Despite investigations by local, county and state authorities into construction practices at the Laurel Springs RV Resort near Lakewood Cove, contractors seem to have stepped up the pace of construction. They’ve also launched a major cleanup effort around the detention pond. Contractors triggered a cease-and-desist letter from the County Attorney, with the threat of a lawsuit, after it became apparent the developer was emptying its stormwater into Harris County Precinct 4’s Edgewater Park contrary to permits and approved plans. Contractors also apparently cut down a wide swath of trees in the northern part of the park.

Photos Showing Construction Activity Since Last Friday

Looking west toward Sorters-McClellan Bridge over 59. Edgewater Park on left. RV Resort on right. Silt fence at the base of the pond corresponds to approximate southern boundary of RV Resort on survey. Taken 2/24/22.
Looking south along Laurel Springs Lane at freshly poured concrete at entrance. Taken 2/24. This afternoon (2/25), trucks were pouring more concrete.
Pipes being laid in northern part of RV Resort. Note water still ponding from rain in early January. Soil reports in the site’s stormwater pollution prevention plan claimed the soil was sandy loam which would have absorbed the rain by now.
Still no pipe from the corner of the detention pond leading to the pump housing in the round white concrete housing at top of frame. 2/23/22.

The detention pond was to have drained into the Lakewood Cove storm sewer system with the aid of pumps. But there’s no inlet yet at the pond.

Looking east toward Laurel Springs on 2/19/22.
Plans approved by City of Houston for pumping stormwater in detention pond into Lakewood Cove’s storm sewer system.
Contractors pulling up tree debris from below detention pond. 2/18/22. Looking SW.
Looking south toward Edgewater Park. Contractors initially piled the debris on the western (right) wall of detention pond, but ran out of room. They then started hauling it round to northern edge of pond where trucks are carting it away.

Investigations Still in Progress

Neither the County, City, nor Texas Commission on Environmental Quality would comment on the status of their investigations this week except to say that they are still ongoing. According to the Harris County District Clerk’s website, Harris County has not yet filed a lawsuit against the developer.

Overall, the developer appears to be cleaning up its act. But as you can see in the first shot, they seem to have made a significant and serious intrusion on Edgewater Park.

Posted by Bob Rehak on 2/25/22

1641 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.