Tag Archive for: funding

San Jacinto Received Only 1% of HCFCD Spending in 2026 Q1

4/14/26 – The San Jacinto Watershed received only 1% of all HCFCD spending in Q1, despite being the county’s largest watershed and having the worst flooding.

Harris County Flood Control District (HCFCD) has published updated spending figures for 2018 Flood Bond Projects through the end of the first quarter of 2026. Analysis also revealed:

  • No Kingwood or Huffman Area projects have reached the construction stage yet
  • Spending on Lake Houston Area projects continues to lag other watersheds throughout the county.
  • HCFCD’s years-long spending slowdown may be stabilizing

Separately, Dr. Tina Petersen, PhD, HCFCD’s executive director, recently announced several positive developments for projects on Cypress Creek, the East Fork and Lake Houston Dam.

Let’s look at the funding analysis first. The screen captures below come from the HCFCD Activity Page and speak for themselves.

Overall Spending Slowdown Stabilizing

The chart below shows incremental spending for ALL watersheds since the start of the flood bond in 2018. But the far right shows only one quarter for this year so far. If the first quarter were annualized, it would approximately equal 2025 year-end spending.

Incremental spending after 2026 Q1 for all watersheds.

However, all phases of activity have declined dramatically since the management change at HCFCD in 2021.

Where the Money Went in Q1

The chart below shows the San Jacinto Watershed ranked 14th versus others. Of the $52 million total dollars spent, more than half of the watersheds received less than $1 million each. Only five watersheds received more than $2 million. The Cypress Creek Watershed received $22 million (36% of the total). That $22 million was three times more than the next largest watershed – White Oak at $6.76 million.

Q1 2026 spending for all watersheds totaled only $52 million.

Petersen attributes construction delays to “getting the funding in place.”

San Jacinto Spending Slowed, Too

Looking closer at the San Jacinto watershed, we can see it dropped sharply. But part of the apparent drop has to do with the fact that you are only looking at one quarter so far for the first quarter of 2026.

Incremental spending for the San Jacinto watershed since 2018

In Q1, HCFCD spent only $524,000 in the entire San Jacinto Watershed. Of that, $491,000 came from partners. Only $33,000 came from HCFCD’s bond or budget.

Breakdown of 2026 Q1 spending in San Jacinto Watershed. Dark blue represents partner spending.

But the most significant takeaway should be the volume of spending in the watershed compared to the total for all watersheds during the quarter…

$.052 million is exactly one one-hundredth of $52 million.

Q1 San Jacinto spending vs. total for all watersheds

And that’s for the county’s largest watershed – where the worst flooding occurred during Harvey. See below.

worst first
Chart showing feet above flood stage of 33 gages of misc. bayous in Harris County during Harvey.

Total and Construction Spending

Overall, HCFCD and its partners have spent almost $2.2 billion to date.

Total spending by watershed associated with the 2018 flood bond

But most of that has been on upfront studies, engineering and right-of-way acquisitions. Of the total $2.2 billion spent so far, only $1 billion has been on construction – 36%.

Construction spending through 2026 Q1 from 2018 flood bond.

Among watersheds, the San Jacinto ranks 13th on construction spending (not including County-Wide Spending) since 2018. White Oak ranks #1 with $148 million. To date, the San Jacinto watershed has received $21.5 million – one seventh of the construction dollars received by White Oak.

Status of Kingwood/Huffman Projects

Only three projects are active in the Lake Houston Area.

The Kingwood Diversion Ditch is still in engineering. It is fully funded and includes:

  • Additional channel capacity
  • A new diversion structure at the confluence with Bens Branch
  • Four bridge replacements
  • A new outfall to the San Jacinto West Fork south of Deer Ridge Park.

Petersen says construction could start as early as 2027.

She expects the Taylor Gully and the Woodridge Stormwater Detention Basin Project to start construction in May 2026. It is also fully funded and includes:

  • New stormwater detention basin
  • Bridge replacement at Rustling Elms
  • Channel widening and deepening

The Luce Bayou Watershed will receive a new detention basin near FM2100 and the Huffman-Cleveland Road to support regional drainage improvements. Construction plans for the fully funded project are nearing completion, according to Petersen.

Status of Lake Houston Gates and East Fork Detention

Farther upstream on Cypress Creek, Petersen said she expects to finally start construction on the TC Jester East Basin soon. HCFCD also claims to have finished construction on the Mercer Basin on Cypress Creek near the Hardy Tollroad.

When I met with Petersen and State Representative Charles Cunningham last week, she also addressed:

  • A $20 million Inter-Local Agreement with the City of Houston for new Lake Houston Gates. It is on the 4/16/26 Commissioners Court Agenda. See Item 126.
  • San Jacinto East Fork stormwater detention basins. It’s unlikely any will be built. But “we’ve identified several locations along the East Fork, where if someone wants to sell their property, we will buy it … and we will get FEMA funding to do that.”.

Posted by Bob Rehak on 4/14/26

3150 Days since Hurricane Harvey

How Crenshaw Saved Kingwood Project from Chopping Block

1/30/26 – A four-million dollar earmark secured by U.S. Representative Dan Crenshaw for widening the Walnut Lane Bridge in Kingwood saved the entire $44 Million Kingwood Diversion Ditch Project from being killed by the Democratic members of Harris County Commissioners Court.

U.S. Rep. Dan Crenshaw gives the thumbs up to the Walnut Lane Bridge project. Widening the bridge is necessary to widen the Kingwood Diversion Ditch (background) which will also help reduce flood risk along Bens Branch.

Crenshaw requested the funding in 2023. Congress awarded it in 2024. Then in 2025, the Democratic members of Harris County Commissioners Court passed a motion to reallocate all funding from projects that fell below the top quartile of their equity prioritization framework to projects in the top quartile. That was because inflation had eaten up 25-30% of the purchasing power in the 2018 Flood Bond.

Ramsey to the Rescue

At the time, Precinct 3 Commissioner Tom Ramsey PE warned that killing projects in Quartiles 2, 3 and 4 could have dire unintended consequences. The Diversion Ditch project fell into Quartile 3.

After the Democrats saw how much partnership funding they would lose by killing projects in the lower quartiles, they relented. In their next meeting, they voted to exempt projects in the lower quartiles that already had partnership funds committed.

That breathed new life into the Kingwood Diversion Ditch project because it included widening of the Walnut Lane Bridge which Crenshaw had already secured funding for.

Multiple Benefits: A Texas Twofer

But the project will benefit far more of Kingwood than just the people who live in Diversion Ditch floodplains. It will also benefit people who live near Bens Branch. That includes the Villages of Bear Branch, Kings Forest, Hunters Ridge, Town Center, Kings Harbor and Kingwood Greens.

That’s because widening the Diversion Ditch will take excess stormwater out of Bens Branch and allow water to move safely down the Diversion Ditch. The planned improvements will take Bens Branch from a 2-year level of service to a 100-year level.

Bens Branch and Kingwood Diversion Ditch
Kingwood Diversion Ditch in white, new outfall in green, and Bens Branch in red.

That means homes in the Bens Branch floodplains should be safe in anything up to a 100-year storm. Currently, the stream is at risk of flooding parts of its watershed every two years.

Twelve seniors died along Bens Branch in the Harvey flood who lived at Kingwood Village Estates. That’s a third of all the people in Harris County and a fifth of all the people in the state who died as a result of Harvey flooding.

When the Diversion Ditch project is completed, Crenshaw will have helped protect people and property values in approximately half of Kingwood.

Bob Rehak

Crenshaw Support Crucial on Other Projects, Too

The Kingwood Area Drainage analysis found that, based on the number of people who benefit, the Diversion Ditch project is one of the two most important in Kingwood. Another is the Taylor Gully/Woodridge Project which Crenshaw also secured funding for.

In fact, Crenshaw secured funding for 10 Lake Houston Area Projects in 2024 alone.

Editorial Comment: I interviewed Crenshaw in 2018 when he first ran for Congress and have followed his work in Washington ever since. The man is a warrior, scholar and leader. He fights tirelessly to improve the lives of his constituents. He studies issues. And thoughtfully and patiently explains them. There’s no way he could have known what Commissioners Court would do in 2025 when he proposed the Walnut Lane Bridge funding in 2023. Regardless, his proactive effort will improve the safety of tens of thousands of his constituents.

For more information including a timetable for the Kingwood Diversion Ditch Project, see this recent post.

Posted by Bob Rehak on 1/30/26

3076 Days since Hurricane Harvey

Top Flood-Related Stories of 2025: Part II – Regs and Funding

12/28/2025 – This is the second part of a three part series on the top flood-related stories of 2025. Part I covered the major disasters of the year. Part II will cover the government response in terms of regulations and funding for flood mitigation efforts. And Part III will cover the progress of mitigation.

Government Response to Camp Mystic/Guadalupe Tragedy

Hearings on the Camp Mystic disaster last July identified a failure of warning signs (weather reports, alarm systems, etc.) as one of the primary causes. Investigations also discovered that the camp’s operators lobbied for changes to flood maps so that they could build in floodplains. And then they evidently expanded the camp before regulators became aware. Finally, evacuation plans were evidently not well communicated or understood.

In response, the Texas Legislature passed the Heaven’s 27 Camp Safety Act (a reference to the number of young girls who died at Camp Mystic). The act bars camp cabins in high risk areas. It also requires camps to have state-approved emergency plans, regular evacuation drills and disaster alert systems.

Lawmakers approved nearly $300 million “to boost flood preparedness, including $200 million to match federal disaster aid, $50 million for local grants to purchase flood warning equipment and $28 million to improve weather forecasting.” A companion bill also expanded government oversight of youth camps.

FEMA Cancels BRIC Program

In April, FEMA announced that it is ending the Building Resilient Infrastructure and Communities (BRIC) program and canceling all BRIC applications from Fiscal Years 2020-2023.

It also canceled the fiscal year 2024 notice of funding opportunity (NOFO), involving $750 million for grants. 

BRIC was FEMA’s largest pre-disaster mitigation program. Congress established it through the Disaster Recovery Reform Act of 2018. Its purpose: to fundamentally shift federal-disaster spending from post-disaster recovery to pre-disaster risk reduction. In other words, to encourage a shift from “Repair” to “Resilience.”

BRIC aimed to prevent disasters by helping communities build to higher standards. Flood-risk reduction grants typically helped finance projects such as:

  • Regional detention and retention basins
  • Flood diversion channels
  • Levee and floodwall construction or upgrades
  • Drainage improvements exceeding minimum code standards
  • Nature-based solutions (wetlands, floodplain restoration)
  • Elevation or floodproofing of critical facilities (hospitals, EOCs, fire stations)

A press release that accompanied the cancellation of the BRIC program called it a “wasteful, politicized grant program.” However, investments in hazard mitigation programs are the opposite of “wasteful,” according to the Association of State Flood Plain Managers. They point to studies showing flood-hazard mitigation investments return up to $8 in benefits for every $1 spent. 

States sued to prevent the cancellation. The lawsuits are still locked up in courts.

Prevention is always cheaper than correction. After Harvey, a Harris County engineering study found 20 times less damage in subdivisions using newer, more stringent building codes compared to those built under older codes.

FEMA Slowdown

Meanwhile, approvals for other types of FEMA grants have slowed. According to The Hill, Department of Homeland Security Secretary Christy Noem has adopted a policy of personally approving all major expenditures that cost $100,000 or more. The Hill article reported $900 million in grants and loans reportedly awaiting Noem’s review.

Separately, in other FEMA news, according to the Washington Post, hundreds of residents signed up for FEMA buyouts after Cat 4 Hurricane Helene devastated the southeast in 2024. Not one has yet been approved. 

HUD/GLO Finish Rebuilding Program

On a more positive note, the Texas General Land Office (GLO) administers U.S. Department of Housing and Urban Development (HUD) flood-mitigation/disaster-relief programs in Texas. The GLO recently announced completion of the rebuilding of more than 9600 homes across the state under its Homeowner Assistance Program (HAP). That total includes mostly homes from its Hurricane Harvey disaster recovery mission. But it also includes homes impacted by Imelda, Laura, and repetitive flooding events in the Rio Grande Valley.

GLO poster celebrating program completion.

Status of Other GLO/HUD Programs

The GLO continued advancing long-term recovery and resilience by administering more than $1 billion in Community Development Block Grant for Disaster Recovery and Mitigation Projects. Additionally, HUD approved the GLO’s plan for $555 million to help communities impacted by 2024 Disasters.

The GLO completed reviews and approvals of all remaining project applications under the Regional Mitigation Program (RMP), providing funding for critical infrastructure improvements including drainage systems and flood-prevention measures. In total, the GLO has approved more than 200 RMP projects for more than $1.1 billion.

The GLO also approved more than $135 million in applications through the Disaster Recovery Reallocation Program (DRRP). It utilizes unspent disaster recovery funds from older disasters to help communities with outstanding unmet needs. These investments will reduce risk related to hurricanes, tropical storms, flooding, and other hazards.  

The agency also announced it will be closing applications at the end of the year for both the Local Hazard Mitigation Plans Program (LHMPP) and the Resilient Communities Program (RCP). Both are part of the GLO’s long-term strategy to help communities strengthen local planning efforts, modernize codes, and protect life and property from future disasters.

Montgomery County Updates Flood Regulations

Eight years after Harvey, Montgomery County finally adopted new subdivision, floodplain, and drainage regulations.

The county adopted its new subdivision (development) regulations on March 4, then amended them on May 27 and October 14. MoCo also issued subdivision guidelines and recommendations on November 4.

Commissioners adopted a new Drainage Criteria Manual on August 26. And new Floodplain Management Regulations became effective on October 1, 2025.

While MoCo regs don’t perfectly reflect the Minimum Drainage Standards recommended by Harris County for other counties draining into it, they are a great improvement.

Competing Forces at Work

Flood safety is a constant struggle between competing forces that increase or reduce flood risk. There are so many, the public can hardly know whether it’s winning or losing.

Just because the government appropriates money, doesn’t mean it’s enough or will be spent promptly.

Even if it is, will it actually reduce risk in the face of offsetting factors such as legislative loopholes, grandfather clauses, willful blindness, the profit motive, shifting political winds, and insufficiently mitigated upstream development?

And maybe that’s THE Top Flood-Related Story of 2025. More on that tomorrow.

Posted by Bob Rehak on 12/28/2025

3043 Days since Hurricane Harvey

GLO, HUD Funding Approved for 7 HCFCD Projects So Far

11/20/2024 – The Texas General Land Office (GLO) confirmed funding approval from the U.S. Department of Housing and Urban Development (HUD) for seven Harris County Flood Control District (HCFCD) projects.

In June of last year, HCFCD submitted two projects lists to GLO for $825 million in HUD Community Development Block Grant disaster relief (CDBG-DR) funding and flood mitigation (CDBG-MIT) funding.

Since then, HCFCD has worked with GLO to finalize the HUD applications. HCFCD presented an update to Commissioner’s Court in early October, 2024. Today, GLO provided an update to the update.

CDBG-DR Projects

According to an email from GLO spokesperson Brittany Eck received today, seven DR projects have received funding approvals to date. They include:

Eck also said that five more CDBG-DR projects are under final quality-control review. “We are making sure the project submissions are complete and meet all federal eligibility requirements so that there are not issues or concerns down the road.”

Disaster Relief projects have the tightest deadlines. So, all parties focused on those first.

CDBG-MIT Funding Still Under Review

“Seventeen CDBG-mitigation projects are still in various stages of preliminary review,” said Eck.

“We are working back and forth on requests for more information required by HUD on many of the projects,” said Eck. “We continue to work very closely with the HCFCD team to make sure they have all available resources needed to complete the applications. Overall our team is very pleased with the progress being made and the relationship continues to be strong.”

Only two mitigation projects have not yet been submitted for preliminary review.

  • Kickerillo-Mischer Preserve Channel Rehabilitation (100-00-00-X115)
  • Channel Conveyance Improvements (C147-00-00-E002) in the Sims Bayou Watershed.

Tremendous Progress

“HCFCD has made tremendous progress on these funds,” said Eck. “However, the rate of approval may not yet demonstrate the progress being made behind the scenes.”

She added, “This process, especially considering the amount funds being administered is an extremely lengthy federal process. Additionally HCFCD has needed to combine projects due to functionality and the GLO is working closely with them to ensure eligibility in the most efficient timeframe imaginable.”

Kingwood Projects Not Mentioned in This Update

Eck did not comment on the status of two Kingwood projects. I can only assume they are still under review. She did not mention any that had been eliminated.

The two Kingwood projects:

Woodridge Village detention basin photographed on 10/25/24. Project paused pending outcome of HUD financing approval.

In its October update to Commissioners Court, HCFCD said the Woodridge Stormwater Detention Basins were originally below the funding line for CDBG-DR.

“The original engineering analysis indicated that only Woodridge Basin Compartment 1 was needed for the Taylor Gully mitigation,” said the update. “As the analysis has progressed it indicates that Compartment 2 (or a portion of it) may also be needed. Due to other projects potentially reducing in budget from the initial estimates, there may be funding available to include the Woodridge basin in the Taylor Gully project.”

That word “may” in the last sentence worries me.

HCFCD did not propose the Kingwood Diversion Ditch project for HUD consideration. HCFCD called the diversion ditch one of the two most important projects in Kingwood. That funding will have to come from somewhere else.

Posted by Bob Rehak on 11/20/24

2640 Days since Hurricane Harvey

HCFCD Flood-Mitigation Spending Down for Third Straight Year

Harris County Flood Control District (HCFCD) flood-mitigation spending finished down for the third year in a row last year. Spending for all four quarters totaled $243.1 million, a little more than half of its peak in 2020.

Spending for 2023 was 56% of its 20-year peak in 2020 at $433 million. Here are the exact amounts spent by HCFCD year by year since 2000.

Possible Reasons for Slowdown

HCFCD flood-mitigation spending increased each quarter last year, but the total wasn’t enough to prevent another annual decline.

HCFCD watchers have conjectured about possible reasons for the slowdown. They include:

Bond Fully Funded, But Inflation Taking Toll

Despite the slowdown, there was some very good news last year. During 2023, thanks to those HUD funds, the 2018 flood bond became fully funded.

The original bond contained approximately $5 billion in projects. But voters approved only $2.5 billion. The ambitious project list associated with the bond contained a bet that HCFCD could raise as much money from partners as it did from voters. And last year, the District did just that. Partner commitments now exceed another $2.5 billion.

Now, HCFCD must spend the money before inflation steals it away. Inflation has already reduced the purchasing power of bond funds by 15-20% in the last four years. Twenty percent of a $5 billion, is another billion that the grant writers must raise just to stay even.

Where is Money Going? Will There Be Enough to Finish All Projects?

That raises two questions, “Where is the money going?” It certainly isn’t going proportionally to all watersheds or precincts.

The four graphs and tables below show where the flood-bond money and partner money has gone since Harvey and during the last quarter.

County-wide projects include such things as planning, MAAPnext, subdivision drainage projects and preliminary planning for flood tunnels (see Z-level projects at end of list).

Q3 2017 through end of 2023.

Note that “Since Harvey” includes a year’s worth of spending not in the flood bond. Voters passed the bond on the first anniversary of Harvey. The District spent $172 million during that year. So the actual amount of bond/partner funds spent to date should total a bit over $1.8 billion.

Q4 2023 Spending Shows Shifts in Some Spending Priorities

Compare those figures with the last quarter of 2023 to see how priorities have or haven’t changed.

By comparing this bar chart with the one immediately above, we can see that relative spending in the San Jacinto watershed has remained consistent if dismal. The county’s largest watershed ranked 14th since Harvey and 13th last quarter.

Other noteworthy observations:

Brays Bayou spending dropped to fourth place from its perennial spot atop the pyramid. Most projects in Project Brays are now completed.

Willow Creek dropped from eighth place to last.

Sims Bayou jumped from 12th place to 6th.

Spending in the Little Cypress Creek watershed jumped to first place from fifth…even outpacing county-wide spending. That may be related to engineering for several large land purchases made earlier in the bond for the Harris County Frontier Program. The Frontier Program buys land in optimal locations in developing watersheds for flood-mitigation projects, such as detention basins. Then it leases capacity back to developers.

Fourteen watersheds received less than a million dollars in spending last quarter.

Based on data obtained via FOIA Request

And four watersheds of Harris County’s 23 watersheds received less than $100,000 last quarter.

The difference in spending between the high and low watersheds last quarter was more than 500 to 1!

I need more time to dig into these numbers. Look for additional analysis in the days to come.

Posted by Bob Rehak on 1/22/2024

2337 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Third-Quarter Flood-Mitigation Spending Trends, Surprises

10/15/23 – Third quarter flood-mitigation spending data is now available for Harris County Flood Control District and its partners. In some ways, the data shows a continuation of previous trends. But the data also contained some surprises. The major findings:

  • Spending continued to dip. Slower project delivery means inflation will claim an increasingly large percentage of taxpayer dollars and may force cancellation of some bond projects.
  • If the last quarter of this year is anything like the first three, we could see less than half the activity in 2023 than we saw in 2020.
  • The trend toward investing more heavily in minority areas continued and even accelerated. But there was one notable exception – Cypress Creek and its tributaries.
  • An unusual $9.7 million real-estate transaction for a stormwater detention basin near the Mercer Arboretum skewed the Cypress Creek total. That was 16.5% of all HCFCD spending for the quarter.
  • Without it, many of the numbers below would also have been skewed. For instance, total spending and average spending per watershed would vary dramatically.
  • The focus on so-called “equity” spending and the Cypress Creek watershed meant 15 watersheds saw less than a million dollars in activity during the quarter. And five of those received less than $100,000.

Let’s look at each and the implications. Everything below INCLUDES the unusual real estate transaction near Mercer. In several places, I note how things would have changed without Mercer.

Overall, Slowdown Magnifies Inflation Concerns

Overall, flood-mitigation spending dipped about 5% in the third quarter compared to the previous quarter. It declined by a little more than $3 million to $58.8 million. That may not sound like much, but it continues a 3-year downward trend and creates delays that expose residents to more flood risk.

As projects are delayed, their costs also escalate due to inflation, raising concerns about whether there will be enough money in the bond to finish all the projects promised to voters.

Spending this year will likely be a hundred million dollars less than the first full year of the 2018 flood bond – when projects were ramping up. See chart below.

Annualized estimate for 2023. 23Q4 data estimated based on average of first 3 quarters. Without Mercer, the 2023 estimate would be below $200 million.

Moreover, spending will be $200 million less than the peak year of 2020 – about half of what it was then.

Halfway through the 2018 10-year flood bond, HCFCD has spent only about a third of the funds approved by voters – $1.65 billion. However, if the present slowdown continues, this will be the third straight year of decline.

The slowdown in project delivery means inflation will increasingly raise costs and undermine the purchasing power of the dollars authorized by voters.

HCFCD acknowledges the serious impact of inflation in its latest bond update to Commissioners Court, and hopes toll-road money remaining in the Flood Resilience Trust will cover any shortfall.

Average Spending in LMI Areas Growing

Data also reveals that with one exception (Cypress Creek and its tributaries), the trend of preferentially allocating funds to Low-to-Moderate-Income (LMI) areas continued and even accelerated when measured by average spending per watershed.

On average during Q3, watersheds with a majority of LMI residents (hereinafter called “LMI watersheds”) received 2.5X more funding than more affluent watersheds – $3.1 million each vs. $1.2 million. That’s up from 1.7X over the longer period since Harvey. So, the gap is widening.

Without the Mercer real-estate transaction, the average for more affluent watersheds would have been cut in half to $600,000. That would have almost doubled the ratio. The recomputed average would created a 4.7X ratio between LMI and all other watersheds for the third quarter.

That trend will likely continue for some time as projects funded by HUD through the Texas General Land Office get approved and start construction. That pot of money will spread across the income spectrum, but projects in lower income areas will likely start first.

Cypress Creek Spending Explodes

In fifteen Harris County watersheds, more than 50% of residents make above the average income for the region.

As a group, those 15 received $18.6 million last quarter – $2 million more than the $16.6 million received by the eight LMI watersheds.

However, the first group is twice the size of the second. And looking deeper within the more affluent watersheds, we can see that Cypress Creek and its tributaries (Willow and Little Cypress) received 79% of that $18.6 million last quarter.

The three Cypress watersheds received almost 4X more funding than the 12 other watersheds in the more affluent category put together.

Cypress Creek and its tributaries consumed 79% of all HCFCD/Partner spending last quarter among watersheds without a majority of LMI residents.

Here’s how that same spending looks in a bar graph.

Only the first three watersheds on the left received more than a million dollars in Q3. The twelve on right received less than $1 million each.

The 12 other watersheds divvied up $3.8 million; they averaged just $348 thousand each.

FOIA request. Data supplied by HCFCD.

$348,000 is one ninth of the $3.1 million average for LMI watersheds. And we know that some of those, such as the San Jacinto, have huge, unmet needs.

Cypress Knocks Brays Out of First Place

Now, let’s look at ALL watersheds in both categories. When looking only at the third quarter, Cypress Creek surged into first place. It nudged out Greens, White Oak, Brays and Sims, all of which have LMI populations greater than 50%.

HCFCD and Partner spending by watershed
Includes all 23 watersheds during 23Q3.

HCFCD finished Project Brays 15 months ago, but still managed to spend $3.8 million there last quarter. That was almost 10X more than it spent during the third quarter in the San Jacinto watershed, the county’s largest, and where the flooding was deepest. HCFCD spent only $400 thousand in the entire San Jacinto watershed last quarter.

worst first
Comparison of 33 gages in Harris County during Harvey showed San Jacinto had worst flooding.

Brays Still Ranks #1 in Total Spending Since Harvey

Since Hurricane Harvey (not just last quarter), Brays still ranks #1. But Cypress now ranks second. If you added its Little Cypress and Willow Creek tributaries in the graph below to the Cypress Creek total, they would rank #1 by more than a $100 million.

Includes all 23 watersheds since Harvey

Brays even managed to increase in the last quarter by $1.5 million while the San Jacinto decreased by $55,000.

Granted, some watersheds have smaller needs than others, but the ratio between the highest and lowest spending exceeds 300X.

Impact of Equity Formula

The spending priorities shown in this post reflect the Equity formula adopted and periodically revised by Harris County Commissioners Court.

Ironically, the language approved by voters in the flood bond never mentions the word “equity.” Paragraph 14G does say that Commissioners Court shall provide for an “equitable expenditure of funds.”

However, most dictionaries define “equitable” as “nondiscriminatory.” Yet the current formula prioritizes projects largely on the racial composition of neighborhoods as described in the CDC’s social vulnerability index.

The theory is that poor people are financially less able to fix their homes after a flood. I accept that.

But some commissioners are using that to push the idea of fixing 500-year flooding in poor neighborhoods before fixing 2-year flooding in more affluent communities.

Therefore, I ask:

  • At what point do we do we say enough money has gone into an LMI watershed and start spending elsewhere to reduce greater flood risk?
  • Why isn’t HCFCD publishing updated flood risk maps as it completes mitigation projects so we can make objective comparisons and see what our tax dollars bought?
  • Why does Harris County’s formula for allocating flood-mitigation funds NOT consider:
    • Flood damage to homes, businesses and retirement communities?
    • Damage to infrastructure, such as bridges, schools, hospitals, grocery stores, traffic arteries, water and sewage treatment plants, etc.?
    • Height of floodwaters, i.e., the severity of flooding?
    • Deaths caused by floods?
  • Is a poor person’s carpet worth more than a rich person’s life?
  • Will there be enough money in the flood bond and flood resilience trust to finish all projects in the bond given inflation?

So many questions. So few answers. Perhaps this explains why trust in government has reached a 70-year low.

Only 20% of Americans now say they trust government “just about always or most of the time.” That’s something to think about as we near the next election.

Posted by Bob Rehak on 10/15/23 and updated 10/16/23 with additional info on Cypress Creek

2238 days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Where Flood-Mitigation Dollars Have Really Gone

An analysis of Harris County Flood Control District (HCFCD) and partner spending since 2000 reveals striking contrasts between watersheds in terms of where flood-mitigation dollars have gone.

Watersheds vary as much as 130 to 1 since 2000 and almost as much since Harvey. Most watersheds remained relatively constant in the rankings during the different time periods. However, a few have shifted up or down a few positions as land was acquired for projects or construction kicked off.

Data below includes spending by HCFCD and its partners from 1/1/2000 to 6/30/2023.

Main Takeaways from the Data

The big stories:

  • Since 2000, the top four watersheds received more flood-mitigation dollars than all 19 others put together. The top four include: Brays, Greens, and White Oak Bayous, and Cypress Creek.
  • Since Harvey the top four received 48%.
  • The distribution of funds continues to show the impact of Harris County’s Equity Prioritization framework.

Harris County’s Equity Prioritization gives weight to race and low-income areas, but not flood damage, the severity of flooding, or protection of infrastructure.

San Jacinto Gets Above Average Damage, Below Average Funding

The San Jacinto ranks below the averages (before 2000 and since Harvey) for flood-mitigation dollars – despite ranking 8th in damaged structures among all 23 watersheds. Damage totals include five major storms (Allison, Memorial Day, Tax Day, Harvey and Imelda).

Compiled from HCFCD Federal Reports

Watersheds Ranked by Funding Since 2000

Here’s how the funding looks in graphs and tables. All data was obtained from HCFCD via FOIA requests.

Data obtained from HCFCD via FOIA requests. Includes Harris County and partner spending.

Here’s the actual data if you want to see exactly how much your watershed received.

From 1/1/2000 through 6/30/23

Watersheds Ranked by Funding Since Harvey

Now let’s look at the how spending shifted after Harvey. Not much, at least relatively speaking.

Includes Harris County and partner spending. San Jacinto climbed two spots, but it is still barely above the median and far below the average.

Here are the actual totals for each watershed shown in the graph above.

Spending from 17Q3 to 23Q2 inclusive.

Feet above Flood Stage

Now let’s look at the severity of flooding. The chart below measures feet above flood stage at different Harris County gages.

Flood Stage is the level at which a river, stream or channel comes out of its banks.

I compiled this chart from data in the Harris County Flood Warning System website.

That 20+ feet above flood stage at the San Jacinto West Fork and US59 was the highest I found in the county.

Damage to Infrastructure

That 20+ feet destroyed Kingwood College, Kingwood High School, all of the businesses in Kingwood Town Center and Kings Harbor, the southbound lanes of US59, the Union Pacific Railroad Bridge, Memorial Hermann’s new Convenient Care Center, sewage treatment plants, and a senior housing complex.

Lone Star College
Harvey flooded 6 of 9 buildings at Lone Star College/Kingwood. Repairs cost a total of $60 million.
I-69 damage and repairs
I-69 Bridge replacement after Harvey. Repairs took 11 months creating massive delays and detours.
UP Bridge
Union Pacific Railroad Bridge that parallels US59 was destroyed and required complete replacement.
Alspaugh’s Hardware during Harvey
New HEB shopping center 1.5 miles from the San Jacinto West Fork was under more than 7 feet of water during Harvey.

Six years after Harvey, many of the commercial areas in Kingwood still haven’t fully recovered. Anchor stores remain empty in three of five shopping centers on Kingwood Drive between Town Center and US59.

Achieving True Equity

While I’m sympathetic to the plight of poorer neighborhoods, I cringe at the self-serving definition of equity used by a Democratic-dominated Commissioners Court to deny funding to the hardest hit area in the county.

We need a system that’s fair to all, not just some. Anything less will perpetuate racial distrust. This is a public safety issue and public safety should not be politicized.

Posted by Bob Rehak on 9/30/23

2223 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Funding Announced for Massive Detention-Basin Complex on Cypress Creek

9/25/23 – Approximately 425,000 people live in the 204 square mile Cypress Creek watershed which has severe repetitive flooding. At a press conference this morning, County, State and Federal officials announced $50 million in funding for a massive complex of stormwater detention basins on Cypress Creek at T.C. Jester Blvd. to help protect those people.

The basins will span approximately 150 acres on both sides of T.C. Jester and include 1200-acre feet of planned stormwater detention capacity, wet bottoms, and recreational trails.

Approximate boundaries of three detention basins – one will go west of TC Jester and two more east. White area is existing basin.

Altogether, the stormwater detention capacity in this area will increase approximately 75X.

Google Earth calculation of existing and planned ponds

The existing pond covers approximately 2 acres and the new areas will cover more than 150.

Looking E over T.C. Jester. Existing 2-acre basin in foreground was site of press conference. Wooded area beyond will become two new detention basins.

Thanks to County, State and Federal Governments

The $50 million will come from three primary sources:

Harris County Flood Control District Executive Director Tina Petersen also reminded everyone of the money designated for Cypress Creek in the Flood Bond, which was considerable.

The GLO/HUD money has been requested but not yet confirmed although all indications are positive at this time. GLO Commissioner Dawn Buckingham has committed to making sure that people in all parts of Harris County benefit from the $750 million.

Timetable and Project Scope

HCFCD Director Dr. Petersen addressed the next steps in the projects. “A portion of the projects on the east side of T.C. Jester will start construction in the next 6 to 9 months. The remainder should go into construction no later than the end of 2024. So we’re going to see these projects move quickly. This type of progress would not have been possible without the critical funding that our Congressman and Representative secured “

The overall project includes three stormwater detention basins within a broader footprint. Two basin compartments are on the east side of T.C. Jester Boulevard and another is on the west side.

Excavation of the west side basin (see below) has already begun under an E&R (Excavation and Removal) Contract. A private contractor is removing the dirt, almost free of charge, then selling it at market rates to recoup costs and make a profit. An estimated 120,000 cubic yards of material has already been excavated to date.

Work to date on basin west of T.C. Jester. Looking N toward Cypresswood Drive.

The contractor began removing dirt in the general area to get a head start on construction, even before final design of the basin. The final design will begin soon.

Each basin will have a wet-bottom with maintenance berms, side slopes and high banks along the outside.

Construction for all basins should begin no later than Q4 2024. They have estimated 8-month construction timelines.

Extent of Benefits

The three stormwater detention basins will work together – taking stormwater from the main stem of Cypress Creek and holding it until water levels recede on the main stem.

The projects will also have recreational benefits such as hike and bike trails.

Director Petersen stated that the projects will primarily benefit the local area, i.e., benefits will not extend very far downstream. The 1200 acre feet will likely take several thousand homes out of the floodplain.

Even though those homes will be in the Cypress Creek area, 1200 acre feet being held back upstream is 1200 acre feet that won’t be in the living rooms of Lake Houston Area residents during the next big flood.

More to Come

Ramsey also pointed to more projects to come, though he didn’t elaborate. He said, “This is $50 million of the $100 million that will be spent over the coming months in the Cypress watershed. So hold on. We’re getting started. This isn’t the end. This is the beginning.”

Speakers at T.C. Jester Detention Basin Press Conference included U.S. Representative Dan Crenshaw, State Representative Sam Harless, Harris County Precinct 3 Commissioner Tom Ramsey P.E., and HCFCD Executive Director Dr. Tina Petersen.

Posted by Bob Rehak on 9/25/2023

2218 Days since Hurricane Harvey

More People Live in Texas Floodplains than Live in 30 States

According to Texas Water Development Board data compiled for the first state flood plan, 5.9 million Texans live in 100- or 500-year floodplains. That means more people live in Texas floodplains than live in 30 states. Yep. Thirty entire states have populations smaller than that of Texas floodplains.

Other key observations also emerge from the data:

  • One in five Texans lives in a floodplain
  • 42% of those live in the San Jacinto watershed.
  • The number of floodplain dwellers in the San Jacinto watershed alone exceeds the population of 15 states and the District of Columbia.

Where Biggest Problems Are

No other watershed comes close to 42%. To understand where the most people live with the most flood risk, see the table below. I compiled it from reports by the 15 regional flood planning groups in Texas.

Column 3 shows people living in 100-year floodplain (1% annual chance) and Column 4 shows the 500-year (.2% annual chance) floodplain population.

When looking at all people living in floodplains, Texas has almost 5.9 million. The last column shows where the largest concentrations of those people reside:

  • Only two other watersheds, the Trinity and Lower Rio Grande, reported double-digit percentages.
  • Trinity had 11.7%. 
  • Lower Rio Grande had 17%. 
  • No other watershed even made it over 5% of the floodplain dwellers.

The pie chart below really drives home the lopsided percentage of the state’s flood-plain dwellers living in the San Jacinto basin. San Jacinto is the large green area.

Compiled from data reported by each of Texas’ Regional Flood Planning Groups.

The San Jacinto basin has more people living in floodplains than the next five watersheds put together.

Possible Reasons for San Jacinto Issues

The TWDB report does not explain why. Likely, a number of factors contribute to the high percentage: 

  • The state’s largest concentration of people, jobs, industry
  • Rapid growth and lax enforcement of development regulations
  • Insufficient upstream mitigation
  • Proximity to coast, tropical storms/hurricanes
  • High rainfall rates
  • Low, flat terrain

Floodplain Dwellers as Percent of State’s Total Population

The U.S. Census Bureau now estimates that 30,029,572 people live in Texas. With almost 5.9 million of them living in a 100- or 500-year floodplain, that means a whopping one in five live in floodplains.

Of the 20% of Texans who live in floodplains:

  • 8% live in a 100-year (1% annual chance) floodplain
  • 12% live in a 500-year (0.2% annual chance) floodplain.

So, statewide, more people prefer to live in the less risky floodplains. But that’s not the case in every watershed. See the San Antonio watershed in the table above. Three times more people live in the riskier, 100-year floodplain than the 500-year.

Coastline Concentrations

The numbers also show concentrations of floodplain dwellers near other parts of the Texas coastline. 

  • The lower Rio Grande has 13 times more people living in a floodplain than the upper Rio Grande.
  • The lower Colorado has twice as many people living in a floodplain than the upper Colorado.
  • The lower Brazos has 2.5 times more people living in a floodplain than the upper Brazos.
  • The San Jacinto, which is one of the state’s shorter rivers and mostly near the coastline has the highest number of people in floodplains by far.

This 2014 NOAA study showed that 40% of the U.S. population lives in coastal counties. Density is far higher in coastal counties compared to inland areas. Coastal counties have 40% of the population but only 10% of the land. 

Coastal areas also face different issues than inland communities. According to NOAA, “These include increased risks from high-tide flooding, hurricanes, sea level rise, erosion, and climate change.”

Cost of Making People Safe 

The San Jacinto Regional Flood Planning Group recommended $46 billion worth of studies and mitigation projects in its regional plan. And the San Jacinto is just one of 15 watersheds in the state!

In sharp contrast to the magnitude of mitigation needs, the legislature voted only approximately $1 billion for flood prevention projects this year.

If I’ve learned one thing about flood prevention, it’s that nothing moves quickly.

Need for More Awareness 

And that gives me a sinking feeling – especially knowing how few people have flood insurance and how many more need it.

The floodplains in our area are huge. We have a lot of people. And thus, the scary numbers for the San Jacinto watershed. And also consider this. The numbers above are likely understated, because they only reflect riverine flooding and not street flooding from poorly maintained ditches.

With few affordable structural solutions in sight, TWDB should spend some of their funds on public awareness and education while we wait for projects to happen. Few people understand how much flood risk they live with…until they flood.

For the entire 63-page report, see TWDB Board Agenda/Item #8 from their July 25th meeting. (Caution: 33 meg download.)

Posted by Bob Rehak on 7/29/23

2160 Days since Hurricane Har vey

Some Projects in Flood Bond Likely Won’t Get Done While Others Not in Bond Will

While speaking to a public meeting of the Harris County Community Flood Resilience Task Force, Scott Elmer, the Flood Control District’s new Chief Partnership and Programs Officer, predicted that some projects in the 2018 flood bond likely will not get done because of a funding gap.

Elmer made this remark while discussing a list of projects proposed by Harris County Flood Control District (HCFCD) for funding from grants totaling $825 million from the U.S. Department of Housing and Urban Development (HUD) and the Texas General Land Office (GLO).

The $825 million is the last large pot of money still sitting on the sidelines from Harvey. But it likely won’t stretch far enough to complete all the projects in the bond.

Despite a partner funding gap of approximately $800 million (published in 2021), the $825 million would only reduce the gap by approximately an estimated $420 million. How could that possibly be? For one thing…

Not all projects proposed to GLO were in the flood bond.

Origins of Funding Gap

To understand the funding gap, one needs to start with the structure of the 2018 flood bond. It contained a list of projects totaling almost $5 billion, but voters approved borrowing only half of that. The other half was supposed to come from partners, such as FEMA, HUD, local governments and the Texas Water Development Board.

Then COVID and inflation struck. Supply chain issues and labor shortages drove up the cost of projects approximately 20-30%, according to Elmer.

Meanwhile, not all of the hoped-for partner funding materialized. For instance, Harris County Flood Control District (HCFCD) was hoping for a billion dollars from HUD, added Elmer, but received only $825 million. (The County siphoned off almost a quarter billion dollars for Harris County Engineering and Community Services Departments.)

Some Projects Expand While Others May Be Excluded

Complicating the squeeze between the upward pressure of price inflation and less-than-hoped-for funding, HCFCD added (in some cases) to the scope of projects listed in the bond.

  • For instance, HCFCD originally budgeted the Greens Bayou Mid-Reach Project for $20 million in the bond. But HCFCD lists it at $90 million in the proposed GLO list – a 4.5X increase. The first figure reportedly includes the original phases of the project. The second includes those PLUS others which had been deferred for a subsequent bond.
  • Another example: The Arbor Oaks Stormwater Detention Basin in the White Oak Bayou watershed started out as a $13.3 million project in the bond, but now weighs in at $42.3 million. Its price more than tripled.

A person familiar with the Arbor Oaks project said it could easily be phased, but that it appears some phases (which had initially been deferred) were now recommended for immediate construction.

Lower part of Arbor Oaks area on bottom left. Bridge is on West Little York. Looking SE toward downtown.
Lower part of Arbor Oaks area on bottom left. Bridge is on West Little York. Looking SE toward downtown.

Those two projects alone account for an additional $100 million in scope.

“Use It or Lose It” Deadlines Place Emphasis on Shovel-Ready Projects

The projects recommended on the GLO list largely came from projects which had already been extensively studied and which are near shovel ready. That’s primarily because of two factors:

  • The county took 2-years between GLO’s announcement of a $750 million allocation for Harris County and the County’s submission of a plan for spending the money.
  • Meanwhile, the original HUD deadlines placed on using the money have not slipped. So, HCFCD now has its back up against a “use it or lose it deadline” wall.

If money isn’t spent before HUD deadlines, HUD will take the money back – not just unspent funds, but all funds allocated to incomplete projects. So, say for instance, HCFCD spent $50 million on a project, but had $10 million to go when the deadline arrived. HCFCD would have to give back the $50 million it already spent.

Obviously, the specter of having already-spent funds clawed back by the federal government made “construction readiness” a huge factor in project selection that wasn’t there almost six years ago when Harvey struck.

This means projects given priority by the Equity Prioritization Framework were closer to shovel ready. Presumably, they also helped meet Low-to-Moderate Income (LMI) requirements placed on the HUD funds.

No other large pots of aid dedicated to Harvey remain out there. So, annual programs, such as FEMA’s Flood Mitigation Assistance (FMA) and Building Resilient Infrastructure and Communities (BRIC) represent HCFCD’s best hope to make up the rest of the funding gap.

But the competition for those grants is nationwide. They include all states, territories, the District of Columbia and tribal lands. And Texas applications are handicapped because Texas has not updated its building codes in almost a decade to qualify for BRIC funding – despite an 11-to-1 payback.

Updating Project Cost Estimates to Recalculate Funding Gap

Elmer says he cannot calculate an exact funding gap at this time. “We’re still working on updating all project costs with the inflation estimates,” he said.

Elmer hopes to have a firmer estimate by August when the Flood Control District expects to issue its second flood-bond update this year.

I personally hope that the District’s recent reorganization can help it track such financing issues better in the future. It appears that after years of promising residents that all projects in the bond would be completed, now some may not be…while others that were not in the bond will be.

And I suspect I know whose won’t be.

Posted by Bob Rehak on 6/24/23

2125 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.