During September, Sprint Sand & Clay excavated another 5,698 cubic yards of material from Woodridge Village, down slightly from the previous month. However, that brought the total to date up to 150,724 cubic yards – a nice milestone.
Attempted development of the property contributed to the flooding of neighboring properties twice in 2019 during May and September.
Background of Project
Sprint’s excavation will create a sixth stormwater detention basin on the former Perry Homes property purchased by Harris County Flood Control District (HCFCD) and the City of Houston in 2021.
Sprint began excavation in January of 2022 under an Excavation and Removal Contract (E&R). The E&R contract gives Sprint the right to remove up to 500,000 cubic yards of material for just $1,000. Sprint then makes its money back by selling the dirt at market rates.
Where Things Stand
To date, here’s where things stand in relation to possible goals:
Acre Feetof Stormwater Detention
% of Atlas-14 Requirement
% of Ultimate
Site Had When Purchased from Perry Homes
271
70%
47%
Has as of 10/3/23
364.4
94.6%
62.8%
Atlas 14 Requires
385
100%
66%
If Sprint Excavates All 500K Cubic Yards
580
150%
100%
As of 10/3/23
The rate of excavation slowed in September compared to August. During August Sprint excavated 10,353 cubic yards – almost twice as much.
E&R contracts often fluctuate like this depending on home- and road-building activity nearby. Regardless, Sprint still exceeded its contract’s monthly minimum of 5,000 cubic yards.
Before/After Pictures For September
The first two photos below show the extent of excavation at the beginning and end of September.
I see no dramatic changes. They did, however, nibble away at the edges in the top left corner, where the tire tracks lead to. Here’s a closeup of that area.
Rain always slows construction activity and it may have played a role here. The pool of water above was one third this size at the start of the month.
5,698 cubic yards of material for September equals 3.5 acre feet. At that rate, the detention basin will not reach Atlas-14 requirements for another 5-6 months. It appears unlikely at this point that Sprint will meet Atlas-14 requirements by the end of the year – unless Sprint really sprints.
No Engineering Report Yet
At the start of the project, HCFCD planned to go beyond Atlas 14 to accommodate possible future increases in rainfall requirements and upstream growth. That would provide an extra margin of safety for people in the area.
HCFCD still has not released the final engineering report yet for Woodridge Village and Taylor Gully. So we don’t know yet how large this detention basin will be, i.e., beyond Atlas 14.
That final engineering report will also determine the final shape of the basin and its connectivity to other drainage on the site.
Posted by Bob Rehak on 10/3/23
2226 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2023/10/20230930-DJI_0516.jpg?fit=1100%2C733&ssl=17331100adminadmin2023-10-03 08:29:292023-11-01 06:09:35Woodridge Village Excavation Slows
At the end of June, stormwater detention basin excavation on Harris County Flood Control District’s (HCFCD) Woodridge Village property reached 92% of Atlas-14 requirements. When HCFCD bought the property from Perry Homes in 2021, it had only 70% of the required detention capacity under Atlas 14.
Atlas-14 defines the current standard for safely containing a 100-year rainfall. The lack of detention basin capacity contributed to the flooding of hundreds of homes along Taylor Gully twice in 2019, after Perry contractors clearcut the property.
The first photo below was taken at the beginning of June 2023 so you can see how much progress has been made in the last month.
The second shows the site at the beginning of July 2023. The primary changes seem to be additional depth and length.
HCFCD spokesperson Amy Crouser said that, “Essentially, the contractor is free to excavate where they want within the provided footprint.”
Where Does Woodridge Village Excavation Go From Here?
HCFCD’s Excavation and Removal contract with Sprint Sand & Clay calls for excavating up to 500,000 cubic yards. Sprint excavated approximately another 8,000 cubic yards in June. That equals approximately 5 acre feet.
If Sprint keeps excavating at that rate, the table below shows that it could reach Atlas 14 requirements by the end of this year.
However, Sprint’s contract calls for excavating UP TO 500,000 cubic yards. Any excavation beyond Atlas-14 needs would create a safety hedge against future needs should they increase.
Calculations based on original construction plans, HCFCD monthly reports, Atlas-14 Requirements and Sprint contract.
Sprint will make only $1,000 from its Woodridge Village excavation contract with HCFCD, but will make its profit by selling the dirt at market rates. It’s a good deal for taxpayers, but carries some uncertainty with it.
If the demand for dirt dries up and excavation slows, HCFCD and Sprint could modify the E&R contract to complete a smaller detention basin sooner. But I assume it would still meet Atlas 14 requirements at a minimum.
But simply excavating the dirt isn’t the end of the job. Harris County still needs to slope the sides, plant grass, and tie the new basin into the site’s existing stormwater-detention-basin network. Engineers are reportedly working on plans for all that, according to HCFCD.
Posted by Bob Rehak on 7/1/2023
2132 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2023/07/20230701-DJI_0022.jpg?fit=1100%2C733&ssl=17331100adminadmin2023-07-01 12:34:532023-07-01 19:33:34Woodridge Village Excavation Reached 92% of Atlas-14 Requirements in June
In the four weeks since my last update, Harris County Flood Control District’s (HCFCD) contractor has excavated another 11,000 cubic yards of dirt from Woodridge Village. That means Sprint Sand and Clay has removed a total of 104,000 cubic yards since it started work under its Excavation and Removal Contract a little more than a year ago.
Sprint is removing the dirt from what will become a sixth stormwater detention basin on the former Perry Homes site. The lack of adequate detention capacity on the site contributed to flooding hundreds of homes in Kingwood twice back in 2019, before HCFCD purchased the property.
New Excavation Already Second Largest on Site
Already, at 62 acre feet, the new basin ranks as the second largest stormwater detention basin on the 268-acre site. Woodridge Village’s five original basins had the following capacities:
N1 = 13.2 acre feet
N2 = 154.7 acre feet
N3 = 42 acre feet
S1 = 18.6 acre feet
S2 = 42.5 acre feet
The new detention basin could more than double capacity on the site. Ultimately, it will exceed Atlas 14 requirements.
Here’s where the original five are located.
The new basin will go between N2 and S1.
Progress by the Numbers
The 11,000 cubic yards excavated in the last 28 days averages 2,750 cubic yards per week. That’s an increase of 220 cubic yards per week compared to the previous month. It’s also 1,000 cubic yards per week more than the weekly average since the start of the contract.
The current monthly rate more than doubles the minimum required under Sprint’s contract.
The excavation of 100,000 cubic yards marks yet another milestone. Sprint has now removed more than 20% of the 500,000 cubic yards allowed under the contract.
February vs. March Photos
To get a feeling for just how much 11,000 cubic yards is, compare these photos taken at the ends of February and March.
A Head Start on Construction
In December 2022, HCFCD revealed the results of its analysis of alternatives to reduce flooding adjacent to Woodridge and Taylor Gully. HCFCD is now working on finalizing those plans.
Excavation and removal contracts give HCFCD a head start on construction while engineers finish plans. This compresses the timetable.
The contract also saves taxpayers money. It gives Sprint the right to remove up to 500,000 cubic yards for a grand total of only $1000. Sprint makes its money by selling the dirt at market rates to home- and road builders. The only restriction: the dirt can’t be placed in the floodplain.
Posted by Bob Rehak on 4/4/2023
2044 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2023/04/20230401-DJI_0375.jpg?fit=1200%2C799&ssl=17991200adminadmin2023-04-04 10:05:432023-04-04 10:05:45Woodridge Village Excavation Surpasses 100,000 Cubic Yards
A new floodwater detention basin that will ultimately more than double the capacity of Woodridge Village is expanding slowly but steadily. To date, 33,159 cubic yards have been excavated! The pictures below show progress since the start of work in late January.
Sprint has agreed to remove up to 500,000 Cubic Yards of dirt for only $1,000. However, it has the right to sell the dirt at market rates to make a profit. But the dirt can only elevate structures outside of current floodplains.
Three Months Into Contract, Beating the Minimums
When Perry Homes finished its planned floodwater detention basins, it had enough capacity to hold a hundred year rain as defined by pre-Atlas-14 standards. But capacity fell 40% short of Atlas-14 requirements.
The addition of the new detention basin should take capacity well beyond Atlas-14 requirements and create a safety margin that accommodates additional upstream development.
Excavation under an E&R contract can have ups and downs. When construction booms, excavation moves along quickly. But when construction slows, excavation can, too. However, the contract does have minimum excavation requirement of 10,000 cubic yards per month written into it.
At 36,000 cubic yards after roughly 2.5 months, Sprint exceeds the minimum. But if that rate continues, it could take another four years to reach 500,000 cubic yards.
At some point, the county may choose to step in and pay market rates for excavation to speed things up. But until then, every truckload hauled out of Woodridge Village by Sprint will reduce the ultimate cost.
Posted by Bob Rehak on 4/18/2022
1693 Days after Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2022/04/20220417-DJI_0241.jpg?fit=1200%2C799&ssl=17991200adminadmin2022-04-18 17:12:172022-04-18 17:20:21Progress Report New Woodridge Village Floodwater Detention Basin
Here’s something to give thanks for on Thanksgiving. Harris County Flood Control District (HCFCD) announced Wednesday, 11/24/21, that Sprint Sand & Clay could begin excavation of another large detention pond on the Woodridge Village property as early as November 29. Lack of detention pond capacity on the property while it was being cleared contributed to flooding hundreds of homes in Elm Grove and North Kingwood Forest twice in 2019.
Not Enough Detention Pond Capacity Existed to Meet Atlas-14 Requirements
Thus, the twice-flooded homeowners have been living in constant fear since then of every storm that passes overhead. PTSD caused some to postpone home restoration or even move away. So this should come as great news to the community.
Sprint Sand & Clay will excavate material as needed under the terms of an HCFCD E&R contract. E&R stands for Excavation & Removal. HCFCD will pay Sprint just $1000 to excavate 500,000 cubic yards. Sprint then has the right to resell the dirt to developers, contractors and road builders at market rates.
Creating Extra Capacity
When Perry left the site, it had constructed 271 acre feet of detention. The site needed another 108.4 acre feet of detention pond capacity to meet Atlas-14 requirements, but will get 310 (the number of acre feet in 500,000 cubic yards). That almost triples the required additional volume and more than doubles the current capacity…all for $1000.
That extra capacity will create a margin of safety for residents in case expected rainfall rates increase again in the future.
It will also create a buffer against future development. For instance, it should help those downstream on Taylor Gully where it joins White Oak Creek. Rapid development continues upstream on White Oak Creek.
Nature of Contract Will Lower Cost, but Could Extend Completion Date
The nature of an E&R contract benefits taxpayers from a cost standpoint. It’s like getting free help. However, there’s also a potential hitch; demand fluctuation could delay the dirt’s removal. The contract obligates Sprint to remove a minimum of 5,000 cubic yards per month. But Sprint can average that, taking 10,000 cubic yards one month and none the next.
Thus, Elm Grove and North Kingwood Forest residents might see furious excavation activity one month and none the next.
Regardless, HCFCD checks progress periodically with drones. And if Sprint looks like it is not complying, HCFCD has the right to terminate the contract. Otherwise, removal of the dirt could take up to three years.
The contract gives Sprint the right to sell the dirt anywhere with one condition. The ultimate placement must be outside any known floodplain – including the 500-year/0.02% annual chance floodplain.
This is the first time HCFCD has signed such a contract for work outside of Harris County. Woodridge Village sits in Montgomery County immediately north of the county line.
HCFCD started using E&R contracts all over Harris County long before the Bond. It was a way to show progress on detention basins that HCFCD had no money to build. The Cutten Road, Lauder Road, and Aldine-Westfield basins on Greens Bayou all started with E&R contracts.
Pond Will Go in Southern Section of Woodridge
The detention pond excavation will take place close to Sherwood Trails and Elm Grove to help intercept water coming off the steep northern portion of the site. See the green area below.
The new pond will also border the road that Perry built into the site. That will help facilitate removal of the dirt. See the photo below.
Construction Must Observe Stormwater Quality Requirements
HCFCD emphasized that all normal stormwater quality precautions will remain in effect. Rain that falls during excavation will be pumped into one of the site’s existing detention ponds (on the right in the photo above) to keep sediment from migrating downstream. That’s important because HCFCD just finished excavating Taylor Gully to restore its conveyance. No one wants to see it get plugged up again.
Site Closed During Construction
The construction work involves heavy machinery. Physical barriers and safety signage alerting visitors will be placed at access points. Residents should follow all posted signs and remain clear of the construction zone.
Trucks Will Work Around High-School Schedule
HCFCD has coordinated the contractor’s work schedule with administrators at Kingwood Park High School and Humble ISD to avoid arrival and departure times at the high school.
HCFCD officials emphasized that the final dimensions of the pond could change as excavation proceeds. But dimensions should be determined long before Sprint finishes excavation.
Posted by Bob Rehak on 11/25/2021
1549 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/11/20211123-Project-Location-Map-Woodridge-Basin.jpg?fit=1200%2C774&ssl=17741200adminadmin2021-11-24 16:00:312021-11-27 06:13:36Excavation of Additional Woodridge Village Detention Pond to Begin Soon
Tuesday, 7.20.21, Harris County Commissioners will vote on a contract with Sprint Sand & Clay for excavation of a Woodridge Village detention basin. Item #21-3394 on the agenda is only for $1000, but it gives the contractor the right to enter the site and begin removing up to 500,000 cubic yards of dirt (at no cost to HCFCD) which it can then sell.
Backup provided to commissioners states that “This benefits the District because excavation and removal is always the highest cost of any stormwater detention basin that is constructed.”
Amount of excavation TBD – somewhere between 20,000 and 500,000 cubic yards, depending on plans that HCFCD will deliver to the contractor based on the outcome on an engineering study currently underway.
The contractor must properly dispose of the spoils, which it is allowed to sell to make its money on the contract.
Contractor is liable for any materials that are disposed of improperly, i.e., within Base Flood Elevation or the 500-year flood plain and must identify all disposal locations.
Time allowed: 3 years.
Termination of contract possible if contractor fails to excavate a minimum average of 5,000 cubic yards every month.
Contractor responsible for environmental mitigation if necessary, excluding wetlands.
The contractor must provide an approved Stormwater Pollution Prevention Plan and abide by it.
The contract outline contains the map above but does not specify the exact size, depth or location of the proposed work within the outlined area – just that it will occur in Montgomery County. Engineers will supply additional details at a later date.
Sprint Sand and Clay is a regular contractor for HCFCD. Currently, the company is excavating the massive Cutten Detention Basin near 290, Beltway 8 and Cutten Road.
Posted by Bob Rehak on 7/20/21
1421 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/07/20210526-RJR_8313.jpg?fit=1200%2C800&ssl=18001200adminadmin2021-07-19 21:34:452021-07-19 21:41:04Commissioners Vote Tuesday on Contract for Woodridge Village Detention Pond Excavation
Perry Homes’ current contractors have excavated 3X more detention pond volume in ten weeks than the previous contractors did in virtually two years. During this past week, they finished excavating three ponds on the northern section of Woodridge Village. Together, they comprise 77% of the total detention volume for the whole site.
Excavation Done, but Finish Work Remains
That doesn’t mean they’re totally done with the ponds. Recent aerial photos show that they still have much finish work to do. That includes:
Shaping the sides
Creating backslope swales
Installing pipes to funnel water from the swales into the ponds and channels
Ensuring water can flow out of Adams Oaks in Porter on the west side of the subdivision into Taylor Gully as it previously did
Creating concrete “pilot channels” in the center of the ponds and larger channels
Planting grass along the sides of the slopes to reduce erosion
Installing outflow control in several places to hold back floodwaters
Building maintenance roads around the ponds
Elm Grove resident Jeff Miller, who monitors the progress of construction daily, says crews are already hard at work on many of those tasks.
Ponds NOT Expanded Beyond Initial Plans
Miller has compared the width and depth of ponds to the initial plans and verified that the ponds are being built to original specifications. Since the ponds were designed to meet pre-Atlas 14 rainfall requirements, that means the site will still hold 30-40% less runoff than needed to meet current regulations.
With the peak of hurricane season now less than two months away, Perry Homes is in a race against risk. The company may regret the six months of virtual inactivity between the completion of pond S2 and the start of work on ponds N1, N2, and N3 in early April.
The faster pace of current construction puts pressure on Harris County and the City of Houston to complete an offer if an offer will be made. Elm Grove residents lobbied the City and County to purchase the property and build a regional flood detention facility. They center would also help protect downstream residents on the East Fork and Lake Houston.
However, at a Kingwood Town Hall Meeting in February, Mayor Pro Tem Dave Martin announced that the City would not participate in a deal. He said it was the County’s responsibility.
Then in May, the County increased its demands. The County now wants the City to contribute land in lieu of cash to cover half the purchase AND construction costs for creating additional detention.
County and City Clamp Down on Communications
Since then, the County has clamped down on communications regarding this subject. Rumors suggest that all parties are still trying to make a deal happen. But the County has denied all FOIA requests and referred them to the Texas Attorney General for a ruling on their denials. That often happens when negotiations are in progress, according to a knowledgeable source.
What Happens Next?
At the contractor’s current rate of progress, it’s entirely possible that contractors will complete all work on detention ponds in July.
With approximately $14 million dollars invested in the property, with hurricane season here, with lawsuits pending, and knowing that the amount of detention is insufficient to hold a 100-year rain, Kathy Perry must be sweating bombshells.
Ms. Perry may be hoping for a City/County offer, but she can’t be counting on one. If she were, she could have sold the dirt coming out of those detention ponds. Instead, however, she’s building up land elsewhere on the site to keep her options open and develop the site if a deal falls through.
That dirt will have to be moved again at taxpayer expense if the county builds additional detention ponds.
Pictures of Site as of 6/19/2020
Here’s what the site looked like as of 6/19/2020.
Need for Grass if Deal Not Reached Quickly
Note how the grass on the southern side of the gully has all died. That raises a question. If Perry, the City and County do not complete a purchase agreement soon, will Perry plant grass on the northern section to slow runoff. Right now, it’s all hard-packed dirt.
Planting grass over an area this large would be a big investment and might get in the way of construction if Perry decides to develop the land. But it will reduce flood and legal risks.
Posted by Bob Rehak on 6/20/2020
726 Days after Hurricane Harvey and 275 after Imelda
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/06/20200619-DJI_0205.jpg?fit=1200%2C900&ssl=19001200adminadmin2020-06-20 14:57:582020-06-20 14:58:16Perry Contractors Now Focusing on Finish Work for Detention Ponds
In the last week, contractors have finally started excavating the N1 detention pond at Woodridge Village. Work on the excavation of N2 continues. It also appears that they may have started prep work for excavating the N3 pond. See photos below.
The next Commissioners’ Court Meeting is set for May 19. The agenda for that meeting should be posted May 15.
Excavation Begins on N1 Pond (First Pond on Northern Section)
On May 5, 2020, Jeff Miller, an Elm Grove resident, noticed excavation activity near the Webb Street entrance to Perry Homes’ Woodridge Village. Engineers designated this area for the N1 (first northern) detention pond.
Miller also shot this video on 5/6/2020, showing the progress contractors have made on the excavation in one day.
N2 Excavation Continues
I took the shot below on May 1 with a telephoto lens from the north end of Village Springs in Elm Grove. It shows excavation work continuing on the N2 pond.
Additional Work in Area of N3 Pond
On May 5th, Jeff Miller photographed the N3 area from a closer vantage point. It appears only the surface layer has been scraped off so far.
Putting New Work in Context of Entire Project
Here’s the layout for the five Woodridge Village Detention Ponds. Contractors finished work on the two southern ponds earlier this year.
When the northern detention ponds are complete, the detention system will still not be fully functional because there are no streets or storm drains yet to funnel water into them. Still, some detention is better than no detention with hurricane season three weeks away and an above average season predicted.
The County hopes to meet with the City next week to discuss the donation of land. The County also reportedly feels that the four days between Perry Homes’ extended deadline (May 15) and the next commissioners’ court meeting (May 19) will not present a problem if the the City meets the conditions.
Posted by Bob Rehak on 5/6/2020with thanks to Jeff Miller
981 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/05/Detention-Ponds-Numbered-copy.jpg?fit=1500%2C1191&ssl=111911500adminadmin2020-05-06 17:23:192020-05-06 17:48:30Contractors Begin Excavation of N1 Detention Pond at Perry Homes’ Woodridge Village
Instead of accelerating completion of detention ponds on Woodridge Village as Perry Homes promised, the company appears to have pulled all excavation equipment from the site. Contractors who were supposed to have been working on detention pond N-1 have gone…BEFORE they finished S2 and BEFORE they finished a berm sealing off the southern portion of the site at Fair Grove Drive.
Equipment Left Site Instead of Beginning On Next Pond
Perry Homes had promised in its letter to accelerate construction, but this will slow it down – if they ever return. The only work being done Friday? Removal of some dead tree piles on the northern portion of the site.
Jeff Miller took all the pictures and videos below on Friday and Saturday. He also monitored work on the site and provided this scouting report.
Woodridge Village Section One Now a Virtual “Ghost Town”
This weekend, Woodridge Village Section One looked like a ghost town, not a bustling construction site with people working against a deadline.
Still Removing Dead Trees/Mulch on Northern Section
Perry Homes Intentions Now a Mystery
As of Sunday morning 12/22/2019, no equipment actually working on construction could be seen on the site. The excavators and dump trucks parked at Fair Grove for months have been removed.
Perry Homes is NOT accelerating completion of detention ponds as it promised the City of Houston.
Instead, Perry Homes has thrown a curtain of silence around this job. It’s hard to know what their intentions are. At this point, Perry Homes’ lawyer J. Carey Gray has as much mud on his face as Elm Grove residents had in their homes.
The only thing we can say with certainty: Lowering flood risk for the people of Elm Grove does not seem high on Perry Homes’ priority list.
For Sale And For Lease Signs Serve as Christmas Yard Decorations
Meanwhile, a drive down Shady Maple or Village Springs, the two streets that border Taylor Gully, revealed residents’ attempts to salvage Christmas from the chaos of floodwaters. Dumpsters and debris still line the streets. Some people still live in trailers in their driveways. No apple cider around the hearth for them. They’ll be lucky to find space for a table top Christmas tree. For Sale and For Lease signs outnumber Christmas yard decorations ten to one.
Kathy Perry Britton just added another credit to her resume, “The CEO Who Stole Christmas.”
Posted by Bob Rehak on 12/22/2019with reporting and images by Jeff Miller
845 Days since Hurricane Harvey and 94 since Imelda
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2019/12/IMG_0679.jpg?fit=1200%2C900&ssl=19001200adminadmin2019-12-22 12:09:152019-12-22 12:58:38Perry Homes Pulls Excavation Equipment From Woodridge Village Before Finishing Detention Ponds
Thursday night at the Kingwood Town Hall Meeting, the City discussed a meeting between Perry Homes and city officials including the City Attorney. The subject: How to avoid flooding Elm Grove and North Kingwood Forest again. City officials said they demanded multiple concessions from “Perry Homes.” Two days later, and only hours before the Town Hall meeting, Perry Homes (according to City officials) sent the City a letter outlining what it could do. Mayor Sylvester Turner read portions of the letter to the overflow crowd. It met with mixed reaction. Some people were grateful; others skeptical; still others angry.
Much to his credit, Council Member Dave Martin posted the letter on his FaceBook page. I have reposted it here for your convenience, along with my reactions and those of several other residents.
Rehak’s Opinions
I was not in the meeting between “Perry” and the City so I cannot comment on the tone of the meeting or how the City presented its “demands.” However, several things struck me about this letter right from the opening paragraph. First of all, it’s not from Perry. That’s why I put Perry in quotes above.
The developers expressed how saddened they were by Elm Grove flooding. Yet they are suing the victims. This raises a sincerity issue from the git-go.
They say, “Your idea of sharing our collective intellectual capital was a good one, and we appreciate having the City’s input.” Sounds pretty collaborative to me. That’s normally good, but it certainly does not fit with how the City characterized meeting.
The law firm representing Perry’s subsidiaries, PSWA and Figure Four Partners, sent the letters, not Perry.
Even though the engineering plans for the site call for DETENTION ponds, the lawyer now refers to them as RETENTION ponds. The difference between the two is storage capacity. The latter is like renting a storage shed that’s 80% full…and still paying full price. The City attorney needs to question this.
The letter only says that they discussed accelerating the schedule, not that they have accelerated it.
The letter lays out timing to construct each detention pond. But it doesn’t say whether they will perform work concurrently or sequentially. If concurrently, the work would take 9+ months. If sequentially, it could take 26 months. They talk about beginning “each project as quickly as the plans can be approved.” This suggests a one-at-a-time approach that could potentially add up to 780 days…assuming there are only “minimal delays” for bidding, approvals, weather, etc.
They promised to spend 45 days completing the two southern ponds. Those ponds are already substantially complete.
The letter promises to build a berm 2 feet above the 100-year flood elevation between Woodridge Village and Elm Grove. An even higher berm failed during Imelda. Floodwaters overtopped it. Perhaps that’s because Montgomery County bases flood maps on data from the 1980s.
They talk about delaying development of homes and streets (impervious cover) until they complete detention ponds. Delaying impervious cover seems like a genuine concession; developers like to build in sections so profit from one can help bankroll the next.
The lawyers claim their clients have not yet completed plans and specifications. However, LJA Engineering seemed to have a pretty comprehensive set.
The letter provides no guarantees and no penalties for non-compliance or missing target dates.
Because Perry has never revealed a construction timetable, we can’t tell whether this schedule beats their original one.
All in all, the timetable in this letter, seemed to take a lot of time for work that they could have completed by now.
Miller recently had an “aha” experience when driving by a 5-acre commercial construction site in Kingwood. It had more heavy equipment operating on it than Perry’s 268-acre site did at its peak last summer, he said.
Miller is a retired process engineer. Based on observation of that and other sites, Miller estimated excavation of three more detention ponds would take only about a month if Perry pulled out the stops. Other engineers and construction experts share this opinion.
Josh and Jon Alberson’s Opinions
Both of these brothers have engineering degrees from Georgia Tech. Josh is a chemical engineer and Jon a civil engineer. Jon works on giant construction projects for one of the largest companies in America. The Alberson brothers estimate only 10 days more than Miller. They shared their calculations. The calculations assume a two-step process. Excavate and stack the dirt. Then spread and grade it at a later time.
Basically, they calculated the volume of dirt that needs to be removed. Then they divided that volume by the per-load capacity of heavy equipment. Next, they estimated the time to move one load and return for the next. Using this technique, they could ultimately determine the total time it would take to excavate the three remaining ponds. They consulted with Caterpillar on the capacity of different types of equipment and their recommendations. Follow along to check their math.
Assume tractor cycle time for scraping, moving to pile, and returning to pond is 15 minutes. This would be a conservative transit time.
Then assume the tractor operates 20 hours per day.
Lunch – 1 hour per shift = 2 hours per day
Maintenance = 1 hour per day
Breaks = 2 x 15 minute breaks per shift = 1 hr per day
Loads per Day = 20 hours per day * 4 loads per hour = 80 loads per day
Number of Days with 1 Scraper Tractor
10,582 loads / 80 loads per day = 132 days
Number of Days with 4 Scraper Tractors
10,582 loads / (80 loads per day * 4) = 33 days
Assume 20% lost time due to non-productive time, weather, etc.
33 days * 1.2 = 40 days
Said Jon, “Most projects can move 8000 cubic yards per day.”
The two agreed on roughly the same time frame but argued over the optimum combinations of day and shift lengths, pieces of equipment, etc.
That’s just the time to dig the ponds. It assumes they stack the dirt somewhere nearby, then grade and compact it at a later date. Let’s assume that takes another month. But the ponds are excavated!
Now, we’re talking roughly TWO months instead of 9 to 26 months. And beating one or two hurricane seasons.
Note: The LJA Engineering report, upon which these calculations are based, shows at least three different storage capacities for the ponds on the northern section under “ultimate conditions”:
Exhibit 2 shows a total of 209.4 acre feet.
Table 3 shows a total of 154.2 acre feet.
Table 7 and the Conclusion show a total of 163 acre feet.
For the analysis above, the Albersons used the highest volume because it represented the most difficult case. Contractors could excavate the smaller totals, if accurate, in even less time. If 154.2 is accurate, excavation would take only 30 days.
Nancy and Abel Vera’s Opinions
Regardless of how Perry Homes staffs this job, it’s going to take some sweat. That’s the one thing that was not in evidence yesterday or today. Despite the assurances of J. Cary Gray, Attorney at Law, multiple residents reported seeing NO activity on the construction site.
As of Saturday afternoon, Nancy Vera still has seen no activity on the construction site. See the video below taken the day after the Town Hall.
Vera’s husband Abel, manages giant construction projects around the world for one of the world’s largest engineering companies. He agrees that the construction could move much faster.
“If they had the proper equipment and man power, they could move fairly quickly. But they have never done that! They took more than six months to put in this one pond by our house [S2]. And they didn’t even really get going till after the May 7th storm.”
Abel Vera, Resident just south of S2 Detention Pond
A Faster Way?
This video shows the scraper equipment that Alberson and Caterpillar recommended to move large volumes of dirt quickly. The video runs 13 minutes but you will get the idea after a minute or two. These guys collect dirt while rolling.
Contrast that with what I saw earlier this summer. I watched as a backhoe filled up one dump truck after another. It took several minutes to fill up each truck with multiple scoops. Then each truck took the dirt to its ultimate destination more than a half mile away rather than piling it up near the pond and returning for more dirt. It was a long, slow, dusty procedure with lots of dead time between loads.
A Good Deal?
So, does the letter from Counsellor Gray represent a good deal for the residents of Elm Grove. I think not. If Perry Homes really cared about the safety and peace of mind of Elm Grove residents, they could move much faster. The letter commits them to nothing except delaying homes and streets until all detention is in. That’s something. But with most of the surface being hard-packed clay, the threat of rapid runoff remains until they finish all those detention ponds. And someone really needs to proofread that LJA report. It’s scary to think that this whole development could be based on erroneous calculations. I’m surprised Montgomery County approved it.
Posted by Bob Rehak on 10/19/2019 with help from Josh and Jon Alberson, Abel and Nancy Vera, and Jeff Miller
781 Days since Hurricane Harvey and 30 since Imelda
The thoughts in this post represent my opinions on matters of public policy and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2019/10/Cat.jpg?fit=1500%2C700&ssl=17001500adminadmin2019-10-19 14:11:002019-10-19 17:17:16“Perry” Letter: A Good Deal?