain despite repeated pleas from homeowners.

One home owner, a retired Marine, flooded five times in five years. His neighbors, a middle aged couple, flooded ten times in ten years.

Street flooding caused by another bad culvert. Photo courtesy of Tammy Gunnels.

The couple invested more than a quarter million dollars trying to flood-proof their home and virtually wiped out their life savings.

Let’s hope Montgomery County fixes that drain soon…as fast as TexDoT jumped on the Porter Dam problem.

Posted by Bob Rehak on 12/22, 2018

480 Days since Hurricane Harvey