Tag Archive for: construction progress

March Update on Humble ISD Ag Science, North Transportation Center Construction

When Humble ISD began clearing land for its new ag science and north transportation centers in Porter near Woodridge Village, flood-wary residents expressed concern. Woodridge Village had contributed to flooding Elm Grove and North Kingwood Forest twice in 2019 and residents feared additional clearing of forests would add to their problems. However, the contractors successfully built detention ponds and installed drainage before any major storms hit. No one has flooded yet due to these projects. A flyover of both facilities on 3/3/2021 showed the state of construction progress on both sites.

Ag Science Center

Humble ISD broke ground for its new seven-acre northern ag science facility last November. The contractor quickly finished clearing the site and building a detention pond. Now, work has started on the underground portion of the project – utilities, plumbing and drainage. Aerial photos taken last week show large amounts of pipe stockpiled near Ford Road. Photos also show concrete forms being staked out for building foundations. Humble ISD says the target opening for the new ag science center is still 2021.

Photo looking west shows relationship between Humble ISD Ag Science Center (foreground), Ford Road, North Kingwood Forest (left) and Woodridge Village (background). Note pipe being stockpiled near road.
Looking NNW, you can see trenches for pipe and forms for concrete.

When complete, this site will replace the ag barn facility at Deer Ridge Park in Kingwood. It flooded multiple times. Each time, students had to move their animals to safety. And one of the barns sustained structural damage. The purpose of this site: to improve safety.

North Transportation Center

Meanwhile, a quarter mile away, the North Transportation Center is taking its final shape. This project started several months before the new ag science center.

Contractors have poured the most of the concrete for building pads and parking lots. A large retention pond has partially filled with standing water. Two buildings have gone up and roofs are being put on. But the contractors have not yet “dried in” the buildings. They still have to install windows and doors before interior finish-work can begin.

Looking NE at Humble ISD North Transportation Center Construction Progress as of 3/3/2021.
Looking south at same site. Note the ag science center in the background at the top of the frame. Ford Road on right.

Target opening for this facility is also the 2021 school year. Humble ISD says the new transportation center will save $2 million per year in operating costs due to shorter routes. Currently, one transportation center in Humble serves the entire district. The center should also improve response times.

Humble ISD financed both projects with its 2018 bond program.

Last week, Harris County purchased more than two thirds of Woodridge Village for a major flood reduction project. Work on that should start soon. With that and the completion of these Humble ISD projects, nearby residents should sleep easier.

Posted by Bob Rehak on 3/7/2020

1286 Days since Hurricane Harvey and 535 since Imelda