HCFCD Issues Flood Bond Update as of March 30, 2021

In the March 30, 2021 Harris County Commissioner’s Court Meeting, Harris County Flood Control District (HCFCD) gave a Flood Bond update. Here’s where projects in the 2018 Flood Bond program stand.

Overview

In the 30 months since the bond was approved by Harris County voters, the Harris County Flood Control District has used bond funds to:

  • Accept 25 grants totaling approximately $960 million with Bond funds providing around $259 million in local matching funds
  • Execute 326 engineering agreements totaling $241 million
  • Award 39 construction agreements totaling $296 million
  • Procure 19 staff augmentation agreements providing 113 contract staff members
  • Acquire nearly 340 properties at a value over $208 million for construction projects, floodplain preservation, and wetland mitigation banks
  • Make $115 million available to the Office of the County Engineer to manage and construct drainage improvements in nearly 100 subdivisions across Harris County
  • Conduct 140 community engagement meetings with over 11,413 attendees
  • Complete nearly 630 home buyouts at a value over $130 million with over 680 additional in process for a buyout (since Hurricane Harvey)
  • Complete over $125 million repair program to address damages to District infrastructure caused by Hurricane Harvey

19 Projects Completed, 372 Underway

The flood bond update shows that of the 19 projects completed so far, investigations, analyses and studies comprised 15.

Altogether there are 372 individual HCFCD projects in progress related to the Bond Program. The table below shows the stages of those projects.

88% of all projects identified in the flood bond are currently underway and at some state of completion.

Only 21 Projects Not Yet Started

Only 21 Bond projects have not yet started. They are all in the fourth quartile of the bond prioritization framework and will begin between July 2021 and March 2022. Of those, two are in the San Jacinto watershed: CI-61 (East Fork, West Fork, and Lake Houston Dredging) and F-15 (General Drainage Improvements near Atascocita).

Dredging included a $10 million match with estimated partner funds of $40 million.

FEMA/Army Corps, TWDB and City of Houston funds have covered dredging in the river to date.

Status of Lake Houston Area Projects

Other projects in the Lake Houston Area at least partially underway.

Luce Bayou and Huffman

Project underway include right-of-way acquisition, design and construction of general drainage improvements in the Luce Bayou Watershed and near Huffman (total $20 million). Luce Bayou right-of-way acquisition and floodplain preservation ($10 million) has also started.

Gates on Lake Houston Dam

Design and construction of additional gates on Lake Houston ($20 million) is nearing completion of the design phase. The City of Houston has taken the lead on that project but has made no announcements on it recently.

Other Projects Lake Houston Area Partially Underway
  • The San Jacinto Watershed Study ($625,000)
  • Funding for future partnership projects based on the SJR watershed study ($18.75 million)
  • Investigation of potential detention sites around the Glendale Dredge site in Partnership with the City of Houston ($50,000)
  • Conveyance improvements along Panther Creek ($10 million)
  • General drainage improvements east of Lake Houston ($10 million)
  • General Drainage Improvements near Kingwood ($10 million)

One Third of Projects Now Past Design Phase

One third of all projects have already begin work outside.

Ellis Not Content with 40% of Construction Going into Two Bayous in His Precinct

40% of all projects under construction are in Greens and Halls Bayou Watersheds, the two Precinct One Commissioner Rodney Ellis cares most about. He wants to slow down projects in other areas to focus more on projects in his area.

For a discussion of how the meeting went, check back tomorrow.