Where Flood-Bond Spending Is Going, When New Flood Maps Will Be Released

On the Harris County Commissioner’s Court agenda for today are two Harris County Flood Control District (HCFCD) “transmittals.” One will update commissioners on flood-bond spending to date. The other will update commissioners on the progress of new flood maps (the MAAPnext program). They are items 269 and 270 on today’s agenda.

Transmittals are reports by departments. Commissioners don’t usually discuss them unless one of the commissioners wishes to make comments for some reason. So, I’m calling them to your attention here.

Flood-Mitigation Spending Through Third Quarter Reaches $865 Million

About half of the $865 million spent on flood mitigation since voters passed the bond in 2018 has come from bond funds. The rest has come from grants and local partnerships. See pie chart below on left.

The left pie chart underscores the importance of partnership funding.

The map below shows where flood-bond spending has occurred.

Flood-mitigation spending by watershed since approval of flood-bond in 2018.

The winner in the $weep$take$: HCFCD spent almost $154 million on Brays Bayou.

Other leading watersheds (rounded to nearest million) in flood-bond spending included:

  • $81 million in Addicks Reservoir
  • $76 million on Greens Bayou
  • $76 million on Cypress Creek
  • $50 million on Little Cypress Creek
  • $46 million on White Oak Bayou
  • $32 million on Clear Creek

With a few exceptions, this spending reflects the influence of the Harris County Flood-Bond Equity Prioritization Framework implemented in 2019. That framework gives highest priority to low- to middle-income watersheds with a high social-vulnerability index. Thus, tiny Halls Bayou has received more assistance than the largest watershed in the county – the San Jacinto River. And Brays Bayou has received almost 11 times more assistance than Buffalo Bayou.

Two notable exceptions are:

  • Vince Bayou which is almost totally inside the City of Pasadena and is therefore primarily Pasadena’s responsibility.
  • Little Cypress Creek which is part of HCFCD’s experimental Frontier Program. The Frontier Program aims to prevent future flooding by buying up land on the cheap before it’s developed. HCFCD then sells detention basin capacity to developers to help make back its investment.

Other Insights Gained from Report

  • Most projects are ahead of schedule and on budget. Good news!
  • More than half of buyouts have been completed and enough funding apparently remains to complete the rest.
  • Progress continues on the $124 million FEDERAL Flood Damage Reduction project on White Oak Bayou, where six stormwater detention basins will hold almost a billion gallons of stormwater. That’s equivalent to about a foot of stormwater falling over almost 5 square miles.
  • No actual projects in the Kingwood Area have begun construction yet. However, the Excavation and Removal Project on Woodridge Village could soon begin.

Additional maps in the full report show:

  • Dollars funded to date by watershed (Note, for instance, another $47 million in funding already committed to Brays).
  • Active Maintenance projects
  • Active Capital projects

Also, a massive GANNT chart shows the stages of every project in every watershed and county-wide projects.

Check out the full report here.

Controversy over Previous Version of Report

An earlier version of this report generated some controversy. People in some watersheds didn’t believe the reported expenditures. Members of the Northeast Action Collective questioned whether any projects had started in their watersheds. They demanded immediate cancellation of projects in Kingwood and transfer of Kingwood’s funds, so that projects in Halls and Greens Bayou could start immediately.

That’s, in part, why I wrote “How to Find and Verify Flood-Related Information: Part I.” Flood-mitigation projects are hard to spot from the ground. Construction almost always happens out of sight behind tall fences and dense tree lines. After construction, the projects are often disguised as parks. For those who doubt, I recommend confirming the existence of projects from the air.

I haven’t confirmed every project in the county, but I have spot-checked many. And I have yet to find discrepancies between what HCFCD reports and what I can see from the air.

C-25, a Halls Bayou Detention pond now under construction by HCFCD
C-25, a Halls Bayou Detention pond now under construction by HCFCD. The bayou runs through the trees in the foreground.
flood detention basin
New basin at Hopper and US59 on a tributary of Halls Bayou.
Lauder Detention Basin on Greens Bayou as of 10/12/2021
Lauder Detention Basin on Greens Bayou as of 10/12/2021. Phase One of a two-phase project is nearly complete.
Cutten Road detention basin on Greens Bayou continues its relentless expansion.
Phase 2 Aldine Westfield Basin
Phase 1 of the Greens Bayou Aldine-Westfield Basin on left is complete. Phase 2 on right is now beginning.

For more information that includes watershed spending data before the flood-bond, check out the funding page.

MAAPnext Effort About to Be Turned Over to FEMA

Harris County Flood Control (HCFCD) estimates it has completed 86% of its part of the flood-map updates. HCFCD will deliver drafts of the new maps to FEMA in January for review and kick off a campaign of public meetings at the same time. The public will see draft maps in February. A public comment period of 90 days will follow. And FEMA hopes to release preliminary flood insurance insurance rate maps by mid-year next year.

I have had a peek at the new maps and reports. And I must say, the effort should result in a dramatic leap forward in flood-risk understanding. Individualized reports will inform homeowners of their flood risks from a variety of different sources, including street flooding. The prototype of the website is very user friendly.

After receiving preliminary maps from HCFCD, it typically takes FEMA another 18-24 months to release final, official flood maps. That gives affected property owners time to comment and appeal. The process looks like this.

MAAPnext milestones as of the end of 2021.

Posted by Bob Rehak on 11/30/2021

1554 Days since Hurricane Harvey