City of Houston Re-evaluating Benefit-Cost Ratio on Lake Houston Gates Project Alternatives

According to minutes of the Coastal Water Authority (CWA) February 9 board meeting posted in March, work on the project to add more gates to Lake Houston was paused in January while the City of Houston updated the project’s benefit-cost ratio.

gates for Lake Houston and Conroe
Lake Houston and Lake Conroe gates side by side. Lake Conroe’s gates (right) can release water 15 times faster.

CWA Board Minutes Give High-Level Overview of Concerns, Status

Screen capture from CWA Feb. 9, 2022, minutes approved and posted in March.

Earlier, in December, the board learned that the project team was trying to get the benefit/cost ratio above 1.0, so benefits exceed costs.

Screen capture from CWA January 12, 2022, board minutes.

At that time, the CWA hoped to receive the updated BCR later in January. But it still hadn’t happened by the February board meeting.

Martin Says “September-ish” for BCR Report

City of Houston Mayor Pro Tem Dave Martin said he hopes to have the BRC report in a “September-ish” time frame. I asked him whether the Community Impact report was accurate when it said the project had been scaled back to 500 feet of crest gates as opposed to the original 1500 feet. He said “no,” and that the engineers were looking at multiple options. He also said “1.0 is incorrect as well,” but did not elaborate.

That leaves a lot of questions regarding this project.

History of Project

After Harvey, the Lake Houston Area Task Force identified adding additional gates to Lake Houston as one of three primary strategies to reduce flood risk in the Lake Houston Area. The idea: to equalize the discharge rates of the flood gates on Lake Houston and Lake Conroe. Conroe’s is 15X greater. That makes it difficult lower both lakes quickly in advance of approaching storms.

As a temporary strategy, the City and SJRA agreed on a temporary, seasonal lake lowering strategy to create more capacity in Lake Conroe until more gates could be added to Lake Houston. But the strategy met with significant pushback from Lake Conroe residents and lawmakers. The Lake Conroe Association even took the SJRA to court to stop it.

At various times, City representatives have discussed 10 and 6 additional tainter gates, plus 1500-, 1200-, and 1000-feet of crest gates. Engineers and City officials have repeatedly emphasized the need to balance costs, downstream impacts, and flood risk reduction.

Back in October 2020, the engineers calculated that the upstream influence of the dam ended at approximately Lake Houston Parkway. But they never explained why. It would seem that if the influence extended upstream to US59 when the lake is at its normal level, that the influence should extend at least that far in a flood. However…

BCR Not Based on Harvey Damage

Much of the damage to the Humble/Kingwood Area during Harvey happened upstream of the West Lake Houston Parkway Bridge. It included:

  • $60 Million to Kingwood College
  • $70 million to Kingwood High School
  • $50 million to Kingwood County Club
  • 283 homes in Barrington
  • 218 homes in Kingwood Lakes
  • 97 apartments in Kingwood Lakes
  • 110 homes in Kings Forest
  • 100% of businesses in Kingwood Town Center
  • 225 homes in Kingwood Greens
  • 30 homes in Deer Cove
  • 3 Homes in Deer Ridge Estates
  • 32 homes in Trailwood Village
  • An unknown number of homes in Forest Cove
  • 78 townhomes in Forest Cove
  • All of the Big Box stores along 59
  • Homes and business north of Deerbrook mall
  • 40% of all businesses in the Lake Houston Chamber
  • Humble ISD admin building
  • Destruction of US59 southbound lanes
  • Union Pacific Railroad Bridge

However, Black & Veatch does not base its benefit-cost ratio calculations on another Harvey. They’re basing it on 25- and 100-year storms. Almost all homes, businesses and infrastructure near the lake are already above those levels – at least based on pre-Atlas 14 standards. That may explain the difficulty and delays with benefit/cost ratio calculations and the multitude of scenarios examined.

Time, Uncertainty: More Factors to Consider in Cost and Risk Reduction

Each flood-risk reduction alternative would reduce lake levels by a different amount during a 100-year storm and therefore require its own BCR.

Other factors to consider: How much time do dam operators really need to lower Lake Houston? And how much uncertainty are they willing to live with?

Given the desire to preserve water, these are crucial considerations. If forecasters can reliably predict a need to lower the lake two days before a storm instead of one, operators may only need half the number of new gates. That could get the cost down to the point where the benefit-cost ratio needs to be.

But don’t forget another element of uncertainty: Atlas 14. FEMA has not yet approved the new flood maps based on the higher rainfall totals. Those could put more people in or closer to the floodplains. Below is the timetable for flood map updates currently posted on the MAAPnext website.

Timetable for flood map updates from MAAPnext.

Posted by Bob Rehak on 4/4/22 and updated on 4/5/22 with MAAPnext timetable

1679 Days since Hurricane Harvey

Reminder: Floodgate Meeting at Kingwood Community Center on Thursday, July 8

On Thursday, July 8, Mayor Pro Tem Dave Martin will host a pubic meeting to discuss the status of adding more floodgates to the Lake Houston Dam. Preliminary engineering finished earlier this year. In March, the Coastal Water Authority board approved Black & Veatch to begin final engineering.

Need for More Gates

The Lake Houston Area Task Force identified more and higher capacity floodgates as a key element in the area’s flood-mitigation strategy. The current gates have one-fifteenth the capacity of those at the Lake Conroe Dam. That makes it difficult to shed water from Lake Houston before people flood if Lake Conroe opens its gates as it did during Harvey.

During Harvey, Conroe released 79,000 cubic feet per second. That was one third of all the water coming down the West Fork between Humble and Kingwood. All by itself, that 79,000 CFS would have been the ninth largest flood in West Fork history. And that made the difference between flooding and not flooding for thousands of homes and businesses near the lake.

During Harvey, the peak flow over the spillway was five times the average flow over Niagra Falls. A wall of water 11 feet tall cascaded over the spillway above. Enough to fill NRG stadium in 3.5 minutes.

Lake Houston Dam During Harvey. The proposed crest gates would go in the far upper left of the spillway.

Floodgate Meeting Details

See the meeting details below.

Thursday, July 8, 2021
At the Kingwood Community Center (4102 Rustic Woods)
Doors Open 5:30 PM
Dredging Update Starts 5:45 PM
Gate Update Starts at 6 PM

Chief Recovery Officer, Stephen Costello, will provide a very brief update on Lake Houston Dredging operations at 5:45 p.m. before the Spillway Improvement Project program begins.

The program to discuss the Lake Houston Dam Spillway Improvement Project will start at 6:00 p.m. and conclude at 7:45 p.m. But don’t worry about sitting through a 2 hour meeting.

The main presentation by Black & Veatch, the project engineers, will be followed by a short Q&A session. The meeting will then transition into breakout sessions. Breakout tables will let residents engage with project management staff and engineers in small groups to ask more detailed questions.

Project Benefits

The Lake Houston Dam Spillway project will increase the outflow capacity of the Lake Houston Dam. The project proposes installing new crest gates in the existing uncontrolled spillway. This will allow for a rapid decrease of water levels in Lake Houston in advance of storm events to prevent or reduce upstream flooding. Engineers estimate the recommended alternative could help about 35,000 residents and 5,000 structures. It’s important for people to understand that if they flooded from streams or channels far from the lake during Harvey, this may not help them.

Funding

A Federal Emergency Management Agency (FEMA) Hazard Mitigation Grant Program provides $4.3 million for engineering and positions the city to receive another $42.7 million for construction.

Posted by Bob Rehak on 7/6/2021 based on info provided by Dave Martin’s Office

1407 Days since Hurricane Harvey

May 2021 Gate Project Update for Lake Houston Dam

In its March 10th board meeting, the Coastal Water Authority (CWA) accepted the recommendation of a preliminary engineering report to add one thousand feet of crest gates to the uncontrolled spillway portion the Lake Houston Dam. The additional release capacity would let operators shed water faster before, during or after major storms to reduce the risk of flooding.

At the March meeting, directors also approved $4.4 million to begin Phase II of the project. Phase II calls for Black & Veatch to proceed to final engineering of the gates and a coffer dam to protect the work area during construction.

Read the minutes of the March board meeting here. The discussion of the gates starts on page 4 under Item B.

This morning, at its May board meeting, directors received an update on the progress of Phase II work to date and plans for the remainder of the project.

Start of Phase II Engineering Approved in March

In the March meeting, CWA approved funds to begin Phase 2 of the engineering which includes the final design of the selected alternative by Black & Veatch. The selected alternative was “crest gates” constructed on the uncontrolled spillway portion of the dam on its west side. (See below.)

Looking NE at the Spillway of the Lake Houston Dam is in foreground. One thousand feet (about a third) of this spillway will be replaced with crest gates. Gates will be placed at the end closest to the camera position in the image above.

Dam operators can raise or lower crest gates from a bottom hinge, much like the lid on a piano. When in the up position, gates hold water back. When lowered, they release water.

During Harvey, the peak flow over the spillway was five times the average flow over Niagra Falls. A wall of water 11 feet tall cascaded over the spillway above. Enough to fill NRG stadium in 3.5 minutes.

Scope of Phase II Design Work

Also in March, CWA and Black & Veatch completed negotiation of the scope and fee for the final design. The key deliverables during Phase II will include:

  • Plans to modify the spillway to support the 1,000 linear feet of crest gates (in five 200-foot long sections)
  • Design of the cofferdam system to protect the work areas during construction
  • Preparation of a new gate operations plan for CWA Lake Houston Dam operators.

Director Douglas Walker moved to authorize the Executive Director to issue a contract amendment with Black & Veatch Inc. in the amount of $4,465,727.00 for “Phase 2 – Final Design of the Lake Houston Dam Spillway Improvement Project.” Director Giti Zarinkelk seconded the motion. The Motion carried unanimously.

May Update

In the May board meeting this morning, directors received an update on Phase II work to date and plans.

In April, the design team held a number of workshops and coordination meetings.

Black & Veatch also completed three weeks of field surveying of the existing spillway; that’s why CWA temporarily lowered Lake Houston during that period.

In other news, for next steps CWA will:

  • Submit the permit application to the US Army Corps of Engineers by the end of May.
  • Support City of Houston in a public outreach meeting scheduled for June 17. The public outreach meeting will coincide with the public comment period for the permit application. CWA expects permitting to take nine months, i.e., through March of 2022.
  • Complete final design by the end of September 2022.
Screen capture from portion of CWA Board meeting today shows status of Phase II Design work on the dam.

Next Steps

Does all this mean construction is assured? No. The Army Corps could reject the permit or FEMA could find some fault with the plans. But at least it shows progress. If all plans and permits are approved, construction dollars have already been committed by FEMA. Originally, construction was supposed to have been completed within three years from April 8, 2020. That now looks unlikely unless the City can obtain a deadline extension from FEMA..

Posted by Bob Rehak on 5/12/2021

1352 Days after Hurricane Harvey