Army Corps Updates West Fork Dredging Progress

The US Army Corps of Engineers has just released a graphic that updates the Lake Houston Community on West Fork dredging progress. With a little more than two months to go before the scheduled completion of the project, about two thirds of the work has been completed. That’s a visual estimate, not one based on volume of sand removed.

The clock started ticking on this project on July 15, 2018. The contract called for completion in 270 days or about mid-April. However, contractors encountered three back-to-back-to-back floods in December and January that set them back. The Corps’ last scheduled completion date was at the end of April.

The dredging progress may be slightly behind schedule, even given the addition of the “weather days.” However, contractors hope to make up the time as weather improves.

Work to date shown in solid colors. Unfinished work shown as empty boxes. Expected completion date is end of April.

To download a high-resolution version of this progress map, click here.

Artwork courtesy of the U.S. Army Corps of Engineers.