Tag Archive for: Entergy

Northpark Drive Expansion Project Overcoming Hurdles

8/8/24 – In the last year, the Northpark Drive expansion project hit several snags. But one by one, project partners seem to be overcoming the hurdles.

Contractors discovered utility poles and gas lines in their way. Permits to bore under the railroad and bridge over it took longer than expected. Delays forced changes in plans to keep crews busy. And eventually, when project managers ran out of alternative options, contractors had to shift crews to other jobs.

After months of delays that hampered progress, hope is finally on the horizon.

Paving the Way for Faster Progress

The pace of construction could soon accelerate again.

  • CenterPoint has moved all of its facilities east of Loop 494 and only a few conflicts are left west of 494.
  • Entergy is almost done removing its east-to-west poles at Northpark/494. This will let contractors complete the storm water drainage system, construct new feeder roads, and build at-grade vehicle crossings over the rail tracks. 
  • Comcast, Tachus, AT&T, PS Lightwave, MCI, Optimum, BrightSpeed, and Crown Castle have either finished relocating their facilities, submitted relocation plans under review at the City, or received Permits for relocation. In the last case, they have also provided schedules to the TIRZ
  • A new water main will allow service to be transferred from Porter SUD to City of Houston. This same water main also serves the newly installed fire hydrants along Northpark. 
  • Contractors and UnionPacific have resolved right-of-way issues. Work should start on the rail crossings later this year. 
  • Project managers have acquired additional rights of way from private property owners
  • Alternate plans are in place for rerouting traffic
  • Entergy has submitted Plans for permits that will let them bury their power lines west of 494 and underneath the railroad tracks  on Northpark Drive.

Most of these changes, while barely visible, are highly critical.

Improved Working Relationship with Entergy

Project Manager Ralph De Leon predicts motorists could soon see visible progress. Brian Garcia, Entergy’s customer service manager, agrees.

Both men cite an improved working relationship. Weekly meetings between their teams have reportedly resolved most technical, permitting, and scheduling issues.

Next Steps

Harper brothers has finished burying culvert down the center of Northpark. Now the company will begin installing culvert on the north side of the street westward. It will eventually connect to the system at Self-U-Storage.

Looking west at extent of culvert installation. From here, culvert will move north/right to make room for surface turn lanes and a bridge over the railroad tracks and Loop 494.

The next leg will go under the railroad tracks and Loop 494. It will  connect the eastern and western sections of the storm water drainage system.  

In general, the next major steps for the Northpark Drive Expansion include:

  • Shifting westbound traffic toward the center
  • Burying drainage culverts on the north side of the street.
  • Building permanent access roads on the north.
  • Shifting traffic back to the permanent lanes.

Keep your fingers and tire jacks crossed. Working out many of these unforeseen issues delayed the project 188 days so far. The delays also forced Harper Brothers Construction to divert some of its crews to other jobs to keep them busy.

Photos of Work to Date and In Progress

Crews today worked on bringing power to new, temporary traffic signal locations.

Crews worked on three of the four corners of Northpark and Loop 494. Old power lines on the fourth corner (lower right) were previously de-energized and poles topped. Comcast will reportedly move its cable on those poles next week.
Crews are also spreading and compacting dirt over installed culverts. (Looking W toward US59)
Ditto in the opposite direction. Looking east toward Diversion Ditch.

Upcoming Construction Schedule

To look ahead at planned Northpark Drive expansion activities for the next few weeks, see a schedule on the Lake Houston Redevelopment Authority project page.

For More Information

For more information about Northpark Drive expansion and a history of the project, see these posts on ReduceFlooding.

Posted by Bob Rehak on 8/8/24

2536 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Northpark Expansion Obstacles Finally Being Addressed

6/21/24 – Entergy has removed some – but not all – blockages to the Northpark expansion project related to its equipment. The project is designed to build an all-weather evacuation route for 78,000 Kingwood residents.

Entergy removed several of its poles that blocked expansion of the roadway earlier this week.

The company is also committing to dates for the removal of other poles that remain in the way of construction.

The Lake Houston Redevelopment Authority/TIRZ-10 first notified Entergy that it would have to move its equipment in 2020. On February 6th this year, the City of Houston finally set a firm deadline. It gave Entergy 30 days to move its equipment. That deadline was obviously missed.

Entergy says it has been working diligently to help Northpark expansion move forward. As we move into what is expected to be a very busy hurricane season, here’s where the TIRZ and Entergy say things stand and what I have been able to verify photographically.

Some Poles Already Removed Earlier This Week

Entergy removed several poles that blocked construction progress on Tuesday, June 18. They were located near Dunkin’ Donuts and Public Storage.

Note old pole on ground in front of Public Storage (out of frame to right).

Primoris, an Entergy contractor, took down that and several other poles that day.

More Entergy poles being removed by Primoris crew in front of Dunkin’ Donuts

Two other groups of poles continue to block construction, however. Here’s what Entergy is doing to address those.

Blockage #1: Poles West of Car Wash

The first blockage is a group of three poles immediately west of the Quick Quack Car Wash where new westbound turn lanes will begin. This group of poles still holds a Comcast cable. See below.

Looking W. Three short poles on left between Duncan Donuts and Quick Quack Carwash have yet to be moved.

Comcast has committed to burying this cable next week. Then Primoris can remove the poles for Entergy.

Blockage #2: Poles near Loop 494

The second group also has three poles – at Loop 494 and the Union Pacific railroad tracks. However, these three poles have two separate issues with which Entergy must contend.

  • They supply redundant power to the businesses along Northpark.
  • An Internet provider, Brightspeed, also has a line mounted on two of the three poles. (See #2 and #3 below.)
Entergy Delay Forces Change to Northpark Expansion Plan…Again
Looking W from over Northpark across 494. Three more Entergy power poles blocking Northpark Drive expansion.

To get these three poles out of the way of Northpark expansion, Entergy has three options:

  • Move them north (right in photo above)
  • Bore under the roadway and tracks
  • A combination of the above.

According to Brian Garcia, Entergy’s project manager, his company has chosen a combination of the two approaches. It will move the overhead lines north temporarily while it works out permits and easements with TXDoT and Union Pacific.

Once Entergy has secured permissions needed, it will then bury the lines, a solution that is more reliable. It is also more expensive because two moves are involved rather than one. But it should let construction move forward faster.

Entergy has committed to delivering a plan to temporarily relocate Pole #1 (in the photo above) by end of day today.

Weather permitting, Entergy also plans to actually relocate its wires on Poles #2 and #3 by 6/28/24 – next Friday. Entergy would then top its old poles. That would let BrightSpeed remove its cable. And then Primoris could remove the old poles.

Union Pacific Sets Meeting on Crossing Signals

Meanwhile, Union Pacific (UP) has set a meeting for July 9 to talk about relocating its crossing signals. It’s a firm deadline, according to De Leon, the TIRZ’s project manager for Northpark Expansion.

Unexpected delays by any party in this ballet of corporate behemoths could create a domino effect that could push the Northpark project back into next year. Or even force cancellation.

Blockage #3: Transformer At Exxon

Meanwhile, at the Exxon Station near US59, Entergy also has a transformer that must be moved farther back from the roadway. See red circle below. The distance has to do, in part, with line-of-sight issues for motorists. Its height means that it could block the view of motorists entering or leaving the roadway.

Entergy transformer at US59 (top) and Northpark (right) circled in red.

But working around the transformer presents serious construction problems. The wires leading to/from it are not up to code, according to De Leon.

He says that the City building code calls for underground wiring to be encased in steel. But the wiring in this area is not. That could jeopardize the safety of heavy equipment operators working to expand Northpark in this area.

Garcia disagrees. He says all of their equipment and lines meet or exceed all applicable building codes.

Several weeks ago, a contractor for the TIRZ did some exploratory hydro-excavation as part of its due diligence for the roadway expansion project. The contractor found Entergy wires that were exposed, not encased like De Leon says they should have been.

Wiring near Entergy transformer exposed during exploratory hydro-excavation process.

De Leon shared this photo in the June TIRZ board meeting. He says it creates a major safety issue for construction workers near the transformer. According to him, the workers could be electrocuted if, for instance, the bucket of an excavator accidentally cut one of the wires.

Garcia says Entergy crews will move the transformer. But De Leon and his contractors are concerned about what could happen if they encounter similar wires as they work in the same general area.

Posted by Bob Rehak on 6/21/2024

2488 Days since Hurricane Harvey

Entergy Delay Forces Change to Northpark Expansion Plan…Again

6/15/2024 – Fireworks erupted in the Lake Houston Redevelopment Authority/TIRZ-10 Board Meeting on 6/13/24 over more Entergy delays related to the Northpark Expansion plan.

Four years after being notified to move its power poles and a transformer, Entergy still has equipment blocking the expansion. Ralph De Leon, the TIRZ project manager, explained that as a consequence, the TIRZ has been forced to modify its plans yet again.

Power Poles Conflict with Westbound Detour

Original plans called for routing westbound traffic in the vicinity of the bridge over the railroad and Loop 494 onto permanent turn lanes next to businesses. However, because Entergy power poles still stand where those turn lanes would go, LHRA decided to move traffic south, parallel to the existing eastbound lanes. See blacktop in photos and schematic diagram below.

Looking ESE from over Loop 494. Instead of funneling outbound traffic into new permanent lanes in front of the businesses on the left, commuters will use temporary lanes built on the blacktop. Photo 6/13/24.
Looking west toward US59 at asphalt that will become temporary westbound lanes. Photo 6/13/24.

The permanent concrete lanes originally were to have gone in the grassy area to the right where the first line of poles is.

Here’s a schematic diagram of the change.

For full, high-res PDF, click here.

Cost Impact Not Yet Clear

Replacing permanent lanes with alternate temporary lanes means that LHRA now will build these lanes twice instead of once. That will increase the project cost. However, no-one in the meeting mentioned an exact dollar amount.

De Leon said that in order to stick with the original traffic diversion plan, the deadline for removing the poles was last year.

Yet Entergy has not yet moved its poles where the new lanes will go. Nor have they provided a timetable for removing the poles. However, Brian Garcia, Entergy’s project manager, expressed confidence that the last poles would be removed “soon.”

It would be safe to say that most other people in the board meeting did not share his optimism. Discussion got heated at times as LHRA tried to pin Entergy down regarding a deadline. Hence, my reference to fireworks above.

Representatives of the City and TIRZ also made it clear that they intended to deduct the cost of the temporary lanes from any money that Entergy might have been entitled to for moving its transformer near the Exxon Station.

Two Groups of Poles

Two separate pole issues exist:

  • The original poles between Benjamin Moore Paints and Loop 494
  • Three key poles near the intersection of Northpark and Loop 494

The first group of poles has been “de-energized.” That means transformers and electric wires have already been moved. However, the old poles still have a fiberoptic communication line hanging from them. (Two lines in places). See below.

Looking west toward US59. Old poles on left still have fiberoptic line on them which must be moved to new poles on right. Photo 6/13/24.

The owner(s) of those remaining line(s) on the left must move them before Entergy can take down the old poles. But the fiberoptic provider has had weeks and not moved its line(s).

At the end of the line of poles above on the left sit three key poles shown in the aerial view below.

These three poles provide a redundant source of energy for businesses along Northpark. The businesses are also fed by power from Kings Mill. Photo 6/13/24

In the power business, it’s a standard/best practice to feed areas from at least two different directions. That way, if power is knocked out on one leg, the other leg can still supply homes and businesses.

Entergy has two choices with these three poles. It could move them north and continue to feed redundant power to Northpark businesses with overhead lines. Or, it could tunnel under Loop 494 and the railroad tracks. Entergy prefers to bore under for reliability reasons.

Again, Entergy’s Garcia is confident that the easements TXDot and Union Pacific require will be easy to obtain and come quickly. But the City and TIRZ do not share his confidence. They struggled for years to obtain their own easements and permits.

So, rather than just move the overhead lines north, Entergy is negotiating with TXDoT and Union Pacific to bore under their properties.

Who Will Bear Increased Costs?

After repeatedly being asked to provide a timetable for compliance, Entergy supplied none and instead shifted the conversation to its costs.

The overhead lines have sufficed for years. But Garcia says that Entergy prefers the underground option.

However, if all parties do not complete construction before October, the entire project could be delayed for months and possibly even cancelled. According to De Leon, Turner Brothers’, the prime contractor with the TIRZ, has other projects stacked up and waiting.

Turner Brothers would have to redeploy crews if they can’t keep them working on Northpark. And there’s no guarantee when those crews would be available again to work on Northpark.

But when the boardroom discussion turned to the need for Entergy to act quickly, Entergy turned the discussion to cost.

Garcia says there’s a significant cost for Entergy to move its overhead lines. If the company can bore underground instead, it would prefer to do that rather move its lines twice.

As a consequence, the TIRZ will be forced to shift traffic twice to keep the project moving.

Moreover, both the TIRZ and Entergy face a firm deadline from the railroad, whose busy season starts in October. They must have boring complete well before then with time for the railroad to lay new track and install new signal equipment.

Meanwhile, Entergy still has not moved its transformer near the Exxon Station at US59.

Argument Over Reimbursement

The transformer is outside the City’s easement but the power poles are inside.

Under Texas law, Entergy is entitled to reimbursement for costs outside City easements, but not those inside.

Ralph De Leon, Northpark Expansion Project Manager

Paying to move poles inside City easements would constitute a “gift of public funds,” which is illegal.

The two sides reached a tentative agreement on reimbursement last December. But then in January, Entergy demanded double the agreed total – without explanation or itemization.

In the June TIRZ board meeting, Garcia said he still needed to get the itemized costs approved by his management.

TIRZ directors (who are unpaid volunteers) could become liable for illegal payments to Entergy, hence the demand for itemized costs.

Other Northpark News

The pace of construction has also slowed due to heavy rains in May, which still have soils wet. When they dry out, contractors will resume:

Preparing to pour new concrete

  • Demolishing old concrete near Loop 494
  • Excavating the south pond at the US59 entry
  • Installing culverts
Looking E at progress of culverts. Ponding water in ditch (foreground) has slowed installation. Photo 6/13/24

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding. Many contain information about previous delays that caused plan changes:

Posted by Bob Rehak on 6/15/24

2482 Days since Hurricane Harvey

Entergy Makes Some Northpark Progress, but Significant Issues Remain

Entergy has made more progress on the Northpark Drive expansion project in the last two weeks than in the previous four years. But despite what you see in the photos below, significant issues remain to clear the way for the first all-weather evacuation route from Kingwood.

Some Progress, But…

Last week, Entergy, a $4 billion company in Texas, erected nine new power poles outside of the City’s right of way. This week, their contractor, Primoris Services, started the process of stringing wire. That’s good news. Really!

But unseen obstacles could still delay the project significantly. For instance:

  • Who will pay for moving Entergy’s ground-mounted transformer and associated power lines near the Exxon Station at US59? Entergy reportedly still wants the Lake Houston Redevelopment Authority (LHRA) to pay for upgrading and moving the transformer and buried cables. LHRA insists that’s an illegal ask because it would constitute a gift of public funds.
  • More power poles remain near Loop 494 that will be difficult to move because of conflicts with new storm drains.
  • Entergy must tunnel under rail tracks.
  • Entergy reportedly still refuses to commit to completion dates for moving its equipment.

Will Entergy Beat Union Pacific?

If Entergy does not resolve issues near the railroad tracks before Union Pacific crews arrive to install new signals and improve the road bed, the project could be delayed years.

Union Pacific reportedly has two crews that rotate through 27 states handling such issues. If we miss them this year, the Northpark project goes to the back of a very long line, according to Ralph De Leon, Northpark project manager for LHRA.

Entergy has already blown a City deadline to move its equipment by March 8. So they have already missed a 30-day deadline by 42 days. But according De Leon, Entergy still refuses to commit to any completion dates.

Ray of Hope

According to Houston Public Works (HPW), Entergy has assigned a new project manager and team to the project. This could be a sign of good things to come.

HPW Senior Division Manager Patrick Nguyen says the City is working with Entergy to resolve easement issues that could result in construction delays and cost escalation. Mayor John Whitmire, who is committed to seeing the project through, has reportedly asked Nguyen to act as an arbitrator.

In an email received today, Nguyen said that “Entergy has assigned a new project manager along with a team to the project.” While diplomatically expressing hope, he did not elaborate further.

Progress Last Week

All nine poles erected last week had pulleys and rope or cables threaded through them when I took these photos today. According to one expert I talked to, crews will use the rope or cables to “pull wire.”

Close up (top left) of cables/ropes and pulleys that will be used to pull new electrical wires from pole to pole.

Compare old and new poles in lower left. Once wire is pulled to a pole, it will be attached to the tip of the insulator.

Moving the poles farther from the street will create room for a six lane bridge plus two turn lanes on each side of the bridge (to meet TXDoT requirements).

LHRA first notified Entergy to move its equipment in 2020. Entergy still won’t commit to a completion date.

The mess at 494

Other Northpark News

Contractors are smoothing out the dirt placed over the culverts between the Kingwood Diversion Ditch and Russell Palmer Road.

Looking west toward Kingwood Diversion Ditch from over Russell Palmer Road

Northpark will expand inwards. Contractors will pour two lanes of concrete in the dirt-covered area above. If I read the schedule correctly, paving in the area above could start within the next two weeks.

West of Russell Palmer (below), contractors buried almost another hundred yards of 6’x8′ culvert last week. Weather permitting, and if they can keep up that same rate of progress, they should be to the railroad tracks in another three months or so.

Looking west along Northpark. Last week, culvert crews were barely past the Shipleys Donut sign the lower right.

However, the culvert will not go all the way to the tracks down the median. As it approaches the point where the bridge starts to rise, it will veer to the right and go under the turn lanes where Entergy is moving back its poles.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 4/19/24

2425 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Northpark Culvert Installation Resumes

Northpark culvert installation resumed in a major way last week.

For several months, utility conflicts stalled installation of the 6’x8′ box culverts down the center of Northpark Drive. During preparation of the center ditch, contractors found gas lines buried at insufficient depth.

With those conflicts now resolved, according to Project Manager Ralph De Leon, installation of the box culverts can now resume. When contractors complete the culverts, dirt will be placed on top of them, and then two lanes of pavement on top of the dirt. The result will be a Northpark Drive that expands inward instead of outward. It will create three lanes in each direction…that should not flood like the thoroughfare currently does.

The expansion project has two primary goals:

  • Get more people in and out of Kingwood faster…
  • …in all weather conditions, even when other thoroughfares are cut off by flooding.

During Hurricane Harvey, West Lake Houston Parkway, Hamblen, Kingwood Drive, and parts of Mills Branch Road were all blocked by rising floodwaters.

Pictures of Installation Progress as of 4/15/24

Since my last post on 4/8/24, contractors completed installation of the culvert at Parkwood Baptist Church and are working their way west past Russell Palmer Road. Today, they were working in front of Shipley’s Donuts.

Looking E. Northpark culvert installation west of Russell Palmer Road near top of frame.
Looking E at Northpark culvert installation. Heavy equipment lifting massive section of culvert to place in hole.
Once men finish prepping the hole in the background…
…step and repeat for almost another mile to 494.

In Other Northpark News

Entergy managed to install five more power poles in the last week. That brings their total to nine in four years.

The new power poles sit back farther from the street. That will create room for four more lanes of traffic adjacent to the bridge that will go over the railroad tracks at 494. The four include two inbound turn lanes and two outbound turn lanes to/from 494.

Project managers first notified Entergy of the need to move the poles in 2020. Construction experts tell me the project could have easily been completed by now.

Not much new has happened at the entry ponds at 59. Heavy rains a week ago have the bottoms covered with water.

Looking west at area that will become the North Pond. Parts of new turn lanes are already being used, reducing traffic congestion somewhat.
Looking SW at South Pond
More culvert awaiting installation which will carry excess stormwater between ponds and Ditch One.

See the route below. It will go behind the businesses on the north side of Northpark until reaching the Kingwood Diversion Ditch and Bens Branch.

Northpark Drive drainage improvements

That pretty much does it for visible progress during the last week.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 4/15/24

2421 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Northpark Entergy Saga: New Power Poles Slowly Going Up

In the latest episode of the Northpark Entergy saga, last week, Entergy finally began erecting new power poles outside of the Northpark Drive expansion right of way. While this is a huge improvement after four years of no Entergy activity, don’t get too excited.

In its quest to help develop an all weather evacuation route for 78,000 people, Entergy managed to erect four poles in five days. And there’s no sign of progress near Entergy’s transformer by the Exxon station at US59 either.

In other Northpark news:

  • The extra northbound turn lanes at 59 seem to be complete almost all the way back to Chick-Fil-A.
  • At Russell Palmer and Northpark, the crossover closure will take longer than expected.
  • Construction of the four decorative planting areas in the two stormwater retention-basins at US59 is now complete and contractors have filled in dirt behind the retaining walls.

See photos and details below.

Last of four decorative landscaping areas (right) is now complete and backfilled.
Entergy … La La, La La La!

On 4/2, I reported that Entergy had delivered new power poles to Northpark in preparation for moving their lines out of the City right of way.

Five days later and four years after first being notified, Entergy appears to have erected a grand total of four poles while others remain scattered on the ground.

The four Entergy power poles erected along Northpark during the week of April 1, 2024

Here’s what two look like from the ground.

See new poles on the right. Entergy has not yet placed equipment on any poles, nor has it relocated wires.

Meanwhile, many of the poles they delivered to the job site last week remain scattered on the ground.

Looking E. Northpark Drive (on right). UP Railroad Tracks out of frame on the bottom.

Moving the poles back will make room to construct turn lanes from Northpark onto Loop 494.

As I photographed Entergy’s underwhelming progress, I was reminded of what American ingenuity can achieve when companies put their shoulders into projects.

For instance, the transcontinental railroad took six years to build. Even more impressive is what the companies could achieve in a day…without modern equipment.

The Union Pacific once laid eight miles of track in a single day. Stung by the competition, “the Central Pacific concocted a plan to lay 10 miles in a day. Eight tracklayers put down 3,520 rails, while other workers laid 25,800 ties and drove 28,160 spikes in a single day.”

Compare that to Entergy’s four poles in four years. I guess that’s what happens when you give companies a monopoly in an area.

On February 6, the City of Houston gave Entergy an ultimatum to have the project completed by March 8. Tomorrow will be April 8.

Entergy appears to have put its A Team on the project. Speaking of A Teams, it only took three years to invent the atomic bomb, test it, deliver it, and conclude World War II.

But of course, Entergy is dealing with electricity and there are safety issues involved.

Entergy transformer at US59 still unmoved.

The Entergy transformer will require some study. To inspire public confidence, Entergy reportedly is putting its top engineers on the project.

Northbound Turn Lanes onto US59

On a happier note, traffic is now using new northbound turn lanes at US59, temporarily eliminating a huge bottleneck…until new pavement will go down for the existing lanes.

Looking W from 59 toward 494. North is left.

A new schedule posted by the Lake Houston Redevelopment Authority shows that most work in the next month will focus on underground utilities. Those include water lines, storm drains, and box culverts on both sides of the street.

According to the schedule, Harper Bothers Construction will also install the giant reinforced box culverts in the median of Northpark toward 59 for the rest of the month.

Before pavement goes farther east, more underground work is needed. Note culvert lined up in front of businesses.

Russell Palmer Crossover Work Delayed

The work near the Russell Palmer intersection must be taking longer than expected. Originally it was supposed to be finished by tomorrow morning at 5AM. But the new schedule shows it being completed by next Friday, 4/12/24.

A flashing sign along Northpark this morning warmed motorists to expect daily lane closures. However, there were none this morning. And contrary to earlier announcements, motorists were making it through the intersection.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 4/7/24

2413 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

New Entergy Power Poles Finally Arrive On Northpark

I got a tip last night that new Entergy power poles finally arrived. Today, I photographed the long-awaited equipment. The poles are not up yet. Nothing is connected to them. Most are just lying in the dirt.

In the quest to build an all-weather evacuation route for 78,000 Kingwood residents, readers may remember that the Lake Houston Redevelopment Authority/TIRZ-10 has sparred with Entergy for four years. Entergy’s power lines need to be moved out of a City-owned easement to accommodate the expansion of Northpark Drive.

I have confirmed that the poles belong to Entergy. Entergy also claims that they will begin erecting the poles in the next few days, weather permitting.

My source did not provide an estimated date for completion. Nor did the source discuss plans for moving Entergy’s transformer near the Exxon station at US59.

But still, this is progress.

Making Way for Surface Turn Lanes

The existing Entergy power poles need to move back to make way for two surface turn lanes that will parallel the bridge over the UP railroad tracks at Loop 494.

One of the two new westbound turn lanes will let traffic turn left onto 494 and the other will let it turn right. This is a TXDoT requirement.

As you can see from the overhead clutter, this is not going to be a simple job.
Entergy has dropped new poles every few feet for several blocks down Northpark.
Entergy power poles back beyond the orange stakes on the left.

The City of Houston issued Entergy an ultimatum to have its equipment out of the way by March 8. March 8 came and went without a sign of Entergy along Northpark. Now, almost a month later, we finally have some movement that could avert a costly legal battle that had the potential to shut the expansion project down.

This is good news. The presence of the power lines in the right of way has delayed construction considerably and forced contractors to take tasks out of sequence.

Union Pacific access issues have already been worked out. So, hopefully, construction should move faster now.

Elsewhere Along Northpark

Northbound turn lanes at 59 have reached their full width and are growing longer.

Outbound traffic was confined to one lane today, causing considerable delays.
Note freshly poured concrete being finished.

As soon as the new turn lanes are complete, traffic in the old lanes will be rerouted to them. Then contractors will repave the old lanes. That process should take three months according to LHRA. Westbound traffic should expect delays.

LHRA encourages commuters to take alternative routes.  For the next phase of work, the contractor will install new storm sewer pipes and inlets along with the new concrete roadway.

Russell Palmer Intersection Closed This Weekend

Farther east, contractors have already removed a pole mounted traffic signal at the Northpark/Russell Palmer Intersection. This weekend, they will rip up the intersection to extend the box culverts in the median. The crossover will close from 9pm Friday night, April 5, to 5am Monday morning, April 8, to make way for construction.

Looking W toward US59 across Russell Palmer along Northpark. The crossover will be ripped up this weekend to extend the culverts.

Traffic was backed up for more than a mile in each direction this afternoon because of multiple lane closures as you can see above.

Construction is never easy. Pack your patience. Plan on delays. And search for alternative routes for the duration.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 4/2/24

2408 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Northpark Expansion Update, Still No Sign of Entergy

In the last three weeks, the Northpark expansion project has made slow, but steady progress, despite the fact that Entergy still has not moved any power poles or its transformer. For the moment, contractors seem to be working around the absentee utility issues, which have lingered for four years.

The bulk of activity has focused on the two stormwater detention basins near US59; drainage between 59 and 494; and new northbound turn lanes at 59. In addition, contractors spliced in a section of culvert by Parkwood Baptist Church near Russell-Palmer Road.

A gap was caused by a conflict with an existing water line to the church. The water line was too close to the surface. Therefore, contractors could not place the culvert deep enough. Rerouting the water line became its own small construction project, requiring engineering diagrams, approvals, estimates, change orders, permits and city inspections.

Another Week, Another Turn Lane

Most progress this week could be seen at the entries.

Looking NE from over 59 and Northpark Drive. Note fresh concrete for two additional right-hand, outbound turn lanes.
Looking east. Photos taken Wednesday afternoon 3/27/24. Outbound traffic was backed up to Russell-Palmer Road.
Note fresh concrete pour and men smoothing it. Also note culvert and connectors being stockpiled for new storm sewers.
Farther east, we can see more prep work for the drainage that must be installed before work on the surface.

Rain Slows Basin Excavation

More than three inches of rain in the week before I took these shots seems to have slowed down excavation of the detention basins at the 59 entry.

Ponding water gives hint of what is to come. Looking N over south pond.
Looking E across north pond. Both retaining walls in the north pond are finished and the concrete is curing. Backfill is already completed behind the walls.
Looking S across Northpark at south pond.
Workers are still removing the wooden forms around the last retaining wall. Fill has not yet been placed behind the wall.

Work at Russell Palmer Scheduled

Lake Houston Redevelopment Authority/TIRZ 10 has posted a lane closure notice for the Russell-Palmer crossover between the east- and westbound lanes of Northpark from 9pm on Friday, April 5th to 5am on Monday, April 8th. That’s next weekend.

Crews will remove old pole-mounted traffic signals and replace them with wire-mounted signals. This will enable contractors to continue laying culvert toward the west. Right now the pole-mounted lights are in the center the road. That area will eventually be paved over.

Pole-mounted traffic signals at Russell Palmer will be removed to make way for extension of culvert.

Here is the 3-week lookahead schedule posted on March 21.

Entergy Still MIA

Entergy was first notified of conflicts with the expansion project in 2020. They still haven’t moved their equipment, such as this transformer. At this point, they have ignored a City of Houston ultimatum for three weeks. Entergy has not returned phone calls to clarify when it plans to take action.

Transformer at Exxon Station. The box that’s putting the whole expansion project in a box.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 3/29/24

2404 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

First Concrete Poured for Northpark Drive Expansion

Earlier this week, contractors poured the first concrete for Northpark Drive expansion. It was for the first of several new outbound lanes at US59.

Looking north across Northpark. US59 on left. Note fresh concrete for first of new through- and turn lanes. 3/15/24.

Crews are doing both surface and subgrade work, moving back east towards Chick-Fil-A.

Stormwater Retention Basin Progress

Elsewhere along Northpark, excavation work continued on the south pond. The twin ponds will double as decorative ponds and stormwater detention basins to handle extra runoff from the wider roadway.

Looking N across south retention pond on Friday afternoon 3/15/24.

Also, in the south pond, Texas Wall & Landscape is continuing work on the retaining walls.

Setting forms for additional concrete in second retaining wall in South Pond
Crews were also bringing in fill to place behind the recently completed large retaining wall on the north pond.

What to Expect Next

According to the Lake Houston Redevelopment Authority website, crews will continue to work on drainage down the middle of Northpark and along the north side of the road, expecially between 59 and 494.

Looking E at construction of drainage and new outbound lanes along Northpark.

Entergy Power Lines Still Not Moved

Farther east, you can see that Entergy power lines still have not moved. The photo below shows where the bridge over the railroad tracks will go. In the bottom right corner, the roadway will expand to 10 lanes. Six will bridge over the tracks. And four (two on each side) will carry surface traffic turning north and south onto Loop 494.

However, Entergy’s power lines are in the way of the extra lanes.

Looking E along Northpark from over UP railroad tracks.

The big question at this point is when Entergy will move its power lines. It also has not yet begun moving its transformer near the Exxon Station at 59. Entergy ignored a City of Houston deadline to complete moving its lines by March 8. After another 8 days, the company has not yet even begun the work. Nor have they offered the public an explanation why.

Unfortunately, weather forecasters predict this hurricane season will be especially active. And one of the main purposes of this project is to provide an all-weather evacuation route for 78,000 Kingwood residents.

For More Information

For more information about the project including Phase I, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 3/8/24

2391 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Entergy Ignores City Deadline to Move Northpark Power Lines

Today, Entergy missed yet another deadline in a long series of deadlines to move its power lines to make room for Northpark Drive expansion.

On February 6, the City of Houston sent a letter to Entergy, demanding that the company move its power lines out of the City’s right of way within 30 days. That would have given them until March 8 to comply. But as of today, March 9, 2024, not one of the poles had moved.

The City’s agent, Lake Houston Redevelopment Authority/TIRZ 10, first asked Entergy to move the poles four years ago. This is just another in a long line of disappointments that have delayed the Northpark Drive Expansion Project – driving up taxpayer costs, increasing flood risk, and snarling traffic.

Last month, Entergy refused to provide ReduceFlooding.com with a copy of its response to the City. And today, Entergy did not return a phone call explaining why the company ignored the City deadline.

Before/After Photos

Here’s how the north-side/west-bound expansion area near the UP tracks looked before the City sent its demand letter.

Entergy power poles in the way of Northpark expansion
Photo taken Jan. 13, 2024, before City sent letter to Entergy.

And here’s how the same area looked this morning. Not one pole has moved as a result of the City’s February 6 letter.

Photo taken around noon on March 9, more than 30 days after letter was sent. Nothing has moved.
Reverse angle. Looking E along Northpark at endless backups and poles still in original locations. Also taken March 9th.

As I took these photos Saturday near noon, traffic was backed up more than a mile!

Clash over Cash

In the past, Entergy asked for compensation to move its poles. But according to an LHRA spokesperson, compensation is not allowable under Texas law because the poles were in a City right of way and not covered by an easement. Thus, any payment would have constituted a “gift of public funds,” which the Texas Constitution prohibits

Entergy was, however, legally entitled to compensation for moving buried wires in an easement near the Exxon station at US59. Entergy had agreed to move them for $711,000 near Christmas last year. However…

Entergy still has not moved buried wires or a transformer near the Exxon station at US59.

…within days after the disagreement about payment for relocating the poles, Entergy’s asking price to move the underground wires mysteriously increased by half a million dollars. Simultaneously, their cost estimate went from line item to lump sum – without itemization. Since then, the asking price has increased another $200,000 without explanation.

Previous Communications with Entergy

City of Houston held Utility Coordination Meetings with Entergy on 10/8/20, 12/10/20, 01/14/21, 2/11/21, 3/11/21, 2/10/22, 3/10/22, and 4/14/22.

In addition, the City also emailed Entergy’s Utility Relocation consultant on 12/07/20, 06/21/21, 06/30/22, 07/22/22, 08/19/22, 09/20/22, 10/21/22, 01/11/23, 01/24/23, 03/03/23, 05/17/23, 07/19/23, 08/23/23, 10/16/23, 10/26/23, 12/01/23, and 12/13/24, 01/16/24.

I don’t care to speculate on the motives for Entergy’s lethargy. However, I’m pretty certain that if this goes to court, the entire project could be delayed years.

You can draw your own conclusions and point fingers where you will.

If there was ever any doubt, Entergy now knows that one of the main goals of Northpark Expansion is to provide an all-weather evacuation route for 78,000 Kingwood and Porter residents. Personally, I hate feeling like a pawn in Entergy’s game.

Posted by Bob Rehak on 3/9/24

2384 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.