Tag Archive for: Chris Mueller

Recommended Floodgates Could Release at Rate of Lake Conroe During Harvey

City of Houston Mayor Pro Tem Dave Martin’s office has supplied ReduceFlooding.com with the Black & Veatch Engineering report on the recommended alternative for adding floodgates to Lake Houston. One key finding immediately jumped out at me that wasn’t in Martin’s press release last week. The recommended gates would have a release capacity that virtually equals the highest release rate of Lake Conroe during Hurricane Harvey.

The Lake Conroe release rate during Harvey maxed out at 79,000 cubic feet per second (CFS).

The eleven tainter gates recommended by Black & Veatch would have a release rate of 78,700 CFS.

New Possibilities, More Certainty

That opens up a world of possibilities. For instance, the City could wait to start releasing water until it knew water was coming downstream from Harvey.

Said Martin, “Once constructed, we can release with a moments notice which gives us great opportunities to coordinate release protocols with the SJRA!!”

Previously, Public Works has been reluctant to release water in advance of a storm because the release rate of the existing gates is so small. They have to start lowering the lake so far in advance of storms that a storm can veer away before it gets here. If it does, that means water has been wasted.

The recommended floodgates should provide much more certainty for operators and avoid waste.

Key Elements of Recommendation

site of proposed gates for Lake Houston on east side of dam
Gates would be placed at the original channel for the San Jacinto River seen in foreground.

Other key elements of the recommendation include:

  • Locating the floodgates in the earthen eastern portion of the dam near the old channel of the San Jacinto River.
  • Creating baffles and a dissipation basin downstream from the new gates to break up the flow and reduce water velocity
  • “Outdenting” the gates (i.e., building them in front of the current dam)
  • A bridge between the two parts of the earthen dam
  • Using tainter gates, the same type used at Lake Conroe.
  • A 3.5 year construction schedule.

The last point means that if construction started in January, the earliest completion date would be mid-2026.

However, given the need to line up additional funding in the state legislature, 2027 is a more realistic date.

For a complete discussion of the project history, constraints, alternatives, recommended options, construction drawings, rationales, and costs, see the entire 28-page Black and Veatch Report by Chris Mueller, PhD, P.E.

Posted by Bob Rehak on 12/14/22 based on the Black & Veatch Report

1933 Days since Hurricane Harvey

Floodgate, Dredging Plans Unveiled

At one of the first large public meetings since Covid began, several hundred people crowded into the Kingwood Community Center last night. They came to see the City unveil floodgate and dredging plans for Lake Houston. Stephen Costello, PE, the City’s Chief Recovery Officer, addressed dredging. And Chris Mueller, PhD, PE, of engineering firm Black & Veatch discussed adding more floodgates to the Lake Houston Dam. Mayor Pro Tem Dave Martin coordinated the meeting.

To see both presentations, click here. Or see the summaries below.

Dredging: About Half Done

In late 2019, the Army Corps finished hydraulic dredging in the area south of the West Fork mouth bar. Then in early 2020, the City of Houston began mechanical dredging to extend the effort. In terms of the estimated dollars designated for dredging, the effort is about halfway done.

The first four rows on this chart are done or almost done. They total $114 million out of a projected total of $222 million.

The last two rows on the chart above are estimates because they depend on bids currently in progress and a long-range plan not yet complete. The need for a long-term plan and maintenance dredging were identified early on by the Army Corps so that any benefits of dredging were not immediately wiped out by future sedimentation.

Scope of Long-Range Dredging Plan Still in Development

A long-range dredging plan for Lake Houston is critical. We must understand where the sediment comes from, how fast it builds up, where it builds up, and the consequences of not removing it periodically.

The numbered dots in the photo above show channels south of the East and West Forks draining into Lake Houston where sediment can also build up.

Costello says the City is currently working with affected homeowner associations to discuss cost-sharing arrangements.

He also says that the City must identify a long-range site for depositing the spoils that is suitable for hydraulic dredging. He called the mechanical dredging now in progress “not sustainable.” Currently, the City is using Berry Madden’s property on the West Fork south of Kingwood’s River Grove Park to deposit the mechanical dredging spoils. That’s a long haul for barges on the East Fork.

Next Dredging Steps: Channel to East Fork and East Fork Itself

Contractors must next deepen the channel between the West and East Forks of the San Jacinto to move dredging equipment and spoils back and forth (see below).

Current location of dredging is near yellow dot.

From there, dredgers will move slightly north of where Luce Bayou (far right) enters the East Fork and begin dredging the East Fork mouth bar. See large circle above. The map shows that area grew shallower by up to nine feet between 2011 and 2018. Imelda, in September 2019, made it grow even shallower. Note the fresh deposits of sand in the photo below now poking up above the water.

Growth of East Fork Mouth Bar after Imelda in September 2019. Photo taken in November 2019.

Additional Floodgates for Lake Houston Dam

Chris Mueller of Black & Veatch then discussed the reasons for adding additional floodgates to Lake Houston, preliminary engineering findings, and an implementation schedule.

The primary objective: to increase the outflow capacity of the dam to reduce the risk of future flooding. However, he emphasized that reducing the risk for people upstream of the dam cannot have an adverse impact on people below it. See below.

He emphasized that Lake Houston is, first and foremost, a drinking water reservoir. He also emphasized that the dam is almost seventy years old and near the end of its useful life. Significant safety issues exist in working with such old concrete.

Calculating the Benefit/Cost Ratio of Additional Floodgates

Mueller then explained how FEMA calculates the benefit/cost ratio of additional floodgates.

  • On the benefit side, it considers: the reduction in water surface level; how many buildings and streets that will prevent from flooding; reduced societal impacts; and reduced impacts to business revenues. These are primarily damage costs avoided.
  • On the cost side of the equation, FEMA factors in construction costs and annual operation and maintenance costs.

To win project approval, the City must show that the benefits of additional floodgates exceed the costs in a 100-year storm, similar to Imelda. Such a storm elevates the lake 10 feet.

The peak inflow to Lake Houston in a 100-year storm: 286,000 cubic feet per second (CFS), enough to fill the Astrodome in 3 minutes! However, during Harvey, SJRA estimated the peak inflow at 400,000 cfs.

Proposed Alternative Produces 11-Inch Benefit Nearest Dam

A hydrologic and hydraulic analysis conducted by Black & Veatch will help prove up the benefit/cost analysis. The San Jacinto Watershed (including Buffalo Bayou) includes flow from eight counties.

In evaluating about ten alternatives for adding floodgates, Black & Veatch considered both cost and non-cost factors listed below.

The company’s first choice was to install additional gates on the earthen portion of the dam on the east side. But environmental considerations there would have delayed the project by a decade or more.

So they decided to recommend a 1,000 feet of crest gates on the west side of the spillway instead. See example of crest gates in operation below.

An air bladder near a bottom hinge raises or lowers the floodgates to let water in/out

Such gates would increase the discharge capacity to 45,000 cfs, more than four times the current capacity of 10,000 cfs. That’s still only about a third of the discharge capacity of the floodgates on Lake Conroe. But according to Martin, that would still be enough to lower the level of the lake 4 feet in 24 hours.

However, before floodgate construction can begin, engineers must evaluate:

  • Downstream impacts and how to mitigate them
  • Impact to the stability of the existing concrete dam

Back in the 1950s when the Lake Houston dam was built, engineers did not use rebar. So this will be a delicate operation. Contractors must cut 6 feet into the existing spillway; cap the remaining concrete with a slab; and install the crest gates on top of the slab.

Black & Veatch must also develop an operations protocol for new floodgates that maximizes upstream benefits and limits downstream impacts. Mueller shared this schedule with attendees.

Best-Case Project Timeline Shows Completion in 2024

Schedule as of 7/8/2021. Detailed engineering could take another year.

A best-case scenario shows construction starting at the end of 2022 and finishing before the start of hurricane season in 2024. So, at least three more hurricane seasons to get through before seeing any benefit from additional gates.

Posted by Bob Rehak on 7/9/2021

1410 Days since Hurricane Harvey